ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / Assetz Sora & Saki Phase 2

Registration approved No litigation declared Residential/Group Housing project

Assetz Sora & Saki Phase 2

By NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED

RG-KA-82057 · RERA PRM/KA/RERA/1251/309/PR/210524/006929 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jul 2029Possession promisedno revision filed
4 of 18Construction stages donefurthest along: RCC or MS Framed structure, 30%
392 of 634Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 152 documents Report an error

Assetz Sora & Saki Phase 2 is a Residential/Group Housing project by NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/309/PR/210524/006929 on 21 May 2024. Possession is promised by 31 Jul 2029. 242 of the 634 units on this registration are recorded sold or booked, and 4 of 18 construction stages are filed complete.

At a glance

Project

  • NameAssetz Sora & Saki Phase 2
  • TypeResidential/Group Housing
  • Location
    • Bengaluru North
    • Bengaluru Urban
    • 562110
  • Pincode562110
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/309/PR/210524/006929
  • ReraGenie IDRG-KA-82057

Builder

  • NameNETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED
  • Entity typeCompany
  • CINU72200KA2004PTC033597
  • GSTIN29AADCN7046D1ZG
  • Authorized SignatoryNARASARAJU MADHAVA RAJU
  • DirectorsNARASARAJU MADHAVA RAJU, NARASA KESHAVA RAJU, NARASARAJU MADHAVA RAJU, SRIDHAR RAJU RAMARAJU, VEENA KESHAVA RAJU
  • Project HeadGurumoorthy. N
  • Other registrations1 more →

Key dates

this monthRegisteredMay 2024PromisedJul 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on21 May 2024
  • Promised completion31 Jul 2029
  • Revised completionNone
  • Buildings3 building records
  • Documents filed152 files

Current status

38%242 of 634 units booked
24.5%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING A3---2050205
WING A4---2150215
WING A5---2140214

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 18 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 30%.

Building: 24% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)100%
RCC or MS Framed structure30%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes40%
Sewage and Drainage SystemYes0%
Water conservation/rain water harvesting/recharge of ground waterYes10%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes15%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes0%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes40%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningYes0%
StaircasesYes0%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffYes0%
Water conservation and renewable energyYes0%
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,917 sq m
Named landowners5
LandownerVillageDistrict
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED--
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED--
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED--
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED--
NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 292.09 cr
Cost incurredRs 71.63 cr
Spent of the estimate24.52%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 216.86 crRs 49.25 cr
On-site expenditure-Site OverheadRs 58.12 crRs 16.14 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 10.00 crRs 5.27 cr
Approval costRs 5.69 crRs 9.67 lakh
On-site expenditure-Consultants FeesRs 1.42 crRs 87.34 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Rajendran
EngineerB E Pruthviraja
Chartered AccountantY S Shetty & Company

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed152

As listed on the registration, under the names the promoter filed them with; the newest 80 of 152 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/309/PR/210524/006929 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra-compressed.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Sora & Saki Phase 2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra.pdf14 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf14 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) Sora & Saki Phase 2.pdf14 Jul 2026
Q1 2026-27 Water supply and sewage board14 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)14 Jul 2026
Q1 2026-27 KPTCL- BESCOM14 Jul 2026
Q1 2026-27 Fire and Safety14 Jul 2026
Q1 2026-27 Airport Authority of India14 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department14 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra.pdf27 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf27 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer certificate Ph 2.pdf27 May 2026
Q4 2025-26 Water supply and sewage board27 May 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)27 May 2026
Q4 2025-26 KPTCL- BESCOM27 May 2026
Q4 2025-26 Fire and Safety27 May 2026
Q4 2025-26 Airport Authority of India27 May 2026
Q4 2025-26 BSNL/Telecommunication Department27 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form_4_CA _Phase-2 Netra.pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Sora & Saki Phase 2.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Engineer certifiacte Ph 2.pdf16 Jan 2026
Q3 2025-26 Water supply and sewage board16 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)16 Jan 2026
Q3 2025-26 KPTCL- BESCOM16 Jan 2026
Q3 2025-26 Fire and Safety16 Jan 2026
Q3 2025-26 Airport Authority of India16 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department16 Jan 2026
Financial with Schedule 2022-23File: Annexure 1-Financial with Schedule 2022-23.pdf20 May 2024
Source of Funds V1_Phase 2File: Annexure 2-Source of Funds V1_Phase 2.pdf20 May 2024
Area DetailsFile: Annexure 3-Area Details.pdf20 May 2024
FAR DetailsFile: Annexure 4-FAR Details.pdf20 May 2024
Single layout PlanFile: Annexure 5-Single layout Plan.pdf20 May 2024
Single Layout orderFile: Annexure 6-Single Layout order.pdf20 May 2024
Villlage MapFile: Annexure 7-Villlage Map.pdf20 May 2024
Commencement LetterFile: Annexure 8-Commencement Letter.pdf20 May 2024
Height ClarificationFile: Annexure 9-Height Clarification.pdf20 May 2024
Building LicenseFile: Annexure 10-Building License.pdf20 May 2024
Site PlanFile: Annexure 11a-Site Plan.pdf20 May 2024
-BasementFile: Annexure 11b-Basement.pdf20 May 2024
Ground FloorFile: Annexure 11c-Ground Floor.pdf20 May 2024
Typical 15 to 18 Floor & terrance PlanFile: Annexure 11d-Typical 15 to 18 Floor & terrance Plan.pdf20 May 2024
First Floor & Typical 2nd to 13File: Annexure 11e-First Floor & Typical 2nd to 13.pdf20 May 2024
Sectional DrawingsFile: Annexure 11f-Sectional Drawings.pdf20 May 2024
DWG 7_Layout - A0107File: Annexure 11g-DWG 7_Layout - A0107.pdf20 May 2024
Sectional & Elevation site key planFile: Annexure 11h-Sectional & Elevation site key plan.pdf20 May 2024
Floor PlansFile: Annexure 12-Floor Plan.pdf20 May 2024
Common Area detailsFile: Annexure 13-Common Area details.pdf20 May 2024
Engineer LicenseFile: Annexure 14-Engineer License.pdf20 May 2024
Engineer LicenseFile: Annexure 14-Engineer License.pdf20 May 2024
Cost of constructionFile: Annexure 15-Cost of construction.pdf20 May 2024
Agreement to saleFile: Annexure 16a-ATS.pdf20 May 2024
Allotement LetterFile: Annexure 16b-Allotement Letter.pdf20 May 2024
Land CostFile: Annexure 17-Land Cost.pdf20 May 2024
Water PermissionFile: Annexure 18-Water Permission.pdf20 May 2024
Airospace NOCFile: Airospace NOC Clarification.pdf20 May 2024
relinquishment DeedFile: Reliquishment deed.pdf20 May 2024
RTC, survey 176-
Mutation, survey 176-
Encumbrance Certificate, survey 176-
Conversion/Alienation Order, survey 176-
Sale/Title/Gift Deed, survey 176-
Khatha, survey 176-
RTC, survey 177-
Mutation, survey 177-
Encumbrance Certificate, survey 177-
Conversion/Alienation Order, survey 177-
Sale/Title/Gift Deed, survey 177-
Khatha, survey 177-
RTC, survey 470-
Mutation, survey 470-
Encumbrance Certificate, survey 470-

How this compares with Bengaluru Urban

38%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Assetz Sora & Saki Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAssetz Sora & Saki PhaseOther 24Dot size: filed unitsN

Filed coordinates, straight-line distance. 24 registered projects within 2 km.

Builder: NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED

NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED has 2 registrations on RERA Karnataka, including ASSETZ SORA & SAKI Phase 1 and Assetz Sora & Saki Phase 2. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Assetz Sora & Saki Phase 2 is delayed beyond 31 Jul 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Assetz Sora & Saki Phase 2?

The registered promoter entity is NETRA SOFTWARE TECHNOLOGIES PRIVATE LIMITED, a company as per the filing. Its CIN U72200KA2004PTC033597 and GSTIN 29AADCN7046D1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Assetz Sora & Saki Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Assetz Sora & Saki Phase 2?

The professionals named in the filing: Architect: Sandeep Rajendran; Engineer: B E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Assetz Sora & Saki Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Assetz Sora & Saki Phase 2. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Assetz Sora & Saki Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.