ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / TULSI PARADISE

Valid until 31 Mar 2027 Residential/Group Housing project

TULSI PARADISE

By TULSI PARADISE

RG-GJ-81340 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12307/250923 · Last updated on GujRERA portal: 21 Jun 2024

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
Mar 2027Possession promisedno revision filed
12 of 27Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 96%
96 of 120Units unsoldnot recorded sold or booked
Jump to the 36 documents Report an error

TULSI PARADISE is a Residential/Group Housing project by TULSI PARADISE in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12307/250923 on 25 Sep 2023. Possession is promised by 31 Mar 2027. 24 of the 120 units on this registration are recorded sold or booked, and 12 of 27 construction stages are filed complete.

At a glance

Project

  • NameTULSI PARADISE
  • TypeResidential/Group Housing
  • Location
    • B/h Parshwanath Metro city
    • Nr Shyam Elegance
    • T.P No. 46
    • S P Ring Road
    • Sughad
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12307/250923
  • ReraGenie IDRG-GJ-81340

Builder

  • NameTULSI PARADISE
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2023PromisedMar 2027

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2027
  • Registered on25 Sep 2023
  • Promised completion31 Mar 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed36 files

Current status

20%24 of 120 units booked
41.7%Of the estimated cost spent so far

Figures as on 21 Jun 2024, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B---13013
A---67067
C---40040

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building3

As on 21 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

12 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 96%.

B87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor92%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing92%
A86%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor96%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats81%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%
C87%
ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats85%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing20%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing90%

Progress on shared amenities23

As on 21 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes95%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsYes100%
Landscaping and tree plantingYes65%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterYes0%
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%
Compound wallYes100%
Plinth protectionYes100%
Water tankYes100%
Other requirementsNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,037 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 36.00 cr
Cost incurredRs 15.00 cr
Spent of the estimate41.67%
BuildingWingEstimatedIncurred
ANARs 12.00 crRs 5.00 cr
BNARs 12.00 crRs 5.00 cr
CNARs 12.00 crRs 5.00 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSPLINE DESIGN(Devang Vaghela)
EngineerHNS Design Studio

Documents filed36

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12307/250923 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer's certificate (Form 2)21 Jun 2024
Engineer's certificate annexure21 Jun 2024
RERA registration certificate25 Sep 2023
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Property card-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

20%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep TULSI PARADISE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmTULSI PARADISEOther 53Dot size: filed unitsN

Filed coordinates, straight-line distance. 53 registered projects within 2 km.

Builder: TULSI PARADISE

TULSI PARADISE has 1 registration on GujRERA, including TULSI PARADISE. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if TULSI PARADISE is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of TULSI PARADISE?

The registered promoter entity is TULSI PARADISE, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in TULSI PARADISE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TULSI PARADISE?

The professionals named in the filing: Architect: SPLINE DESIGN(Devang Vaghela); Engineer: HNS Design Studio. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TULSI PARADISE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TULSI PARADISE. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TULSI PARADISE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.