RG-KA-82057 · RERA PRM/KA/RERA/1251/309/PR/210524/006929 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Assetz Sora & Saki Phase 2 is a Residential/Group Housing project by NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/210524/006929 on 21 May 2024. Possession is promised by 31 Jul 2029. 242 of the 634 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.
At a glance
Project
- NameAssetz Sora & Saki Phase 2
- TypeResidential/Group Housing
- Location
- Bengaluru North
- Bengaluru Urban
- 562110
- Pincode562110
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/309/PR/210524/006929
- ReraGenie IDRG-KA-82057
Builder
- NameNETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
- Entity typeCompany
- CINU72200KA2004PTC033597
- GSTIN29AADCN7046D1ZG
- Authorized SignatoryNARASARAJU MADHAVA RAJU
- DirectorsNARASARAJU MADHAVA RAJU, NARASA KESHAVA RAJU, NARASARAJU MADHAVA RAJU, SRIDHAR RAJU RAMARAJU, VEENA KESHAVA RAJU
- Project HeadGurumoorthy. N
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on21 May 2024
- Promised completion31 Jul 2029
- Revised completionNone
- Buildings3 building records
- Documents filed152 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A3 | - | - | - | 205 | 0 | 205 |
| WING A4 | - | - | - | 215 | 0 | 215 |
| WING A5 | - | - | - | 214 | 0 | 214 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 30%.
Building: 24% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 30% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 40% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 10% |
| Energy management | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 15% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | Yes | 40% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED | - | - |
| NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED | - | - |
| NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED | - | - |
| NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED | - | - |
| NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 216.86 cr | Rs 49.25 cr |
| On-site expenditure-Site Overhead | Rs 58.12 cr | Rs 16.14 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 10.00 cr | Rs 5.27 cr |
| Approval cost | Rs 5.69 cr | Rs 9.67 lakh |
| On-site expenditure-Consultants Fees | Rs 1.42 cr | Rs 87.34 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sandeep Rajendran |
| Engineer | B E Pruthviraja |
| Chartered Accountant | Y S Shetty & Company |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed152
As listed on the registration, under the names the promoter filed them with; the newest 80 of 152 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/210524/006929 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra-compressed.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Sora & Saki Phase 2.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf | 14 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Sora & Saki Phase 2.pdf | 14 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 14 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 14 Jul 2026 |
| Q1 2026-27 Fire and Safety | 14 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 14 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 14 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra.pdf | 27 May 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf | 27 May 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer certificate Ph 2.pdf | 27 May 2026 |
| Q4 2025-26 Water supply and sewage board | 27 May 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 27 May 2026 |
| Q4 2025-26 KPTCL- BESCOM | 27 May 2026 |
| Q4 2025-26 Fire and Safety | 27 May 2026 |
| Q4 2025-26 Airport Authority of India | 27 May 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 27 May 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra.pdf | 16 Jan 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf | 16 Jan 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer certifiacte Ph 2.pdf | 16 Jan 2026 |
| Q3 2025-26 Water supply and sewage board | 16 Jan 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 16 Jan 2026 |
| Q3 2025-26 KPTCL- BESCOM | 16 Jan 2026 |
| Q3 2025-26 Fire and Safety | 16 Jan 2026 |
| Q3 2025-26 Airport Authority of India | 16 Jan 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 16 Jan 2026 |
| Financial with Schedule 2022-23File: Annexure 1-Financial with Schedule 2022-23.pdf | 20 May 2024 |
| Source of Funds V1_Phase 2File: Annexure 2-Source of Funds V1_Phase 2.pdf | 20 May 2024 |
| Area DetailsFile: Annexure 3-Area Details.pdf | 20 May 2024 |
| FAR DetailsFile: Annexure 4-FAR Details.pdf | 20 May 2024 |
| Single layout PlanFile: Annexure 5-Single layout Plan.pdf | 20 May 2024 |
| Single Layout orderFile: Annexure 6-Single Layout order.pdf | 20 May 2024 |
| Villlage MapFile: Annexure 7-Villlage Map.pdf | 20 May 2024 |
| Commencement LetterFile: Annexure 8-Commencement Letter.pdf | 20 May 2024 |
| Height ClarificationFile: Annexure 9-Height Clarification.pdf | 20 May 2024 |
| Building LicenseFile: Annexure 10-Building License.pdf | 20 May 2024 |
| Site PlanFile: Annexure 11a-Site Plan.pdf | 20 May 2024 |
| -BasementFile: Annexure 11b-Basement.pdf | 20 May 2024 |
| Ground FloorFile: Annexure 11c-Ground Floor.pdf | 20 May 2024 |
| Typical 15 to 18 Floor & terrance PlanFile: Annexure 11d-Typical 15 to 18 Floor & terrance Plan.pdf | 20 May 2024 |
| First Floor & Typical 2nd to 13File: Annexure 11e-First Floor & Typical 2nd to 13.pdf | 20 May 2024 |
| Sectional DrawingsFile: Annexure 11f-Sectional Drawings.pdf | 20 May 2024 |
| DWG 7_Layout - A0107File: Annexure 11g-DWG 7_Layout - A0107.pdf | 20 May 2024 |
| Sectional & Elevation site key planFile: Annexure 11h-Sectional & Elevation site key plan.pdf | 20 May 2024 |
| Floor PlansFile: Annexure 12-Floor Plan.pdf | 20 May 2024 |
| Common Area detailsFile: Annexure 13-Common Area details.pdf | 20 May 2024 |
| Engineer LicenseFile: Annexure 14-Engineer License.pdf | 20 May 2024 |
| Engineer LicenseFile: Annexure 14-Engineer License.pdf | 20 May 2024 |
| Cost of constructionFile: Annexure 15-Cost of construction.pdf | 20 May 2024 |
| Agreement to saleFile: Annexure 16a-ATS.pdf | 20 May 2024 |
| Allotement LetterFile: Annexure 16b-Allotement Letter.pdf | 20 May 2024 |
| Land CostFile: Annexure 17-Land Cost.pdf | 20 May 2024 |
| Water PermissionFile: Annexure 18-Water Permission.pdf | 20 May 2024 |
| Airospace NOCFile: Airospace NOC Clarification.pdf | 20 May 2024 |
| relinquishment DeedFile: Reliquishment deed.pdf | 20 May 2024 |
| RTC, survey 176 | - |
| Mutation, survey 176 | - |
| Encumbrance Certificate, survey 176 | - |
| Conversion/Alienation Order, survey 176 | - |
| Sale/Title/Gift Deed, survey 176 | - |
| Khatha, survey 176 | - |
| RTC, survey 177 | - |
| Mutation, survey 177 | - |
| Encumbrance Certificate, survey 177 | - |
| Conversion/Alienation Order, survey 177 | - |
| Sale/Title/Gift Deed, survey 177 | - |
| Khatha, survey 177 | - |
| RTC, survey 470 | - |
| Mutation, survey 470 | - |
| Encumbrance Certificate, survey 470 | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Assetz Sora & Saki Phase 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 24 registered projects within 2 km.
BARCA AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
Prestige Parklane
APEX REALTY MANAGEMENT PRIVATE LIMITED
Sattva Vasanta Skye
Sattva Resi Private Limited
EMBASSY GREENSHORE
EMBASSY DEVELOPMENTS LIMITED
EMBASSY VERDE PHASE 2
EMBASSY DEVELOPMENTS LIMITED
BARCA II AT GODREJ MSR CITY
M S RAMAIAH VENTURES LLP
See every Bengaluru Urban project, with the district possession charts
Builder: NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED has 2 registrations on RERA Karnataka, including ASSETZ SORA & SAKI Phase 1 and Assetz Sora & Saki Phase 2. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Assetz Sora & Saki Phase 2 is delayed beyond 31 Jul 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Assetz Sora & Saki Phase 2?
The registered promoter entity is NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED, a company as per the filing. Its CIN U72200KA2004PTC033597 and GSTIN 29AADCN7046D1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Assetz Sora & Saki Phase 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Assetz Sora & Saki Phase 2?
The professionals named in the filing: Architect: Sandeep Rajendran; Engineer: B E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Assetz Sora & Saki Phase 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback