Valid until 27 Feb 2025 Residential/Group Housing project

UMA GREENS

By SHIV SHAKTI DEVELOPERS

RG-GJ-85841 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07158/180620 · Last updated on GujRERA portal: 15 Oct 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Feb 2025Possession promisedno revision filed
64 of 72Construction stages doneacross 8 buildings; furthest along: Stilt Floor, 0%
1 of 202Units unsoldnot recorded sold or booked
Jump to the 48 documents Report an error

UMA GREENS is a Residential/Group Housing project by SHIV SHAKTI DEVELOPERS in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07158/180620 on 18 Jun 2020. Possession is promised by 27 Feb 2025. 201 of the 202 units on this registration are recorded sold or booked, and 64 of 72 construction stages are filed complete.

At a glance

Project

  • NameUMA GREENS
  • TypeResidential/Group Housing
  • Location
    • Survey No. 267
    • FP No 79
    • TP 22
    • Kudasan
    • Gandhinagar
    • Kudasan
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07158/180620
  • ReraGenie IDRG-GJ-85841

Builder

  • NameSHIV SHAKTI DEVELOPERS
  • Entity typePARTNERSHIP FIRM
  • Other registrations3 more →
  • Past their filed date3

Key dates

this monthRegisteredJun 2020PromisedFeb 2025

Key facts

Registration and timeline

  • StatusValid until 27 Feb 2025
  • Registered on18 Jun 2020
  • Promised completion27 Feb 2025
  • Revised completionNone
  • Buildings8 building records
  • Documents filed48 files

Current status

100%201 of 202 units booked
100.0%Of the estimated cost spent so far

Figures as on 15 Oct 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building A---28028
Building B---28028
Building C---12012
Building D---26026
Building E---26026
Building F---26026
Building G---28028
Building H---28028

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building8

As on 15 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

64 of 72 construction stages are filed complete across 8 buildings. The stage furthest along is Stilt Floor, at 0%.

Building A89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building B89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building C89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building D89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building E89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building F89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building G89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%
Building H89%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 15 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsYes100%
Treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Fire fightingYes100%
Drinking water facilitiesNoNot applicable
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area8,705 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 24.82 cr
Cost incurredRs 24.82 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Building ANARs 3.10 crRs 3.10 cr
Building BNARs 3.10 crRs 3.10 cr
Building CNARs 3.10 crRs 3.10 cr
Building DNARs 3.10 crRs 3.10 cr
Building ENARs 3.10 crRs 3.10 cr
Building FNARs 3.10 crRs 3.10 cr
Building GNARs 3.10 crRs 3.10 cr
Building HNARs 3.10 crRs 3.10 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHEMANT MEHTA
EngineerBRIJESH J KANSARA

Documents filed48

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA07158/180620 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)15 Oct 2024
Engineer's certificate annexure15 Oct 2024
Accountant's certificate (Form 3)15 Oct 2024
Architect's certificate (Form 1)5 Oct 2024
Site photograph, Building A5 Oct 2024
Site photograph, Building B5 Oct 2024
Site photograph, Building C5 Oct 2024
Site photograph, Building D5 Oct 2024
Site photograph, Building E5 Oct 2024
Site photograph, Building F5 Oct 2024
Site photograph, Building G5 Oct 2024
Site photograph, Building H5 Oct 2024
RERA registration certificate18 Jun 2020
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

100%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep UMA GREENS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Kudasan1,600+ in Gandhinagar

2 kmUMA GREENSOther 260Dot size: filed unitsN

Filed coordinates, straight-line distance. 260 registered projects within 2 km.

Builder: SHIV SHAKTI DEVELOPERS

SHIV SHAKTI DEVELOPERS has 4 registrations on GujRERA, including SHIV SHAKTI RESIDENCY and UMA GREENS. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if UMA GREENS is delayed beyond 27 Feb 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of UMA GREENS?

The registered promoter entity is SHIV SHAKTI DEVELOPERS, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in UMA GREENS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at UMA GREENS?

The professionals named in the filing: Architect: HEMANT MEHTA; Engineer: BRIJESH J KANSARA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UMA GREENS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UMA GREENS. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UMA GREENS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.