ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / TREEMOUNT PHASE 2

Registered No litigation declared Residential / Group Housing project

TREEMOUNT PHASE 2

By PRIMEDALE PROPERTIES LLP

RG-MH-17038 · RERA P52100027816 · Last updated on MahaRERA portal: 11 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 32 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Feb 2027Possession promisedmoved 32 months from the original
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
47 of 78Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 80 documents Report an error

TREEMOUNT PHASE 2 is a Residential / Group Housing project by PRIMEDALE PROPERTIES LLP in Pune, Maharashtra, registered with MahaRERA as P52100027816 on 4 Jan 2021. Possession is promised by 28 Feb 2027. The completion date has moved by 32 months from the original filing. 31 of the 78 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameTREEMOUNT PHASE 2
  • TypeResidential / Group Housing
  • Location
    • Talegaon Chakan Road
    • Malwadi
    • Talegaon Dabhade (R)
    • Mawal
    • Pune
    • 410507
  • Pincode410507
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100027816
  • ReraGenie IDRG-MH-17038

Builder

  • NamePRIMEDALE PROPERTIES LLP
  • Entity typePartnership
  • PartnersChandrakant Nivrutti Garad, Navnath Machindra Yewle

Key dates

this monthRegisteredJan 2021First promiseJun 2024Revised toFeb 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 Jan 2021
  • Promised completion28 Feb 2027
  • Revised completionRevised to 28 Feb 2027 (originally 30 Jun 2024)
  • Buildings1 building record
  • Documents filed80 files

Current status

40%31 of 78 units booked
94.6%Work done, per cost certificate

Figures as on 11 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WingNA10878078

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

C Wing: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 11 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,347 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Aug 2026
LandownerVillageDistrict
Kondeshwar Co-operative Housing Society LimitedMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGION DEVELOPMENT AUTHORITY PUNE
Permissible FSI9354.42
Proposed, not sanctioned9,354 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWarje, Pune
Estimated costRs 8.26 cr
Cost incurredRs 7.81 cr
Work done94.59%
BuildingWingEstimatedIncurred
C WingNARs 7.26 crRs 6.93 cr
-NARs 1.00 crRs 88.62 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK A Architecture
EngineerParag Mawal
Chartered AccountantMahajan and Bhapkar
Chartered AccountantA M Kale and Associates
PartnerRole in project
PRIMEDALE PROPERTIES LLP-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019851Jun 2024 → Jun 2025

Reason as filed by the promoterThe validity of the Project is ending on 30/06/2024. However, the Project is in the final stages and not complete yet due to some unenforceable delays, and we cannot get the OC issued before the due date of validity. Hence, we need more time to complete the Project. Rest assured, we are nearing the completion of the Project, and need some more time to complete the Project work. Therefore, we hereby apply for an extension of Project Registration validity till 30/06/2025.

EA14082622155Jun 2024 → Oct 2026

Reason as filed by the promoterWe Received the Part OC on 16/02/2026, based on which we have handed over possession. At present, the Allottee is not available for signing. We have received the Full Completion Certificate from Planning Authority on 16/02/2026. The Full Occupancy Certificate has been delayed by the authority due to technical reasons. We observed that the number of sanctioned floors And Parking details mentioned in our application are incorrect as per the sanctioned plan. We would like to correct these details in the application. Therefore, it is humble request that the period of handling over possession will

P52100027816/WarJun 2024 → Feb 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Dec 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 28 Feb 2027

Documents filed80

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form-1 (2).pdf11 Sep 2026
Withdrawal Update Form 1File: form-1 (2).pdf11 Sep 2026
Withdrawal Update Form 1File: form-1 (2).pdf11 Sep 2026
Withdrawal Update Form 1File: form-1 (2).pdf11 Sep 2026
Withdrawal Update Form 2File: form-2.pdf11 Sep 2026
Withdrawal Update Form 2File: form-2.pdf11 Sep 2026
Withdrawal Update Form 2File: form-2.pdf11 Sep 2026
Withdrawal Update Form 2File: form-2.pdf11 Sep 2026
Withdrawal Update Form 3File: Form 3 Q4 c.pdf11 Sep 2026
Withdrawal Update Form 3File: Form 3 Q4 c.pdf11 Sep 2026
Withdrawal Update Form 3File: Form 3 Q4 c.pdf11 Sep 2026
Withdrawal Update Form 3File: Form 3 Q4 c.pdf11 Sep 2026
Form 2A (FY 2024-2025)File: Form 2A (6).pdf14 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A (7).pdf14 Aug 2026
Form 1File: form-1.pdf10 Aug 2026
Form 2File: form-2.pdf10 Aug 2026
Form 3File: Form-3-compressed (1).pdf10 Aug 2026
Disclosure of Sold and Booked InventoryFile: Sold unsold inventory (1).pdf10 Aug 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Q4 Disclosure of sold booked inventory.pdf31 May 2024
Declaration in FORM BFile: Form B.pdf24 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4.pdf24 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 c.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-3 c.pdf8 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2020-21.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 3 21-22 Apr- Dec 31-12-2021.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q4 21-22 31-03-2022.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 1 22-23 30-06-2022.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q2 22-23 30-09-2022.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 3 22-23 31-12-2022.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q4 22-23 31-03-2023.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q1 23-24 30-06-2023.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q2 23-24 30-09-2023.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 3 23-24 31-12-2023.pdf7 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf7 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 2020-21.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- Apr-21 to Dec-21.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- Jan-22 to March-22.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-1.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-2.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-3.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-4.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 23-24-Q-1.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 23-24-Q-2.pdf27 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 23-24-Q-3.pdf27 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf27 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-2021-22.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 2020-21.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- April-21 to Dec-21_compressed.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- Jan-22 to March-22.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-1.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-2.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-3.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-4_compressed.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-1_compressed.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-2_compressed.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-3_compressed.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5- 2020-21.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5- 2021-22.pdf27 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5- 2022-23.pdf27 Feb 2024
Layout approvalFile: Layout.pdf26 Dec 2020
Building plan approvalFile: 10_16_compressed.pdf26 Dec 2020
Building plan approvalFile: 11_16_compressed.pdf26 Dec 2020
Building plan approvalFile: 12_16_compressed.pdf26 Dec 2020
Building plan approvalFile: 13_16_compressed.pdf26 Dec 2020
PAN CardFile: Pan Card - Primedale.pdf26 Dec 2020
Copy of the legal title reportFile: SEARCH REPORT.pdf26 Dec 2020
Details of encumbrancesFile: Development Agreement.pdf26 Dec 2020
Copy of Layout Approval (in case of layout)File: Layout.pdf26 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: 10_16_compressed.pdf26 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: 11_16_compressed.pdf26 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: 12_16_compressed.pdf26 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: 13_16_compressed.pdf26 Dec 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement_compressed-2.pdf26 Dec 2020
Declaration in FORM BFile: FORM B_compressed-2.pdf26 Dec 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf26 Dec 2020
Proforma of Allotment letterFile: Draft.pdf26 Dec 2020

How this compares with Pune

40%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 32 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TREEMOUNT PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malwadi13,700+ in Pune

2 kmTREEMOUNT PHASE 2Completed 116Lapsed / revoked 117Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: PRIMEDALE PROPERTIES LLP

PRIMEDALE PROPERTIES LLP has 1 registration on MahaRERA, including TREEMOUNT PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TREEMOUNT PHASE 2 is delayed beyond 28 Feb 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TREEMOUNT PHASE 2?

The registered promoter entity is PRIMEDALE PROPERTIES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TREEMOUNT PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TREEMOUNT PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TREEMOUNT PHASE 2?

The professionals named in the filing: Architect: VK A Architecture; Engineer: Parag Mawal; Chartered Accountant: Mahajan and Bhapkar; Chartered Accountant: A M Kale and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TREEMOUNT PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TREEMOUNT PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TREEMOUNT PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.