UDAAN ARIA

By Udaan Builders and Developers

RG-MH-26729 · RERA P52000008827 · Last updated on MahaRERA portal: 4 Apr 2025

Source: official MahaRERA filing

Red flags

  • 11 complaints at MahaRERA
  • Completion date moved by 65 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 65 months from the original
33 of 77Construction stages doneacross 7 buildings; furthest along: Staircases, 90%
11Complaints at MahaRERAon this registration
Jump to the 146 documents Report an error

UDAAN ARIA is a Others project by Udaan Builders and Developers in Raigarh, Maharashtra, registered with MahaRERA as P52000008827 on 19 Aug 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 65 months from the original filing. 11 complaints are on record with the regulator.

At a glance

Project

  • NameUDAAN ARIA
  • TypeOthers
  • Location
    • Chinchavali Fatak
    • Near Bhivpuri Railway Station
    • Chinchawali
    • Karjat
    • Raigarh
    • 410201
  • Pincode410201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000008827
  • ReraGenie IDRG-MH-26729

Builder

  • NameUdaan Builders and Developers
  • Entity typePartnership
  • PartnerVilasrao Abasao Kengar
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJul 2022Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Aug 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 31 Jul 2022)
  • Buildings7 building records
  • Documents filed146 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A TYPE 01NA80000
C TYPE 02 Wing ANA80000
C TYPE 02 Wing BNA80000
D TYPE 3NA80000
B TYPE 04NA80000
TEMPLENA10000
CLUB HOUSENA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 4 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

33 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Staircases, at 90%.

A TYPE 0185%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%
C TYPE 02 Wing A73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C TYPE 02 Wing B77%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
D TYPE 369%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises45%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B TYPE 0447%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
TEMPLE0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
CLUB HOUSE88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities16

As on 4 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes65%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
Club House and Swimming PoolYes100%

Parking filed76

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots76
Closed/Covered6
Open Space70
BuildingClosed/CoveredOpen SpaceTotal
A TYPE 0101414
C TYPE 02 Wing A01414
C TYPE 02 Wing B01414
D TYPE 301414
B TYPE 0461420

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,310 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI15506.09
Proposed, not sanctioned7,367 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 12 GROUND FLOOR SECTOR 24 VASHI NAVI MUMBAI 400705

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSTRUCTILS CONSULTANTS PVT LTD
ArchitectGirish Thakare
EngineerM/s. Agharkar Consultants
Chartered AccountantRSL AND CO
Chartered AccountantJ B Patel and Associates
PartnerRole in project
Udaan Builders and Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000017301Jul 2022 → Jul 2024

Reason as filed by the promoterI am writing to formally request an extension for the completion of the project "Udaan Aria" (MahaRERA No. P52000008827). We applied for 5th floor Commencement Certificate permission in August 2018 but we received the said permission in November 2022 due to Covid Lockdown & Other Technical Reasons. Also, We have not gotten consent from Allottes because of non-cooperation from existing customers.

EXT52000012368Jul 2022 → Jul 2023

Reason as filed by the promoterWe have registered our project "Udaan Aria" on MahaRERA portal on 19/08/2017 and it was committed till 31/07/2022 (After extension given by MahaRERA as per Order No: - 2l/202l) but due to covid 19 pandemic we had unable to complete the said project within the time. So we request you to extend our period of completion of the project up to 31/07/2023.

EXT52000025392Jul 2022 → Dec 2027

Reason as filed by the promoterat present construction work of the said project is currently on hold due to factors such as changes in the market scenario, the COVID-19 pandemic, unavailability of labor, material shortages, and insufficient funds. Consequently, the project’s construction remains pending. Therefore, we respectfully request an extension of the project deadline until 31/12/2027

Complaints filed with MahaRERA11

Case no.ComplainantRespondentFiled
CC006000000397082Amarjit Singh SethiUdaan builders & Developers14/08/2023
CC006000000397084Amarjit Singh SethiUdaan Builders & Developers14/08/2023
CC006000000397481KRITHIKA HARESH SHARMAM/S UDAAM BUILDERS AND DEVELOPERS13/09/2023
CC006000000408228Sujata Krishna GaikwadM/s. Udaan Builder and Developers17/12/2023
CC006000000500474Priya DsilvaUdaan builders and developers15/05/2024
CC12500464SUNITA SUNIL RAJESHIRKEUdaan Builders and Developers11/02/2025
CC12500773PRAKASH SAMIR ROUTUdaan Builders and Developers07/03/2025
CC12501915Andrea Dsouza DsouzaUdaan Builders and Developers11/06/2025
CC12502223KRITHIKA HARESH SHARMAUdaan Builders and Developers04/07/2025
CC12502686Dnyanesh Sitaram GelyeUdaan Builders and Developers01/08/2025
CC12503578NITIN HARISHCHANDRA THAKURUdaan Builders and Developers08/10/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed146

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 146 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: 1.pdf4 Apr 2025
Building plan approvalFile: 2.pdf4 Apr 2025
Building plan approvalFile: 3.pdf4 Apr 2025
Building plan approvalFile: 4.pdf4 Apr 2025
Building plan approvalFile: 5.pdf4 Apr 2025
Building plan approvalFile: 6.pdf4 Apr 2025
Building plan approvalFile: 7.pdf4 Apr 2025
Copy of Layout Approval (in case of layout)File: 1.pdf4 Apr 2025
Declaration in FORM BFile: form b.pdf4 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: CC 2022_compressed.pdf4 Apr 2025
Building Plan Approval (IOD)File: 2.pdf4 Apr 2025
Building Plan Approval (IOD)File: 3.pdf4 Apr 2025
Building Plan Approval (IOD)File: 4.pdf4 Apr 2025
Building Plan Approval (IOD)File: 5.pdf4 Apr 2025
Building Plan Approval (IOD)File: 6.pdf4 Apr 2025
Building Plan Approval (IOD)File: 7.pdf4 Apr 2025
CERSAI detailsFile: CERSAI DECLARATION.pdf4 Apr 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of Separate Bank Account.pdf4 Apr 2025
Other - TechnicalFile: ANNEXURE A DECLARATION CUM UNDERTAKING.pdf4 Apr 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: real estate.pdf4 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30062024.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30122024.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30092024.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30062024.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30122023.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30062023.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30122022.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30092022.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30062022.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30062021.pdf3 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 30032021.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30092021.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30122024.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30092024.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30032024.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30062024.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30122023.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30092024.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30062023.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30122022.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30092022.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30062022.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30122021.pdf3 Apr 2025
Certificates of CA (Form 3)File: 30062021.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30092024.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30122022.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30122023.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30120224.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 30062023.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30122021.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30122024.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30062024.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30032024.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30122023.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30122022.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30092023.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30062023.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30062021.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: 30032021.pdf3 Apr 2025
Proforma of Agreement for saleFile: GetUserDocumentFileContent.pdf15 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD 14112024 Udaan Aria_11zon.pdf14 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UBD Form 13032024.pdf13 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: UBD Form 13032024.pdf13 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UBD form 2- 30-03-2024_11zon.pdf13 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UBD Form 13032024.pdf13 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: UBD Form 2 30-06-2024_11zon.pdf13 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf13 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 Signed(Final).pdf13 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Udaan Aria FY 23-24.pdf7 Nov 2024
Certificates of CA (Form 3)File: Form-3 Udaan.pdf5 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf27 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf27 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold, Unsold Merged_compressed.pdf27 Jan 2024
Certificates of CA (Form 3)File: DECLARATION.pdf27 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked Inventory 31032023 FINAL.pdf23 Aug 2023
Certificates of CA (Form 3)File: FORM 3 UDAAN ARIA MAR 2023 Signed Upload.pdf23 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A (2019-20).pdf21 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM- 2A FY 2021-22.pdf10 Aug 2023
Declaration in FORM BFile: 13 Annexure 12.pdf9 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf9 Aug 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Udaan AvenueP52000012197NERAL, Raigarh170Sep 2017CompletedJul 2022Late, Jul 2023

How this compares with Raigarh

20%of Raigarh projects moved their completion datethis one moved by 65 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep UDAAN ARIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Bhivpuri Railway Station5,900+ in Raigarh

2 kmUDAAN ARIACompleted 17Lapsed / revoked 17Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: Udaan Builders and Developers

Udaan Builders and Developers has 1 registration on MahaRERA, including UDAAN ARIA. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if UDAAN ARIA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of UDAAN ARIA?

The registered promoter entity is Udaan Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in UDAAN ARIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against UDAAN ARIA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for UDAAN ARIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at UDAAN ARIA?

The professionals named in the filing: Architect: STRUCTILS CONSULTANTS PVT LTD; Architect: Girish Thakare; Engineer: M/s. Agharkar Consultants; Chartered Accountant: RSL AND CO; Chartered Accountant: J B Patel and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in UDAAN ARIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About UDAAN ARIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save UDAAN ARIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.