Home / Browse projects / Pune, Maharashtra / Shubham Tarangan Phase II
Shubham Tarangan Phase II
RG-MH-17491 · RERA P52100029066 · Last updated on MahaRERA portal: 31 May 2026
Source: official MahaRERA filing
Red flags
- 2 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Shubham Tarangan Phase II is a Residential / Group Housing project by Shubham Vipra Associates in Pune, Maharashtra, registered with MahaRERA as P52100029066 on 23 Apr 2021. The registration is recorded completed; possession was promised by 31 Dec 2025. 130 of the 252 units on this registration are recorded sold or booked, and 28 of 44 construction stages are filed complete. 2 complaints are on record with the regulator.
At a glance
Project
- NameShubham Tarangan Phase II
- TypeResidential / Group Housing
- Location
- On Pune Nashik Highway
- Opp. to Reliance Petrol Pump
- 1.5 Kms from Alephata Chowk toward Nashik
- A/P - Ale
- Tal - Junnar
- Dist - Pune
- Ale
- Junnar
- Pune
- 412411
- Pincode412411
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029066
- ReraGenie IDRG-MH-17491
Builder
- NameShubham Vipra Associates
- Entity typeIndividual
- GSTIN27ACFFS9015G1Z0
- PartnersPRADEEP PRATAPRAO WALSEPATIL, VINAY KHUSHALCHAND BADERA
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on23 Apr 2021
- Promised completion31 Dec 2025
- Revised completionNone
- Buildings4 building records
- Documents filed151 files
Current status
Figures as on 31 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Ashwini | NA | 8 | 7 | 56 | 0 | 56 |
| Krutika | NA | 8 | 7 | 56 | 0 | 56 |
| Swati | NA | 8 | 7 | 56 | 0 | 56 |
| Purna | NA | 8 | 7 | 84 | 0 | 84 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 31 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
28 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.
Ashwini94%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 60% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 80% |
Krutika74%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Swati73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 25% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 25% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
Purna75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 25% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 31 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Parking filed428
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| Ashwini | 24 | 74 | 98 |
| Krutika | 28 | 61 | 89 |
| Swati | 28 | 97 | 125 |
| Purna | 28 | 88 | 116 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Vinay Khushalchand Badera | Pune (M Corp.) | Pune |
| Shubham Vipra Associates | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN STUDIO |
| Engineer | SHUBHAM VIPRA ASSOCIATES |
| Chartered Accountant | A S JANGADA & ASSOCIATES |
| Chartered Accountant | NITISH VAIDYA AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| SHUBHAM VIPRA ASSOCIATES | - |
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12504328 | Prajakta Jadhav | Shubham Vipra Associates | 07/12/2025 |
| CC12602043 | Shubham Vipra Associates | Dipankar Narayan Dinda | 07/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Apr 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 29 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Apr 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed151
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: OC upload with cc mail.pdf | 31 May 2026 |
| Occupational CertificateFile: CC mail.pdf | 31 May 2026 |
| Form 1File: Form 1 upload.pdf | 23 May 2026 |
| Form 2File: Form 2 upload final.pdf | 23 May 2026 |
| Form 3File: Form 3 upload.pdf | 23 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 23 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 22 May 2026 |
| Form 2File: Form 2 upload.pdf | 22 May 2026 |
| Form 3File: Form 3.pdf | 22 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 22 May 2026 |
| Form 1File: Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 19 May 2026 |
| Form 1File: Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 19 May 2026 |
| Form 1File: Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 19 May 2026 |
| Form 1File: Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Circular upload.pdf | 19 May 2026 |
| Form 1File: Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 19 May 2026 |
| Form 1File: Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular upload.pdf | 19 May 2026 |
| Form 1File: Final Form 1 upload.pdf | 19 May 2026 |
| Form 2File: Form 2 upload.pdf | 19 May 2026 |
| Form 3File: Form 3.pdf | 19 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold circular.pdf | 19 May 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ASHWINI-KRUTIKA-SWATI-PURNA RERA CERTIFICATE.pdf | 17 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3_31032024_16-07-2025 - converted (1).pdf | 17 Jul 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Shubham Tarangan Phase I | ALE | 172 | Completed | Mar 2019 | Mar 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 151 filed documents as one ZIP, foldered, with a manifest
Keep Shubham Tarangan Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near 1.5 Kms from Alephata Chowk toward Nashik, A/P - Ale, Tal - Junnar, Dist - Pune13,700+ in Pune
K K Market
K K Construction
Ayodhyam Villa
SRP Buildcon
Alephata Central Park
SUV Developers
NEST IN PARK
M/S. JS REALTY
Swami Vishwa Heights
Laxmi Developers
Global Silver Park
VEDANT AND BHUJBAL DEVELOPERS
Builder: Shubham Vipra Associates
Shubham Vipra Associates has 1 registration on MahaRERA, including Shubham Tarangan Phase II. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Shubham Tarangan Phase II is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Shubham Tarangan Phase II?
The registered promoter entity is Shubham Vipra Associates, an individual as per the filing. Its GSTIN 27ACFFS9015G1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Shubham Tarangan Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Shubham Tarangan Phase II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Shubham Tarangan Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Shubham Tarangan Phase II?
The professionals named in the filing: Architect: DESIGN STUDIO; Engineer: SHUBHAM VIPRA ASSOCIATES; Chartered Accountant: A S JANGADA & ASSOCIATES; Chartered Accountant: NITISH VAIDYA AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Shubham Tarangan Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback