Home / Browse projects / Pune, Maharashtra / TIME CITY

Registered No litigation declared Others project

TIME CITY

By RAJENDRA NARAWADE AND SUDHIR NARAWADE

RG-MH-21515 · RERA P52100029707 · Last updated on MahaRERA portal: 13 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 44 months
  • 1 extension taken
  • Rs 9.00 crore secured on the land, in favour of Shree Ram Patsanstha
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 44 months from the original
7 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 50%
50 of 52Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

TIME CITY is a Others project by RAJENDRA NARAWADE AND SUDHIR NARAWADE in Pune, Maharashtra, registered with MahaRERA as P52100029707 on 26 Jun 2021. Possession is promised by 31 Dec 2027. The completion date has moved by 44 months from the original filing. 2 of the 52 units on this registration are recorded sold or booked, and 7 of 33 construction stages are filed complete.

At a glance

Project

  • NameTIME CITY
  • TypeOthers
  • Location
    • Alephata
    • Alefata (N.V.)
    • Junnar
    • Pune
    • 412411
  • Pincode412411
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100029707
  • ReraGenie IDRG-MH-21515

Builder

  • NameRAJENDRA NARAWADE AND SUDHIR NARAWADE
  • Entity typeOthers
  • PropritorSUDHIR MARUTI NARAWADE .

Key dates

this monthRegisteredJun 2021First promiseApr 2024Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Jun 2021
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Apr 2024)
  • Buildings3 building records
  • Documents filed112 files

Current status

4%2 of 52 units booked
65.6%Work done, per cost certificate

Figures as on 13 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MALLNA00000
BUNGALOWSNA00404
RESIDENTIAL BUILDINGNA181648048

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 13 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 50%.

MALL0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUNGALOWS32%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RESIDENTIAL BUILDING41%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,628 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofShree Ram Patsanstha
Secured amountRs 9.00 crore
CERSAI search filedYes
Declared on5 Feb 2026

Approvals and building plan

Sanctioning authoritySub Divisional Office, Junnar- Ambegaon
Permissible FSI4998.18
Proposed, not sanctioned3,792 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchJUNNAR
Estimated costRs 8.00 cr
Cost incurredRs 5.25 cr
Work done65.64%
BuildingWingEstimatedIncurred
RESIDENTIAL BUILDINGNARs 6.00 crRs 5.25 cr
-NARs 2.00 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAAKRUTI ARCHITECT AND INTERIOR DESIGNERS
EngineerAKSHAY DHONDIBHAU BARATE
EngineerSagar Gadge
EngineerADS CONSULTANTS
Chartered AccountantCA VAIBHAV MODI
Chartered AccountantCA ATUL NIGHOT
PartnerRole in project
SUDHIR MARUTI NARAWADE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA12062621346Apr 2024 → Dec 2027

Reason as filed by the promoterThe authorized partner who was primarily looking after and supervising the said project unfortunately expired during the course of execution of the project. Due to his sudden demise, the project work was severely affected and came to a halt for a considerable period. The said partner was actively involved in handling the project-related activities, coordination, decision-making, and execution. Consequently, the remaining partner required time to review the project status, reorganize responsibilities, collect pending information, and resume the work."

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jun 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Mar 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Mar 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Q2 30-09-2024.pdf13 Jul 2026
Form 2File: Form 2 Q2 30-09-2024.pdf13 Jul 2026
Form 3File: Form 3 Q2 30-09-2024.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q2 30-09-2024.pdf13 Jul 2026
Form 1File: Form 1 Q3 31-12-2024.pdf13 Jul 2026
Form 2File: Form 2 Q3 31-12-2024.pdf13 Jul 2026
Form 3File: Form 3 Q3 31-12-2024.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q3 31-12-2024.pdf13 Jul 2026
Form 1File: Form 1 Q4 31-03-2025.pdf13 Jul 2026
Form 2File: Form 2 Q4 31-03-2025.pdf13 Jul 2026
Form 3File: Form 3 Q4 31-03-2025.pdf13 Jul 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q4 31-03-2025.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q1 FY 2026-27.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q2 30-9-2025.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q1 30-06-2025.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q3 31-12-2025.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q3 31-12-2025.pdf13 Jul 2026
Withdrawal Update Form 1File: Form 1 Q4 31-03-2026.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 Q1 FY 2026-27.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 Q2 30-9-2025.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 Q1 30-06-2025.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 Q3 31-12-2025.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 Q3 31-12-2025.pdf13 Jul 2026
Withdrawal Update Form 2File: Form 2 Q4 31-03-2026.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 FY 2026-27.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Q2 30-09-2025.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 30-06-2025.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Q3 31-12-2025.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Q3 31-12-2025.pdf13 Jul 2026
Withdrawal Update Form 3File: Form 3 Q4 31-03-2026.pdf13 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A FY 2025-26.pdf13 Jul 2026
Form 5 (FY 2021-2022)File: Form 5 FY 2021-22.pdf18 Jun 2026
Form 5 (FY 2022-2023)File: Form 5 FY 2022-23.pdf18 Jun 2026
Form 5 (FY 2023-2024)File: Form 5 FY 2023-24.pdf18 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 FY 2024-25.pdf18 Jun 2026
Form 2A (FY 2021-2022)File: Form 2A FY 2021-22.pdf12 Jun 2026
Form 2A (FY 2022-2023)File: Form 2A FY 2022-23.pdf12 Jun 2026
Form 2A (FY 2023-2024)File: Form 2A FY 2023-24.pdf12 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A FY 2024-25.pdf12 Jun 2026
Form 1File: Form 1 Q1 30-06-2021.pdf7 May 2026
Form 2File: Form 2 Q1 30-06-2021.pdf7 May 2026
Form 3File: Form 3 Q1 30-06-2021.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q1 30-06-2021.pdf7 May 2026
Form 1File: Form 1 Q2 30-09-2021.pdf7 May 2026
Form 2File: Form 2 Q2 30-09-2021.pdf7 May 2026
Form 3File: Form 3 Q2 30-09-2021.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q2 30-09-2021.pdf7 May 2026
Form 1File: Form 1 Q3 31-12-2021.pdf7 May 2026
Form 2File: Form 2 Q3 31-12-2021.pdf7 May 2026
Form 3File: Form 3 Q3 31-12-2021.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q3 31-12-2021.pdf7 May 2026
Form 1File: Form 1 Q4 31-03-2022.pdf7 May 2026
Form 2File: Form 2 Q4 31-03-2022.pdf7 May 2026
Form 3File: Form 3 Q4 31-03-2022.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q4 31-03-2022.pdf7 May 2026
Form 1File: Form 1 Q1 30-06-2022.pdf7 May 2026
Form 2File: Form 2 Q1 30-06-2022.pdf7 May 2026
Form 3File: Form 3 Q1 30-06-2022.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q1 30-06-2022.pdf7 May 2026
Form 1File: Form 1 Q2 30-09-2022.pdf7 May 2026
Form 2File: Form 2 Q2 30-09-2022.pdf7 May 2026
Form 3File: Form 3 Q2 30-09-2022.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular 30-09-2022.pdf7 May 2026
Form 1File: Form 1 Q3 31-12-2022.pdf7 May 2026
Form 2File: Form 2 Q3 31-12-2022.pdf7 May 2026
Form 3File: Form 3 Q3 31-12-2022.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q3 31-12-2022.pdf7 May 2026
Form 1File: Form 1 Q4 31-03-2023.pdf7 May 2026
Form 2File: Form 2 Q4 31-03-2023.pdf7 May 2026
Form 3File: Form 3 Q4 31-03-2023.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q4 31-03-2023.pdf7 May 2026
Form 1File: Form 1 Q1 30-06-2023.pdf7 May 2026
Form 2File: Form 2 Q1 30-06-2023.pdf7 May 2026
Form 3File: Form 3 Q1 30-06-2023.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q1 30-06-2023.pdf7 May 2026
Form 1File: Form 1 Q2 30-09-2023.pdf7 May 2026
Form 2File: Form 2 Q2 30-09-2023.pdf7 May 2026
Form 3File: Form 3 Q2 30-09-2023.pdf7 May 2026
Disclosure of Sold and Booked InventoryFile: Sold Circular Q2 30-09-2023.pdf7 May 2026
Form 1File: Form 1 Q3 31-12-2023.pdf7 May 2026

How this compares with Pune

4%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 44 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TIME CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Alephata13,700+ in Pune

2 kmTIME CITYCompleted 2Lapsed / revoked 2Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 9 registered projects within 2 km.

Builder: RAJENDRA NARAWADE AND SUDHIR NARAWADE

RAJENDRA NARAWADE AND SUDHIR NARAWADE has 1 registration on MahaRERA, including TIME CITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TIME CITY is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TIME CITY?

The registered promoter entity is RAJENDRA NARAWADE AND SUDHIR NARAWADE, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TIME CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TIME CITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TIME CITY?

The professionals named in the filing: Architect: AAKRUTI ARCHITECT AND INTERIOR DESIGNERS; Engineer: AKSHAY DHONDIBHAU BARATE; Engineer: Sagar Gadge; Engineer: ADS CONSULTANTS; Chartered Accountant: CA VAIBHAV MODI; Chartered Accountant: CA ATUL NIGHOT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TIME CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TIME CITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TIME CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.