Red flags
- Registration lapsed
- Possession 7 months past the filed date
- Litigation declared, 5 cases
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE PORWAL SUITES is a Residential / Group Housing project by KISHOR SHESHMAL PORWAL in Pune, Maharashtra, registered with MahaRERA as P52100078463 on 12 Dec 2024. Possession was promised by 31 Mar 2026 and is now 7 months past that date.
At a glance
Project
- NameTHE PORWAL SUITES
- TypeResidential / Group Housing
- Location
- Gaothan Area Bhamburda
- SHIVAJI NAGAR
- Haveli
- Pune
- 411005
- Pincode411005
- RERA no.P52100078463
- ReraGenie IDRG-MH-19334
Builder
- NameKISHOR SHESHMAL PORWAL
- Entity typeIndividual
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Dec 2024
- Promised completion31 Mar 2026
- Revised completionNone
- Buildings1 building record
- Documents filed24 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE PORWAL SUITES | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 9 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.
THE PORWAL SUITES: 9% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 95% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 9 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed25
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership22
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Kiran Digambar Rasane | Chinchwad | Pune |
| Arun Digambar Rasane | Pune (M Corp.) | Pune |
| Suman Sadashiv Gambhir | Pune (M Corp.) | Pune |
| Sharad Suresh Kundup | Pimpri Chinchawad (M Corp.) | Pune |
| Neha Naresh Natu | Pimpri Chinchawad (M Corp.) | Pune |
| Sushama Sudhakar Palkar | Baramati (M Cl) | Pune |
| Santosh Gopal Rasane | Pimpri Chinchawad (M Corp.) | Pune |
| Hemlata Gopal Rasane | Pimpri Chinchawad (M Corp.) | Pune |
| Shobha Nandkumar Mangale | Isbavi | Solapur |
| Sanjay Prabhakar Rasane | Pune (M Corp.) | Pune |
| Deepak Prabhakar Rasane | Pune (M Corp.) | Pune |
| Prakash Prabhkar Rasane | Pune (M Corp.) | Pune |
| Pranjal Anil Rasane | Pune (M Corp.) | Pune |
| Sameer Anil Rasane | Pune (M Corp.) | Pune |
| Alka Anil Rasane | Pune (M Corp.) | Pune |
| Shushila Prabhakar Rasane | Pune (M Corp.) | Pune |
| Mangala Balwant Palkar | Satara | Satara |
| Pushpalata Balwant Palkar | Satara | Satara |
| Pramod Vasant Rasane | Pune (M Corp.) | Pune |
| Vilas Vasant Rasane | Pune (M Corp.) | Pune |
| Satish Vasant Rasane | Pune (M Corp.) | Pune |
| Subhash Vasant Rasane | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Hemant Mahatekkar |
| Engineer | Sagar Jagdale |
| Chartered Accountant | Archana Kakade |
| Partner | Role in project |
|---|---|
| KISHOR SHESHMAL PORWAL | - |
Litigation declared5
| Case | Court | Status |
|---|---|---|
| 6/2022 | CJSD Pune | Evidence |
| 8/2022 | CJSD Pune | Evidence |
| 9/2022 | CJSD Pune | Evidence |
| 10/2022 | CJSD Pune | Evidence |
| 246/2022 | CJSD Pune | Evidence |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 2 Nov 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 Nov 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed24
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Other - TechnicalFile: document_1 (1).pdf | 9 Dec 2024 |
| Building plan approvalFile: scan 14.pdf | 3 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: scan 14.pdf | 3 Dec 2024 |
| Other - TechnicalFile: file.pdf | 27 Nov 2024 |
| Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATES.pdf | 12 Feb 2024 |
| Declaration in FORM BFile: FORM B- Declaration.pdf | 12 Feb 2024 |
| CERSAI detailsFile: CERSAI details.pdf | 12 Feb 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATES.pdf | 12 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: SEPARATE BANK ACCOUNT RERA.pdf | 1 Feb 2024 |
| Building plan approvalFile: scan 15.pdf | 2 Nov 2023 |
| Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf | 2 Nov 2023 |
| PAN CardFile: 1 PAN Card.pdf | 2 Nov 2023 |
| Copy of the legal title reportFile: 1 Copy of the legal title report.pdf | 2 Nov 2023 |
| Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf | 2 Nov 2023 |
| Proforma of Allotment letterFile: 1 Proforma of Allotment letter.pdf | 2 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf | 2 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SKM_36724092018500.pdf | 2 Nov 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: scan 15.pdf | 2 Nov 2023 |
| Other - LegalFile: 1 Other - Legal.pdf | 2 Nov 2023 |
| Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate (1).pdf | 2 Nov 2023 |
| Deviation Report with respect to Allotment letterFile: 1 Deviation Report with respect to Allotment letter.pdf | 2 Nov 2023 |
| Deviation Report with respect to model copy of AgreementFile: 1 Deviation Report with respect to model copy of Agreement.pdf | 2 Nov 2023 |
| Proforma of Agreement for saleFile: 1 Proforma of Agreement for sale.pdf | 2 Nov 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations.pdf | 2 Nov 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- All 24 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep THE PORWAL SUITES on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near SHIVAJI NAGAR13,700+ in Pune
VENKATESH LAUREL
SHREE VENKATESH BUILDCON PVT LTD
One Place - F C Road
PALASH REALTORS LLP
NIRMAN SHREYAS
PRIVEUS PROJECTS LLP
NEELRATNA
Kotibhaskar Infrastructures &Developers Pv
GBs Business Hub
Growstone Ventures LLP
SAI CHAMBERS
MILIND RAMKRISHNA UPASANI
Builder: KISHOR SHESHMAL PORWAL
KISHOR SHESHMAL PORWAL has 1 registration on MahaRERA, including THE PORWAL SUITES. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that THE PORWAL SUITES shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if THE PORWAL SUITES is delayed beyond 31 Mar 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE PORWAL SUITES?
The registered promoter entity is KISHOR SHESHMAL PORWAL, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE PORWAL SUITES?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for THE PORWAL SUITES?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE PORWAL SUITES?
The professionals named in the filing: Architect: Hemant Mahatekkar; Engineer: Sagar Jagdale; Chartered Accountant: Archana Kakade. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE PORWAL SUITES?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback