Home / Browse projects / Bengaluru Rural, Karnataka / EMBASSY GREENSHORE

Registration approved Litigation declared Residential/Group Housing project

EMBASSY GREENSHORE

By EMBASSY DEVELOPMENTS LIMITED

RG-KA-44333 · RERA PRM/KA/RERA/1250/303/PR/201125/008265 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • Litigation declared, 7 cases

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2031Possession promisedno revision filed
0 of 18Construction stages donefurthest along: Earth work and other leveling..., 98%
251 of 878Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 179 documents Report an error

EMBASSY GREENSHORE is a Residential/Group Housing project by EMBASSY DEVELOPMENTS LIMITED in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/303/PR/201125/008265 on 20 Nov 2025. Possession is promised by 31 Dec 2031. 627 of the 878 units on this registration are recorded sold or booked, and 0 of 18 construction stages are filed complete.

At a glance

Project

  • NameEMBASSY GREENSHORE
  • TypeResidential/Group Housing
  • Location
    • Devanahalli
    • Bengaluru Rural
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/303/PR/201125/008265
  • ReraGenie IDRG-KA-44333

Builder

  • NameEMBASSY DEVELOPMENTS LIMITED
  • Entity typeCompany
  • CINL45101HR2006PLC095409
  • GSTIN29AABCI5194F1ZE
  • Authorized SignatoryShailendra Konanur Subbaraya
  • MdAditya Virwani
  • DirectorsAditya Virwani, JITENDRA MOHANDAS VIRWANI, RAJESH KAIMAL, SACHIN C SHAH, Javed F Tapia, Tarana Lalwani, Shyamm Mariwala, Kulumani Gopalratnam Krishnamurthy
  • Project HeadHriday Desai
  • Other registrations4 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredNov 2025PromisedDec 2031

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on20 Nov 2025
  • Promised completion31 Dec 2031
  • Revised completionNone
  • Buildings8 building records
  • Documents filed179 files

Current status

71%627 of 878 units booked
12.6%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1---1120112
Tower 2---1040104
Tower 3---1310131
Tower 4---91091
Tower 5---1290129
Tower 6---1270127
Tower 7---1290129
Tower 8---55055

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 18 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 98%.

Building: 9% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work98%
Foundation footing work66%
Upto Plinth Level0%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)Not applicable
RCC or MS Framed structure0%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%
Handover0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes0%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes0%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallNoNot applicable
Outdoor Sports facilityYes0%
Indoor Sports facilityNoNot applicable
Swimming PoolYes0%
GymNoNot applicable
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership8

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area58,037 sq m
Named landowners8
LandownerVillageDistrict
Embassy Developments Limited--
Embassy Developments Limited--
Embassy Developments Limited--
Embassy Developments Limited--
Embassy Developments Limited--
Embassy Developments Limited--
Embassy Developments Limited--
Embassy Developments Limited--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 921.20 cr
Cost incurredRs 115.60 cr
Spent of the estimate12.55%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 774.00 crRs 99.64 cr
Marketing costRs 108.00 cr-
Administrative costRs 39.20 cr-
Payment of taxes-Rs 4.80 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJayant Vaitha
EngineerASHOK KANNAN
Chartered AccountantRavindranath N

Litigation declared7

CaseCourtStatus
O.S. 350/12The Senior Civil Judge , Devanahalli-
O.S. 774/14Suit for Partition-
O.S. 348/15Senior Civil Judge Devanahalli-
O.S 152/16Additional Civil Judge & JMFC Devanahalli-
RFA.No.1741/2018 (OS.No.752/2015)The High Court of Karnataka-
O.S. 385/2019/2019The Principal Civil Judge & JMFC, Devanahalli-
R.F.A.No.2259/2019/2019The High Court of Karnataka-

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed179

As listed on the registration, under the names the promoter filed them with; the newest 80 of 179 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/303/PR/201125/008265 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Embassy Greenshore_CA Certificate_Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Embassy Greenshore_Architect Certificate_Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Embassy Greenshore_Engineer Certificate_Q2 26-27.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Embassy Greenshore_CA Certificate_1st Qtly_FY 2026-27 2.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Emabssy Greenshore_Architect Certificate_1st Qtly_FY 2026-27.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Emabssy Greenshore_Engieer Certificate_1st Qtly_FY 2026-27.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Embassy Greenshore_CA Certificate_4th Qtly_FY 2025-26_Mar 26.pdf14 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Embassy Greenshore_Architect Certificate_4th Qtly_FY 2025-26_Mar 26.pdf14 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Embassy Greenshore_Engineer Certificate_4th Qtly_FY 2025-26_Mar 26.PDF14 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Embassy Greenshore_CA Certificate_Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Embassy Greenshore_Architect Certificate_Q3 25-26.pdf15 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Embassy Greenshore_Engineer Certificate_Q3 25-26.pdf15 Jan 2026
Embassy Greenshore_Response letter to KRERA against the queriesFile: 1 Embassy Greenshore_Response letter to KRERA against the queries.pdf17 Nov 2025
Embassy Greenshore_Response to query received on tower unitsFile: 2 Embassy Greenshore_Response to query received on tower units.pdf17 Nov 2025
Embassy Greenshore Water NOC and source of water clarificationFile: 3 Embassy Greenshore Water NOC and source of water clarification.pdf17 Nov 2025
Embassy Greenshore_MOEF NOC Fee paid receipt and DeclarationFile: 5 Embassy Greenshore_MOEF NOC Fee paid receipt and Declaration.pdf17 Nov 2025
RTC, survey 44/1 (P)-
Mutation, survey 44/1 (P)-
Encumbrance Certificate, survey 44/1 (P)-
Conversion/Alienation Order, survey 44/1 (P)-
Sale/Title/Gift Deed, survey 44/1 (P)-
Khatha, survey 44/1 (P)-
RTC, survey 45/1-
Mutation, survey 45/1-
Encumbrance Certificate, survey 45/1-
Conversion/Alienation Order, survey 45/1-
Sale/Title/Gift Deed, survey 45/1-
Khatha, survey 45/1-
RTC, survey 45/2 (P)-
Mutation, survey 45/2 (P)-
Encumbrance Certificate, survey 45/2 (P)-
Conversion/Alienation Order, survey 45/2 (P)-
Sale/Title/Gift Deed, survey 45/2 (P)-
Khatha, survey 45/2 (P)-
RTC, survey 46-
Mutation, survey 46-
Encumbrance Certificate, survey 46-
Conversion/Alienation Order, survey 46-
Sale/Title/Gift Deed, survey 46-
Khatha, survey 46-
RTC, survey 56/1 (P)-
Mutation, survey 56/1 (P)-
Encumbrance Certificate, survey 56/1 (P)-
Conversion/Alienation Order, survey 56/1 (P)-
Sale/Title/Gift Deed, survey 56/1 (P)-
Khatha, survey 56/1 (P)-
RTC, survey 57/1 (P)-
Mutation, survey 57/1 (P)-
Encumbrance Certificate, survey 57/1 (P)-
Conversion/Alienation Order, survey 57/1 (P)-
Sale/Title/Gift Deed, survey 57/1 (P)-
Khatha, survey 57/1 (P)-
RTC, survey 57/3 (P)-
Mutation, survey 57/3 (P)-
Encumbrance Certificate, survey 57/3 (P)-
Conversion/Alienation Order, survey 57/3 (P)-
Sale/Title/Gift Deed, survey 57/3 (P)-
Khatha, survey 57/3 (P)-
RTC, survey 57/4 (P)-
Mutation, survey 57/4 (P)-
Encumbrance Certificate, survey 57/4 (P)-
Conversion/Alienation Order, survey 57/4 (P)-
Sale/Title/Gift Deed, survey 57/4 (P)-
Khatha, survey 57/4 (P)-
Registration CertificateFile: Embassy Greenshore_Certificate of Incorporation_complete set of doc.pdf-
Memorandum of AssociationFile: EDL_MOA and AOA.pdf-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 under way, not due yet
ProjectLocationStatusPromisedDelivered
EMBASSY VERDEKHATA NO. 175/106/A1, 338/59/7/A2 & 338/59/8/A3, IN SY.NO. 57/3, 57/4, 58/1, 59/2, 59/3, 59/4, 59/5, 59/6, 59/7, 59/8 OF HEGGANAHALLI VILLAGE AND , SY.NOs. 94,95,96,97,99,100,103, 106,109,112,116,119&122 OF NAGAMANGALA VILLAGE , Devanahalli , Bengaluru RuralOngoingDec 2030Not due yet
EMBASSY PARADISOSy Nos. 73, 75, 76, 117, 118, 120, 121, 123, 124, 126, 127, 129, 130, 132, 133, 135, 136, 138, 139, 141, 142 OF NAGAMANGALA VILLAGE , KUNDANA HOBLI , Devanahalli , Bengaluru Rural, Karnataka - 562157OngoingAug 2027Not due yet

How this compares with Bengaluru Rural

71%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep EMBASSY GREENSHORE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmEMBASSY GREENSHOREOther 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: EMBASSY DEVELOPMENTS LIMITED

EMBASSY DEVELOPMENTS LIMITED has 5 registrations on RERA Karnataka, including EMBASSY VERDE and Embassy Springs - Phase 2A, Apartments. Its filings declare 4 earlier projects, none of them declared completed. Litigation is declared on 5 of its registrations. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if EMBASSY GREENSHORE is delayed beyond 31 Dec 2031?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of EMBASSY GREENSHORE?

The registered promoter entity is EMBASSY DEVELOPMENTS LIMITED, a company as per the filing. Its CIN L45101HR2006PLC095409 and GSTIN 29AABCI5194F1ZE can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in EMBASSY GREENSHORE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at EMBASSY GREENSHORE?

The professionals named in the filing: Architect: Jayant Vaitha; Engineer: ASHOK KANNAN; Chartered Accountant: Ravindranath N. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EMBASSY GREENSHORE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EMBASSY GREENSHORE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EMBASSY GREENSHORE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.