THE ROOTS

By SRK INFRA PROJECTS PRIVATE LIMITED

RG-KA-86583 · RERA PRM/KA/RERA/1250/303/PR/090925/008075 · Last updated on RERA Karnataka portal: 15 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2030Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Retaining wall (All types), 70%
72 of 100Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 106 documents Report an error

THE ROOTS is a Residential/Group Housing project by SRK INFRA PROJECTS PRIVATE LIMITED in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/090925/008075 on 9 Sep 2025. Possession is promised by 30 Jul 2030. 28 of the 100 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameTHE ROOTS
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/090925/008075
  • ReraGenie IDRG-KA-86583

Builder

  • NameSRK INFRA PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200TG2002PTC038486
  • GSTIN29AAGCS2903M1Z1
  • Authorized SignatoryKancharla Chaitanya Krishna
  • Managing DirectorManthena Satyanarayana Raju
  • DirectorsManthena Satyanarayana Raju, Gorinta Janaki, Savitri Manthena, MANTHENA MOHAN KRISHNAM RAJU, Swati Lakshmi Manthena
  • Project HeadKancharla Chaitanya Krishna
  • Other registrations5 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredSep 2025PromisedJul 2030

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 Sep 2025
  • Promised completion30 Jul 2030
  • Revised completionNone
  • Buildings15 building records
  • Documents filed106 files

Current status

28%28 of 100 units booked
7.8%Of the estimated cost spent so far

Figures as on 15 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block 2---13013
Block 3A---505
Block 3B---505
Block 3C---505
Block 3D---505
Block 3E---505
Block 3F---505
Block 4---505
Block 5A---11011
Block 5B---101
Block 6---16016
Block 7A---606
Block 7B---606
Block 7C---606
Block 7D---606

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 70%.

Building: 5% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work0%
Foundation footing work0%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)70%
RCC or MS Framed structure15%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalYes0%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes3%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes35%
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area21,168 sq m
Named landowners1
LandownerVillageDistrict
SRK INFRA PROJECTS PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 257.27 cr
Cost incurredRs 20.09 cr
Spent of the estimate7.81%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 180.00 crRs 10.37 cr
On-site expenditure-Site OverheadRs 20.00 crRs 1.72 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 20.00 crRs 2.82 cr
Payment of taxesRs 12.28 cr-
On-site expenditure-Salaries of workersRs 12.00 crRs 4.01 cr
On-site expenditure-Consultants FeesRs 6.50 crRs 1.08 cr
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 6.00 crRs 8.62 lakh
Payment of cessRs 49.10 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnand B
EngineerSUHAS M
Chartered AccountantSAGAR VENKATESH

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed106

As listed on the registration, under the names the promoter filed them with; the newest 80 of 106 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/090925/008075 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate - SRK Infr (1).pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect Certificate_Q1 Fy 26-27.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engineer Certificate_Q1_Roots.pdf15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architech Certificate.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engineer certificate.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form4 - Signed_Q3.pdf19 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form2_Architect Certificate-Q3.pdf19 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6- Engineer certificate-Q3.pdf19 Jan 2026
Agreement of saleFile: Agreement of sale.pdf8 Sep 2025
Allotment letterFile: Allotment letter.pdf8 Sep 2025
Project Estimation with engineer signatureFile: Final Project Estimation.pdf8 Sep 2025
Guidance valueFile: CVC Report - Guidance value.pdf8 Sep 2025
Land Cost calculation sheetFile: Land Cost calculation sheet.pdf8 Sep 2025
Form1- CA CertificateFile: Form1- CA Certificate.pdf8 Sep 2025
Latitude and Longitude of the proposed project does not match with the project locationFile: The Roots Longitude and Latitude (1).pdf25 Aug 2025
seperate area calculation sheet as per the approved plan tower wise certified by the engiFile: Area Details (2).pdf25 Aug 2025
the Form -3 Engineer's CertificateFile: Form 3 Engineer certificate (1).pdf25 Aug 2025
structural stability certificate clearly stating the building's safety and durabilityFile: Structural stability certificate (1).pdf25 Aug 2025
project specification with signatureFile: Roots Specifications for rera (1).pdf25 Aug 2025
construction cost details in cost details apge as per engineer certificateFile: Form 3 Engineer certificate (1).pdf25 Aug 2025
Proforma of agreement (AFS) for sale with clearly mentioning all the clauses/sections asFile: ROOTS_ RERA Agreement.pdf25 Aug 2025
Proforma Allotment letter as per the prescribed form with clearly mentioning all the clauses/sectionFile: Allotment Letter Draft (1).pdf25 Aug 2025
Upload the brief project estimation details with Engineer signatureFile: Project Estimation (1).pdf25 Aug 2025
STP design drawing certified by the Engineer as per the guidelinesFile: STP Layout - For RERA (1).pdf25 Aug 2025
upload the Land cost calculation sheet as per the guidance value(Self-attested copy)File: Land Cost (1).pdf25 Aug 2025
)Approved Original Single Plot layout planFile: Roots DP.pdf25 Aug 2025
Approved building planFile: ground Floor.pdf25 Aug 2025
commencement certificateFile: CC.pdf25 Aug 2025
Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: THE ROOTS CDP (1).pdf25 Aug 2025
Demarcation of proposed land in original Village map certified by the competent authorityFile: village map_page-0001 (1).pdf25 Aug 2025
Approval/NOC under section 14 of the KTCP Act from competent AuthorityFile: SECTION 14 OF KTCP ACT (1).pdf25 Aug 2025
Upload chartered accountant certificate (CA)File: Form 1 - CA Certificate (2).pdf25 Aug 2025
profit and loss 2021-22File: P&L- Fy 2021-22.pdf25 Aug 2025
profit and loss 2022-23File: P& L Statement 2022-23.pdf25 Aug 2025
profit and loss 2023-24File: p&L 23-24 (2).pdf25 Aug 2025
balance sheet for 2021-22File: BS- Fy 2021-22.pdf25 Aug 2025
balance sheet for 2022-23File: BS-2022-23.pdf25 Aug 2025
balance sheet for 2023-24File: BS_-2023-24.pdf25 Aug 2025
bank affidavit in the prescribed formatFile: Bank Affidavit.pdf25 Aug 2025
bank 100%, 70%, and 30% account pass sheets or statementsFile: Bank Account Confirmation letter (1).pdf25 Aug 2025
the sources of funds to complete the projectFile: Sources of Funds.pdf25 Aug 2025
architect certificateFile: Architect Certificate RERA (1).pdf25 Aug 2025
Registration CertificateFile: Certificate of Incorporation (1).pdf-
Memorandum of AssociationFile: SRK INFRA - MOA.pdf-
Article of AssociationFile: SRK INFRA - AOA.pdf-
GST CertificateFile: Revised GST Registration.pdf-
Organization StructureFile: Organization Structure.pdf-
Certificate issued by CA Form 1File: Form 1 - CA Certificate (2).pdf-
Certificate issued by Architect Form 2File: Architect Certificate RERA (1).pdf-
Certificate issued by Engineer Form 3File: Form 3 Engineer certificate (1).pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Affidavit Non-litigation.pdf-
Balance Sheet 2023 - 2024File: BS.pdf-
Balance Sheet 2022 - 2023File: BS.pdf-
Balance Sheet 2021 - 2022File: BS- Fy 2021-22.pdf-
Audited Profit and Loss Statement 2023 - 2024File: p&L.pdf-
Audited Profit and Loss Statement 2022 - 2023File: P& L Statement.pdf-
Audited Profit and Loss Statement 2021 - 2022File: P&L- Fy 2021-22.pdf-
Income Tax Return Acknowledgement 2023 - 2024File: ITRV.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITRV Form.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITRV - Ack - Fy 2021-22.pdf-
Director's Report 2023 - 2024File: NA (1).pdf-
Cash Flow Statement 2023 - 2024File: NA (1).pdf-
Auditor's Report 2023 - 2024File: Auditor Repot.pdf-
Auditor's Report 2022 - 2023File: Audit Report 22-23.pdf-
Auditor's Report 2021 - 2022File: Audit Report - FY 2021-22.pdf-
CC-
ground Floor-
Block-2-
will upload later-
will upload later-
THE ROOTS BROCHURE 4BL 2MB-
Relinquishment deed Sadahalli-
ROOTS_ RERA Agreement_ 05-07-2025 (1)-
Allotment Letter Draft (1)-
Affidavit and Declaration (1)-
Affidavit Sec 3 (1)-

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date4 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
THE EARTHGulya Nandhigunda and Sonnamaranahalli Village Tubagere Hobli, Doddaballapur Taluk, Bangalore Rural DistrictOngoingMay 2026Not delivered
THE Estates 1Madakuhosahalli village, Nandi Hobli, Chikkaballapur taluk And DistrictCompleted-No date filed
THE ESTATES IIMadakuhosahalli village, Nandi Hobli, Chikkaballapur taluk And DistrictCompleted-No date filed
THE ESTATES 3.0Channapura village, Tubagere Hobli, Doddaballapur Taluk, Bangalore Rural DistrictCompleted-No date filed
THE ESTATES 2.0Madakuhosahalli village, Nandi Hobli, Chikkaballapur taluk And DistrictCompleted-No date filed

How this compares with Bengaluru Rural

28%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep THE ROOTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmTHE ROOTSOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: SRK INFRA PROJECTS PRIVATE LIMITED

SRK INFRA PROJECTS PRIVATE LIMITED has 6 registrations on RERA Karnataka, including AAMAYA and The Estates 3.0. Its filings declare 8 earlier projects, 6 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if THE ROOTS is delayed beyond 30 Jul 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of THE ROOTS?

The registered promoter entity is SRK INFRA PROJECTS PRIVATE LIMITED, a company as per the filing. Its CIN U45200TG2002PTC038486 and GSTIN 29AAGCS2903M1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in THE ROOTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at THE ROOTS?

The professionals named in the filing: Architect: Anand B; Engineer: SUHAS M; Chartered Accountant: SAGAR VENKATESH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE ROOTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE ROOTS. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE ROOTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.