ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / The Residency

Registration lapsed No litigation declared Residential / Group Housing project

The Residency

By Lak & Hanware Realty LLP

RG-MH-11991 · RERA P51800004331 · Last updated on MahaRERA portal: 13 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • 4 complaints at MahaRERA
  • Completion date moved by 60 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 90%
21 of 130Units unsoldnot recorded sold or booked
4Complaints at MahaRERAon this registration
Jump to the 188 documents Report an error

The Residency is a Residential / Group Housing project by Lak & Hanware Realty LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004331 on 9 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 60 months from the original filing. 109 of the 130 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • NameThe Residency
  • TypeResidential / Group Housing
  • Location
    • JOGESHWARI WEST
    • KEVANIPADA
    • Andheri
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004331
  • ReraGenie IDRG-MH-11991

Builder

  • NameLak & Hanware Realty LLP
  • Entity typePartnership
  • PartnersNIYAZ AHMED ABDULLAH HANWARE, LIYAKAT ALI KHAN

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on9 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed188 files

Current status

84%109 of 130 units booked
101.0%Work done, per cost certificate

Figures as on 13 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
The ResidencyNA26201300130

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

The Residency: 93% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 13 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed56

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots56
Closed/Covered56

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,811 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on8 Jul 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI7428.38
Proposed, not sanctioned6,194 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround floor, Dheeraj Heritage, Daulat Nagar Santacruz West
Estimated costRs 52.51 cr
Cost incurredRs 53.02 cr
Work done100.97%
BuildingWingEstimatedIncurred
The ResidencyNARs 52.31 crRs 53.02 cr
-NARs 20.00 lakh-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMOHAMMED YAKUB KHAN OF M V AND ASSOCIATES
EngineerMR NIYAZ HANWARE of HANWARE CONSULTANTS
EngineerSupCons Consultants
EngineerMOHAMMAD IRFAN SHAIKH
Chartered AccountantJAVED A KAZI
Chartered AccountantP.S.SAKHALKAR & CO
PartnerRole in project
Lak & Hanware Realty LLP-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800012191Jun 2021 → Jun 2023

Reason as filed by the promoter100% construction of Sale building "B" & "C" is completed. Also for Rehab building construction work up to 14th floor has been completed. Also we have applied for OC for "B' & "C" wing. We have received CC up to 18th Floor for rehab building - A Wing. For completing the pending work we need extension.

EXT51800009750Jun 2021 → Dec 2021

Reason as filed by the promoterDUE TO THE COVID-19 PANDEMIC LOCKDOWN.

EXT51800022950Jun 2021 → Jun 2025

Reason as filed by the promoterWe like to inform you that we have completed 100% of sale building “B” & “C” wings & Rehab Building “A” wing up to 14th Floor and we have received Part O.C. till 10th Floor. We have received Full C.C. up to 18th Floor of A-wing which will be completed by June-2025. Therefore, kindly give extension for “A” wing only from 15th floor to 18th Floor till June-2025.

EXT51800016605Jun 2021 → Jun 2024

Reason as filed by the promoterA fire NOC is pending due to a tree that lies between the center of the upcoming road, Road has already been handed over to BMC, but because of Tree Fire Department not issuing NOC. And because of the Absence of NOC, Now for Additional Five floors above the Rehab building are pending to be Constructed, For this purpose we require MahaRERA Extension.

EA10072502038Jun 2021 → Jun 2026

Reason as filed by the promoterDue to the Eligibility (Patrata) issues concerning three hutments located on the road, the Commencement Certificate (C.C.) for the extension of 19th and 20th floors (Sale Components) of Wing ‘A’ (Which is a rehab building up to the 14th floor) was delayed. We have already received LOI - SRA/ENG/2799/KW/PL/LOI. dtd- 21.07.2025 and anticipate receiving the C.C. for the 19th and 20th floors by 30th July 2025. The extension is required only for the 19th & 20th floors of Wing ‘A’.

Complaints filed with MahaRERA4

Case no.ComplainantRespondentFiled
CC12504014Lak & Hanware Realty LLPIsmail Haroon Bachaw14/11/2025
CC12602399SATISH LAXMAN RAUTLak & Hanware Realty LLP24/04/2026
CC12603522Pradeep M BedreLak & Hanware Realty LLP07/06/2026
CC12604450ZAHARA FIROZ RANGWALALak & Hanware Realty LLP17/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Apr 2024

Documents filed188

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 188 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: CC Final upto 20th Floor.pdf13 Jan 2026
Withdrawal Update Form 1File: Form 1 Sept-25.pdf13 Jan 2026
Withdrawal Update Form 2File: July-Sept-2025-Form2.pdf13 Jan 2026
Withdrawal Update Form 3File: July-Sept-2025-Form3.pdf13 Jan 2026
Withdrawal Update Form 1File: Form 1 Jun-25.pdf9 Jan 2026
Withdrawal Update Form 2File: Apr-June-2025-Form2.pdf9 Jan 2026
Withdrawal Update Form 3File: Apr-Jun-2025-Form3.pdf9 Jan 2026
Form 5 (FY 2024-2025)File: FY-2025-Form5-PS.pdf9 Jul 2025
Form 1File: RERA Form 1 Mar 2025.pdf8 Jul 2025
Form 2File: FORM 2 ENGINEER CERTIFICATE MARCH 2025.pdf8 Jul 2025
Form 3File: Jan-Mar-2025-Form3.pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Sol Unsold Jan-Mar-2025.pdf8 Jul 2025
Form 2A (FY 2024-2025)8 Jul 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and booked Updated 300624.pdf7 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and booked Updated 300924.pdf7 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and booked Updated 311224.pdf7 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form1- June 2024.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form1- Sept 2024.pdf6 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Form1- Dec 2024.pdf6 Feb 2025
Certificates of CA (Form 3)File: Apr-June-2024-Form3.pdf6 Feb 2025
Certificates of CA (Form 3)File: July-Sept-2024-Form3.pdf6 Feb 2025
Certificates of CA (Form 3)File: Oct-Dec-2024-Form3.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-June-2024-Form2.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: July-Sept-2024-Form2.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2024-Form2.pdf6 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jan-Mar-2024-Form2.pdf13 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FY-2023-2024-Form2A.pdf13 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and booked Updated 310324.pdf13 Jun 2024
Certificates of CA (Form 3)File: Jan-Mar-2024-Form3.pdf13 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FY-2024-Form5-PS.pdf13 Jun 2024
Declaration in FORM BFile: AFFIDAVIT CUM DECLARATION JUNE 2024.pdf11 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Jan-Mar-24.pdf11 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: CC_Latest_07052024.pdf5 Jun 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: The Residency Part OC.pdf4 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and booked Updated 300923.pdf1 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and booked Updated 311223.pdf1 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240320_0553.pdf20 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240320_0554.pdf20 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 20240320_0555.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240320_0556.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240320_0557.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 20240320_0558.pdf20 Mar 2024
Certificates of CA (Form 3)File: June-23.pdf9 Mar 2024
Certificates of CA (Form 3)File: Sept-23.pdf9 Mar 2024
Certificates of CA (Form 3)File: Dec-23.pdf9 Mar 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Jan-Mar-2023-Form1.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-Jun-2022-Form2.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jul-Sept-2022-Form2.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2022-Form2.pdf7 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jan-Mar-2023-Form2.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FY-2022-2023-Form2A.pdf7 Jul 2023
Disclosure of sold/ booked inventoryFile: DisclosureSoldUnsold26062023.pdf7 Jul 2023
Certificates of CA (Form 3)File: Apr-Jun-2022-Form3.pdf7 Jul 2023
Certificates of CA (Form 3)File: Jul-Sept-2022-Form3.pdf7 Jul 2023
Certificates of CA (Form 3)File: Oct-Dec-2022-Form3.pdf7 Jul 2023
Certificates of CA (Form 3)File: Jan-Mar-2023-Form3.pdf7 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FY-2023-Form5-PS.pdf7 Jul 2023
Declaration in FORM BFile: RERA decleration cum Affidavit.pdf6 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jan-Mar-2021-Form2.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-Jun-2021-Form2.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jul-Sept-2021-Form2.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2021-Form2.pdf13 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jul-Sept-2017.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2017.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-Jun-2018.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2018.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jan-Mar-2019.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-Jun-2019.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jul-Sept-2019.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2019.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jan-Mar-2020.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Apr-Jun-2020.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Jul-Sept-2020.pdf11 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Oct-Dec-2020.pdf11 Apr 2023
Form 2AFile: Jan-Mar-2019.pdf8 Apr 2023
Form 2AFile: Apr-Jun-2019.pdf8 Apr 2023
Form 2AFile: Jul-Sept-2019.pdf8 Apr 2023
Form 2AFile: Oct-Dec-2019.pdf8 Apr 2023
Form 2AFile: Jan-Mar-2020.pdf8 Apr 2023
Form 2AFile: Apr-Jun-2020.pdf8 Apr 2023

How this compares with Mumbai Suburban

84%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 60 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KEVANIPADA6,700+ in Mumbai Suburban

2 kmThe ResidencyCompleted 122Lapsed / revoked 94Abeyance 1Other 150Dot size: filed unitsN

Filed coordinates, straight-line distance. 367 registered projects within 2 km.

Builder: Lak & Hanware Realty LLP

Lak & Hanware Realty LLP has 1 registration on MahaRERA, including The Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that The Residency shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if The Residency is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Residency?

The registered promoter entity is Lak & Hanware Realty LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against The Residency?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for The Residency?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Residency?

The professionals named in the filing: Architect: MOHAMMED YAKUB KHAN OF M V AND ASSOCIATES; Engineer: MR NIYAZ HANWARE of HANWARE CONSULTANTS; Engineer: SupCons Consultants; Engineer: MOHAMMAD IRFAN SHAIKH; Chartered Accountant: JAVED A KAZI; Chartered Accountant: P.S.SAKHALKAR & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Residency. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.