Home / Browse projects / Pune, Maharashtra / SAI CHAMBERS

Registered Litigation declared Residential / Group Housing project

SAI CHAMBERS

By MILIND RAMKRISHNA UPASANI

RG-MH-11095 · RERA P52100010639 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 1 complaint at MahaRERA
  • Completion date moved by 95 months
  • 6 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 95 months from the original
2 of 11Construction stages donefurthest along: Stilt Floor, 95%
53 of 66Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 316 documents Report an error

SAI CHAMBERS is a Residential / Group Housing project by MILIND RAMKRISHNA UPASANI in Pune, Maharashtra, registered with MahaRERA as P52100010639 on 31 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 95 months from the original filing. 13 of the 66 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAI CHAMBERS
  • TypeResidential / Group Housing
  • Location
    • Sr No. 83 F plot no. 819 part
    • Pune
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411005
  • Pincode411005
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010639
  • ReraGenie IDRG-MH-11095

Builder

  • NameMILIND RAMKRISHNA UPASANI
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJan 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 15 Jan 2019)
  • Buildings1 building record
  • Documents filed316 files

Current status

20%13 of 66 units booked
62.9%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAI CHAMBERSNA8695766

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

SAI CHAMBERS: 76% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises93%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.93%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes85%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed38

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots38
Closed/Covered38

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,058 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Sep 2025
LandownerVillageDistrict
Mr GANESH DNYANESHWAR CHAVANPune (M Corp.)Pune
Vishal Vijay Satpute-Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2709.3
Proposed, not sanctioned2,577 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchkasba peth
Estimated costRs 15.13 cr
Cost incurredRs 9.51 cr
Work done62.86%
BuildingWingEstimatedIncurred
SAI CHAMBERSNARs 14.13 crRs 8.64 cr
-NARs 1.00 crRs 87.34 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA H THITE
EngineerANIRUDHA VANARSE
EngineerYashdeep Jadon
Chartered AccountantRamesh Rahalkar
Chartered AccountantPushpa Bogati
Chartered AccountantSPAK & Co.
Chartered AccountantBogati & Co.
PartnerRole in project
MILIND RAMKRISHNA UPASANI-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001501Jan 2019 → Dec 2021

Reason as filed by the promoterDue to non-availability of skilled labours and quality material.

EXT52100005555Jan 2019 → Dec 2021

Reason as filed by the promoterDue to delay in sanction of addition of remaining 3 floors of TDR/TOD fsi of the project, we require additional two year to complete the project.

EXT52100013134Jan 2019 → Dec 2023

Reason as filed by the promoterDue to revised sanctioned obtained from Pune Municipal corporation vide commencement certificate number 10.8.2022 bearing number CC/1254/22 and due to additional units being sanctioned, we need to extend the project completion date for one more year.

EXT52100018462Jan 2019 → Dec 2024

Reason as filed by the promoterDELAY IN PMC SANCTION

EXT52100027440Jan 2019 → Dec 2025

Reason as filed by the promoterI was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the expansion.

EA31122519186Jan 2019 → Dec 2026

Reason as filed by the promoterI was planning to expand the project, but there was a delay in receiving the sanction plan from the local authority. This setback has postponed our project timeline as we need the official approval to proceed with the extension

Litigation declared1

CaseCourtStatus
2722/2025HIGH COURT OF BOMBAYOngoing

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501379Ganesh Dynaeshwar ChavanMILIND RAMKRISHNA UPASANI25/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Mar 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed316

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 316 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 _jun 26.pdf20 Jul 2026
Withdrawal Update Form 2File: Signed Form 2_Milind Upasani_Jun26 (1).pdf20 Jul 2026
Withdrawal Update Form 3File: Form 3 _jun 26 Sai chambers.pdf20 Jul 2026
Withdrawal Update Form 1File: fORM 1 _MAR 26 _ SAI CHAMBERS.pdf18 Apr 2026
Withdrawal Update Form 2File: Form 2 _mar 26 _milind upasani.pdf18 Apr 2026
Withdrawal Update Form 3File: Form 3_mar 26_milind upasani.pdf18 Apr 2026
Layout approvalFile: SHEET-1 Building layout_compressed.pdf28 Mar 2026
Building plan approvalFile: Sanction plan 2026 Pg 2.pdf28 Mar 2026
Building plan approvalFile: Sanction plan 2026 Pg 3.pdf28 Mar 2026
Building plan approvalFile: Sanction plan 2026 Pg 4.pdf28 Mar 2026
Withdrawal Update Form 1File: Form 1_Milind Upsani_Dec 2025.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2Dec 25_ Milind upasani.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3_Milind Upsani_Dec 2025.pdf20 Jan 2026
Form 1File: jun 18.pdf22 Nov 2025
Form 2File: jun 18.pdf22 Nov 2025
Form 3File: jun 18.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: Jun 2018.pdf22 Nov 2025
Form 1File: jun19.pdf22 Nov 2025
Form 2File: jun 19.pdf22 Nov 2025
Form 3File: jun 19.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: jun 19.pdf22 Nov 2025
Form 1File: jun 20.pdf22 Nov 2025
Form 2File: jun 20 (2).pdf22 Nov 2025
Form 3File: jun 20.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: jun 20.pdf22 Nov 2025
Form 1File: mar 21.pdf22 Nov 2025
Form 2File: mar 21 (2).pdf22 Nov 2025
Form 3File: mar 21.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: mar 21.pdf22 Nov 2025
Form 1File: jun 21.pdf22 Nov 2025
Form 2File: jun 21 (2).pdf22 Nov 2025
Form 3File: jun 21 (2).pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: jun 21.pdf22 Nov 2025
Form 1File: sep 21.pdf22 Nov 2025
Form 2File: sep 21 (3).pdf22 Nov 2025
Form 3File: sep 21.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: sep 21.pdf22 Nov 2025
Form 1File: dec 21.pdf22 Nov 2025
Form 2File: dec 21 (2).pdf22 Nov 2025
Form 3File: dec 21.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: dec 21.pdf22 Nov 2025
Form 1File: marr 22.pdf22 Nov 2025
Form 2File: mar 22.pdf22 Nov 2025
Form 3File: mar 22.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: mar 22.pdf22 Nov 2025
Form 1File: jun 22.pdf22 Nov 2025
Form 2File: jun 22.pdf22 Nov 2025
Form 3File: jun22.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: jun22.pdf22 Nov 2025
Form 1File: sep 22.pdf22 Nov 2025
Form 2File: sep 22.pdf22 Nov 2025
Form 3File: sep 22.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: sep22.pdf22 Nov 2025
Form 1File: dec 22.pdf22 Nov 2025
Form 2File: dec 22 (2).pdf22 Nov 2025
Form 3File: dec 22.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: dec 22.pdf22 Nov 2025
Form 1File: mar 23.pdf22 Nov 2025
Form 2File: mar 23.pdf22 Nov 2025
Form 3File: mar 23.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: mar 23.pdf22 Nov 2025
Form 1File: jun 23.pdf22 Nov 2025
Form 2File: jun 23.pdf22 Nov 2025
Form 3File: jun 23.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: jun 23.pdf22 Nov 2025
Form 1File: sep 23.pdf22 Nov 2025
Form 2File: sep 23.pdf22 Nov 2025
Form 3File: sep 23.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: sep 23.pdf22 Nov 2025
Form 1File: dec 23.pdf22 Nov 2025
Form 2File: dec 23.pdf22 Nov 2025
Form 3File: dec 23.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: dec 23.pdf22 Nov 2025
Form 1File: mar 24.pdf22 Nov 2025
Form 2File: mar 24.pdf22 Nov 2025
Form 3File: mar 24.pdf22 Nov 2025
Disclosure of Sold and Booked InventoryFile: mar 24.pdf22 Nov 2025
Form 1File: dec 24.pdf22 Nov 2025
Form 2File: dec 24.pdf22 Nov 2025
Form 3File: dec 24.pdf22 Nov 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
milind upasanibavadhan Khurd pune 214CompletedMar 2013Late, May 2013

How this compares with Pune

20%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 95 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI CHAMBERS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pune (M Corp.)13,700+ in Pune

Builder: MILIND RAMKRISHNA UPASANI

MILIND RAMKRISHNA UPASANI has 1 registration on MahaRERA, including SAI CHAMBERS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAI CHAMBERS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI CHAMBERS?

The registered promoter entity is MILIND RAMKRISHNA UPASANI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI CHAMBERS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI CHAMBERS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI CHAMBERS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI CHAMBERS?

The professionals named in the filing: Architect: RAJENDRA H THITE; Engineer: ANIRUDHA VANARSE; Engineer: Yashdeep Jadon; Chartered Accountant: Ramesh Rahalkar; Chartered Accountant: Pushpa Bogati; Chartered Accountant: SPAK & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI CHAMBERS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI CHAMBERS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI CHAMBERS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.