Home / Browse projects / Bengaluru Rural, Karnataka / TRIAXIS SPLENDOUR +

Registration approved No litigation declared Residential/Group Housing project

TRIAXIS SPLENDOUR +

By M s Triaxis Infra Projects

RG-KA-03158 · RERA PRM/KA/RERA/1250/304/PR/210312/004001 · Last updated on RERA Karnataka portal: 13 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Completion date moved by 36 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
Dec 2026Possession promisedmoved 36 months from the original
18 of 18Construction stages doneevery applicable stage filed complete
45 of 104Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 95 documents Report an error

TRIAXIS SPLENDOUR + is a Residential/Group Housing project by M s Triaxis Infra Projects in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/210312/004001 on 12 Mar 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 59 of the 104 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameTRIAXIS SPLENDOUR +
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1250/304/PR/210312/004001
  • ReraGenie IDRG-KA-03158

Builder

  • NameM s Triaxis Infra Projects
  • Entity typePartnership Firm
  • Authorized SignatorySomashekar Reddy J K
  • OthersChenna Reddy G, G V S Reddy, Srinivasulu Reddy M

Key dates

this monthRegisteredMar 2021First promiseDec 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on12 Mar 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed95 files

Current status

57%59 of 104 units booked
5.8%Of the estimated cost spent so far

Figures as on 13 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Triaxis Splendor+---1040104

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 13 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsNoNot applicable
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesNoNot applicable
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesYes100%
Storm water drainsYes100%
Use of renewable energyNoNot applicable
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes97%
Community HallYes97%
Outdoor Sports facilityYes100%
Indoor Sports facilityNoNot applicable
Swimming PoolYes100%
GymYes97%
ParksNoNot applicable
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesYes100%
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,933 sq m
Named landowners2
LandownerVillageDistrict
M K Manjunath--
M K Hemanth Kumar--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 15.60 cr
Cost incurredRs 90.91 lakh
Spent of the estimate5.83%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 15.60 crRs 90.91 lakh

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAjay Sharma
EngineerMunish Sharma

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EX/PRM/KA/RERA/1250/304/PR/240520/004001Dec 2023 → Dec 2024

Reason as filed by the promoterothers

ExtensionDec 2024 → Dec 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed95

As listed on the registration, under the names the promoter filed them with; the newest 80 of 95 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/210312/004001 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM - 4.pdf13 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 A.pdf13 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 E.pdf13 Oct 2026
Q2 2026-27 Water supply and sewage board13 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Oct 2026
Q2 2026-27 KPTCL- BESCOM13 Oct 2026
Q2 2026-27 Fire and Safety13 Oct 2026
Q2 2026-27 Airport Authority of India13 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department13 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM - 4 FY Q1 Triaxis.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5 certificate.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form6 Tri axis.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4-Q4-FY2025-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5-Q4-FY2025-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Q4-FY2025-26.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Q3 FY2025-26.pdf2 Apr 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5- Q3-Architec certificate.pdf2 Apr 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Triaxis.pdf2 Apr 2026
Q3 2025-26 Water supply and sewage board2 Apr 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)2 Apr 2026
Q3 2025-26 KPTCL- BESCOM2 Apr 2026
Q3 2025-26 Fire and Safety2 Apr 2026
Q3 2025-26 Airport Authority of India2 Apr 2026
Q3 2025-26 BSNL/Telecommunication Department2 Apr 2026
Financial Documents for the year 2019-20 with UDIN number and cheque bookFile: All financial documetns with UDIN number and cheque book copyc.pdf5 Mar 2021
Upto date EC as intimatedFile: Up to date Encumbrace Certificate.pdf5 Mar 2021
Building licenseFile: Building license.pdf5 Mar 2021
Sanction floor plan, elevation and section floorFile: Approved Plans.pdf5 Mar 2021
Relinquishment DeedFile: Relinquishment Deedc.pdf5 Mar 2021
plan copyFile: DANDUPALYA-119-1-plan copy.pdf29 Jan 2021
bank statementFile: bank statement.pdf29 Jan 2021
pan copy self attestedFile: pan copy self attested.pdf29 Jan 2021
IT Tax-2019-20File: IT Tax-2019-20.pdf29 Jan 2021
IT Tax-2020-21File: IT tax -2020-21.pdf29 Jan 2021
EC COpyFile: ec Copy new.pdf29 Jan 2021
affidavit sec (3)1File: affidavit sec (3)1.pdf29 Jan 2021
Noc from water suply copyFile: noc from water suply.pdf29 Jan 2021
KSPCB NOcFile: Kspcb noc.pdf29 Jan 2021
CertificateFile: Triaxis infra project firm Registration copy.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Form Ex 01.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Form Ex 05 Tri axis infra.pdf-
CA Certificate for Funds UtilizationFile: Form Ex 03.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Form Ex 02 DOne.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Form Ex 06 Triaxis infra.pdf-
CA Certificate for Funds required for Project CompletionFile: Form Ex 04.pdf-
AffidavitFile: Form Ex 07 Affidavit_compressed.pdf-
Latest Encumbrance CertificateFile: EC clarification.pdf-
Details Of Sold/ Un-sold UnitsFile: Sold and Unsold Inventory.pdf-
Document 1File: Clarification for project delay.pdf-
Document 2File: Ext contractor New.pdf-
Document 3File: Ext contractor old.pdf-
Document 4File: Form B.pdf-
laisence copy-1-
DANDUPALYA-119-1-plan copy-
Triaxis Infra projects Dandupalya Sale deed-final-
DANDUPALYA-119-1-plan copy-
DANDUPALYA-119-1-plan copy-
laisence copy-1-
specification-
Triaxis Infra projects EC from 1-04-2004 to 29-12-2020-
Affidavit cum Declaration-
Affidavit cum Declaration-
Dandupalya Katha-
JD Agreement Hoskota-
Triaxis Infra projects Dandupalya Sale deed-final-
convertion and sketch copies-
Dandupalya relinquish deed copy submission to BMRDA-

How this compares with Bengaluru Rural

57%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one moved by 36 months
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep TRIAXIS SPLENDOUR + on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: M s Triaxis Infra Projects

M s Triaxis Infra Projects has 1 registration on RERA Karnataka, including TRIAXIS SPLENDOUR +. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if TRIAXIS SPLENDOUR + is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of TRIAXIS SPLENDOUR +?

The registered promoter entity is M s Triaxis Infra Projects, a partnership firm as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in TRIAXIS SPLENDOUR +?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at TRIAXIS SPLENDOUR +?

The professionals named in the filing: Architect: Ajay Sharma; Engineer: Munish Sharma. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TRIAXIS SPLENDOUR +?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TRIAXIS SPLENDOUR +. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TRIAXIS SPLENDOUR + to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.