TREEMOUNT PHASE 2
RG-MH-17038 · RERA P52100027816 · Last updated on MahaRERA portal: 11 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 32 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
TREEMOUNT PHASE 2 is a Residential / Group Housing project by PRIMEDALE PROPERTIES LLP in Pune, Maharashtra, registered with MahaRERA as P52100027816 on 4 Jan 2021. Possession is promised by 28 Feb 2027. The completion date has moved by 32 months from the original filing. 31 of the 78 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameTREEMOUNT PHASE 2
- TypeResidential / Group Housing
- Location
- Talegaon Chakan Road
- Malwadi
- Talegaon Dabhade (R)
- Mawal
- Pune
- 410507
- Pincode410507
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100027816
- ReraGenie IDRG-MH-17038
Builder
- NamePRIMEDALE PROPERTIES LLP
- Entity typePartnership
- PartnersChandrakant Nivrutti Garad, Navnath Machindra Yewle
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Jan 2021
- Promised completion28 Feb 2027
- Revised completionRevised to 28 Feb 2027 (originally 30 Jun 2024)
- Buildings1 building record
- Documents filed80 files
Current status
Figures as on 11 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| C Wing | NA | 10 | 8 | 78 | 0 | 78 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
C Wing: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 11 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Kondeshwar Co-operative Housing Society Limited | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| C Wing | NA | Rs 7.26 cr | Rs 6.93 cr |
| - | NA | Rs 1.00 cr | Rs 88.62 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VK A Architecture |
| Engineer | Parag Mawal |
| Chartered Accountant | Mahajan and Bhapkar |
| Chartered Accountant | A M Kale and Associates |
| Partner | Role in project |
|---|---|
| PRIMEDALE PROPERTIES LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe validity of the Project is ending on 30/06/2024. However, the Project is in the final stages and not complete yet due to some unenforceable delays, and we cannot get the OC issued before the due date of validity. Hence, we need more time to complete the Project. Rest assured, we are nearing the completion of the Project, and need some more time to complete the Project work. Therefore, we hereby apply for an extension of Project Registration validity till 30/06/2025.
Reason as filed by the promoterWe Received the Part OC on 16/02/2026, based on which we have handed over possession. At present, the Allottee is not available for signing. We have received the Full Completion Certificate from Planning Authority on 16/02/2026. The Full Occupancy Certificate has been delayed by the authority due to technical reasons. We observed that the number of sanctioned floors And Parking details mentioned in our application are incorrect as per the sanctioned plan. We would like to correct these details in the application. Therefore, it is humble request that the period of handling over possession will
Reason as filed by the promoterNA
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Dec 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Dec 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Dec 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 28 Feb 2027
Documents filed80
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form-1 (2).pdf | 11 Sep 2026 |
| Withdrawal Update Form 1File: form-1 (2).pdf | 11 Sep 2026 |
| Withdrawal Update Form 1File: form-1 (2).pdf | 11 Sep 2026 |
| Withdrawal Update Form 1File: form-1 (2).pdf | 11 Sep 2026 |
| Withdrawal Update Form 2File: form-2.pdf | 11 Sep 2026 |
| Withdrawal Update Form 2File: form-2.pdf | 11 Sep 2026 |
| Withdrawal Update Form 2File: form-2.pdf | 11 Sep 2026 |
| Withdrawal Update Form 2File: form-2.pdf | 11 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 c.pdf | 11 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 c.pdf | 11 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 c.pdf | 11 Sep 2026 |
| Withdrawal Update Form 3File: Form 3 Q4 c.pdf | 11 Sep 2026 |
| Form 2A (FY 2024-2025)File: Form 2A (6).pdf | 14 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A (7).pdf | 14 Aug 2026 |
| Form 1File: form-1.pdf | 10 Aug 2026 |
| Form 2File: form-2.pdf | 10 Aug 2026 |
| Form 3File: Form-3-compressed (1).pdf | 10 Aug 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold unsold inventory (1).pdf | 10 Aug 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 11 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 11 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf | 20 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Q4 Disclosure of sold booked inventory.pdf | 31 May 2024 |
| Declaration in FORM BFile: Form B.pdf | 24 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4.pdf | 24 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf | 24 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4 c.pdf | 24 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-3 c.pdf | 8 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2020-21.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 3 21-22 Apr- Dec 31-12-2021.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q4 21-22 31-03-2022.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 1 22-23 30-06-2022.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q2 22-23 30-09-2022.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 3 22-23 31-12-2022.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q4 22-23 31-03-2023.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q1 23-24 30-06-2023.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q2 23-24 30-09-2023.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1- Q 3 23-24 31-12-2023.pdf | 7 Mar 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 2022-23.pdf | 7 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 2020-21.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- Apr-21 to Dec-21.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- Jan-22 to March-22.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-1.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-2.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-3.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 22-23-Q-4.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 23-24-Q-1.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 23-24-Q-2.pdf | 27 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2- 23-24-Q-3.pdf | 27 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 2020-21.pdf | 27 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-2021-22.pdf | 27 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 2020-21.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- April-21 to Dec-21_compressed.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- Jan-22 to March-22.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-1.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-2.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-3.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 22-23-Q-4_compressed.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-1_compressed.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-2_compressed.pdf | 27 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3- 23-24-Q-3_compressed.pdf | 27 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5- 2020-21.pdf | 27 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5- 2021-22.pdf | 27 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form-5- 2022-23.pdf | 27 Feb 2024 |
| Layout approvalFile: Layout.pdf | 26 Dec 2020 |
| Building plan approvalFile: 10_16_compressed.pdf | 26 Dec 2020 |
| Building plan approvalFile: 11_16_compressed.pdf | 26 Dec 2020 |
| Building plan approvalFile: 12_16_compressed.pdf | 26 Dec 2020 |
| Building plan approvalFile: 13_16_compressed.pdf | 26 Dec 2020 |
| PAN CardFile: Pan Card - Primedale.pdf | 26 Dec 2020 |
| Copy of the legal title reportFile: SEARCH REPORT.pdf | 26 Dec 2020 |
| Details of encumbrancesFile: Development Agreement.pdf | 26 Dec 2020 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 26 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 10_16_compressed.pdf | 26 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 11_16_compressed.pdf | 26 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 12_16_compressed.pdf | 26 Dec 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: 13_16_compressed.pdf | 26 Dec 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement_compressed-2.pdf | 26 Dec 2020 |
| Declaration in FORM BFile: FORM B_compressed-2.pdf | 26 Dec 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf | 26 Dec 2020 |
| Proforma of Allotment letterFile: Draft.pdf | 26 Dec 2020 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 80 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep TREEMOUNT PHASE 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Malwadi13,700+ in Pune
Filed coordinates, straight-line distance. 268 registered projects within 2 km.
ANANDAM PHASE I
A V BHAT DEVELOPERS LLP
Ashiana Amodh Phase I
Ashiana Housing Limited
Ashiana Amodh Phase 3
Ashiana Housing Limited
HAPPYCITY VARALE
NAMRATA DEVELOPERS PRIVATE LIMITED
Namrata Sarvam
NAMRATA KHANDGE VENTURES
PLATINUM ELITE
Sugat Properties
Builder: PRIMEDALE PROPERTIES LLP
PRIMEDALE PROPERTIES LLP has 1 registration on MahaRERA, including TREEMOUNT PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if TREEMOUNT PHASE 2 is delayed beyond 28 Feb 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of TREEMOUNT PHASE 2?
The registered promoter entity is PRIMEDALE PROPERTIES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in TREEMOUNT PHASE 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for TREEMOUNT PHASE 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at TREEMOUNT PHASE 2?
The professionals named in the filing: Architect: VK A Architecture; Engineer: Parag Mawal; Chartered Accountant: Mahajan and Bhapkar; Chartered Accountant: A M Kale and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in TREEMOUNT PHASE 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.