Registered No litigation declared Residential / Group Housing project

The Poetree Villa Resort

By Shiloh Holiday Homes Hospitalityy LLP

RG-MH-71986 · RERA P51600053355 · Last updated on MahaRERA portal: 4 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedno revision filed
18 of 306Construction stages doneacross 34 buildings; furthest along: Excavation, 0%
32 of 34Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 74 documents Report an error

The Poetree Villa Resort is a Residential / Group Housing project by Shiloh Holiday Homes Hospitalityy LLP in Nashik, Maharashtra, registered with MahaRERA as P51600053355 on 27 Oct 2023. Possession is promised by 31 Dec 2030. 2 of the 34 units on this registration are recorded sold or booked, and 18 of 306 construction stages are filed complete.

At a glance

Project

  • NameThe Poetree Villa Resort
  • TypeResidential / Group Housing
  • Location
    • Rayambe Road
    • Kawanai
    • Igatpuri
    • Kawanai
    • Igatpuri
    • Nashik
    • 422402
  • Pincode422402
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51600053355
  • ReraGenie IDRG-MH-71986

Builder

  • NameShiloh Holiday Homes Hospitalityy LLP
  • Entity typePartnership
  • PartnersAmith Dhiraj Galaa, Chirag Bhatia, Kevinn Jaain

Key dates

this monthRegisteredOct 2023PromisedDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Oct 2023
  • Promised completion31 Dec 2030
  • Revised completionNone
  • Buildings34 building records
  • Documents filed74 files

Current status

6%2 of 34 units booked
54.1%Work done, per cost certificate

Figures as on 4 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tourist Home 4NA11101
Tourist Home 6NA11101
Tourist Home 7NA22101
Tourist Home 8NA22101
Tourist Home 9NA11101
Tourist Home 10NA11101
Tourist Home 11NA11101
Tourist Home 12NA11101
Tourist Home 13NA11101
Tourist Home 14NA11101
Tourist Home 15NA11101
Tourist Home 16NA11101
Tourist Home 17NA11101
Tourist Home 18NA11101
Tourist Home 19NA11101
Tourist Home 20NA11101
Tourist Home 21NA11101
Tourist Home 22NA11101
Tourist Home 23NA11101
Tourist Home 24NA11101
Tourist Home 25NA11101
Tourist Home 26NA11101
Tourist Home 27NA11101
Tourist Home 28NA11101
Tourist Home 29NA11101
Tourist Home 30NA11101
Tourist Home 31NA11101
Tourist Home 32NA11101
Tourist Home 33NA11101
Tourist Home 34NA11101
Tourist Home 35NA11101
Tourist Home 36NA11101
Tourist Home 37NA11101
Tourist Home 38NA11101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 4 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 34 buildings; the table lists the first 20.

18 of 306 construction stages are filed complete across 34 buildings. The stage furthest along is Excavation, at 0%.

Tourist Home 40%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 60%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 7100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tourist Home 8100%
ActivityProgress
Excavation100%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Tourist Home 90%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 100%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 110%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 120%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 130%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 140%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 150%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 160%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 170%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 180%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 190%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 200%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 210%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 220%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 230%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tourist Home 240%
ActivityProgress
Excavation0%
Basement (if any)Not applicable
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed132

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots132
Open Space132
BuildingOpen SpaceTotal
Tourist Home 444
Tourist Home 644
Tourist Home 744
Tourist Home 844
Tourist Home 944
Tourist Home 1044
Tourist Home 1144
Tourist Home 1244
Tourist Home 1344
Tourist Home 1444
Tourist Home 1544
Tourist Home 1644
Tourist Home 1744
Tourist Home 1844
Tourist Home 1944
Tourist Home 2044
Tourist Home 2144
Tourist Home 2244
Tourist Home 2344
Tourist Home 2444
Tourist Home 2544
Tourist Home 2644
Tourist Home 2744
Tourist Home 2844
Tourist Home 2944
Tourist Home 3044
Tourist Home 3144
Tourist Home 3244
Tourist Home 3344
Tourist Home 3444
Tourist Home 3533
Tourist Home 3633
Tourist Home 3733
Tourist Home 3833

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area33,550 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Sep 2025

Approvals and building plan

Sanctioning authorityNMRDA
Permissible FSI34335.58
Proposed, not sanctioned1,366 sq m
Buildings approved34
Buildings sanctioned34

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai - Penninsula Lower Parel, Maharashtra
Estimated costRs 4.59 cr
Cost incurredRs 2.48 cr
Work done54.14%
BuildingWingEstimatedIncurred
Tourist Home 4NARs 41.90 lakhRs 24.85 lakh
Tourist Home 6NARs 41.90 lakhRs 24.85 lakh
Tourist Home 7NARs 41.90 lakhRs 24.85 lakh
Tourist Home 8NARs 41.90 lakhRs 24.85 lakh
Tourist Home 9NARs 41.90 lakhRs 24.85 lakh
Tourist Home 10NARs 41.90 lakhRs 24.85 lakh
Tourist Home 11NARs 41.90 lakhRs 24.85 lakh
Tourist Home 12NARs 41.90 lakhRs 24.85 lakh
Tourist Home 13NARs 41.90 lakhRs 24.85 lakh
Tourist Home 14NARs 41.90 lakhRs 24.85 lakh
-NARs 40.00 lakh-

Certifying professionals and partners12

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHuzefa Rangwala
ArchitectAR Huzefa Rangwala
EngineerMangesh Khadse
EngineerNitin gunjal
EngineerAashlesh Rajesh Nyati
EngineerRajkumar kabra
EngineerAP Associatee
Chartered AccountantVipul Bhandari
Chartered AccountantP N Sabdra & Associates
Chartered AccountantRSPH & Associates
Chartered AccountantCA Vipul Bhandari
Chartered AccountantPratik D Jain
PartnerRole in project
Shiloh Holiday Homes Hospitalityy LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Dec 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed74

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: AR - March 26 .pdf4 Apr 2026
Withdrawal Update Form 2File: ER - March 26 .pdf4 Apr 2026
Withdrawal Update Form 3File: CA - March 26 .pdf4 Apr 2026
Withdrawal Update Form 1File: AR - Dec 25.pdf4 Mar 2026
Withdrawal Update Form 2File: ER - Dec 25.pdf4 Mar 2026
Withdrawal Update Form 3File: CA - Dec 25 .pdf4 Mar 2026
Building plan approvalFile: Plan.pdf20 Dec 2025
Layout approvalFile: Plan.pdf20 Dec 2025
Withdrawal Update Form 1File: AR - sept 25.pdf31 Oct 2025
Withdrawal Update Form 2File: ER - Sept 25.pdf31 Oct 2025
Withdrawal Update Form 3File: CA - Sept 25 final.pdf31 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A - March 25.pdf16 Oct 2025
Form 2A (FY 2023-2024)File: Form 2A - March 24.pdf16 Oct 2025
Form 1File: AR - Dec 23.pdf23 Sep 2025
Form 2File: ER dec 23.pdf23 Sep 2025
Form 3File: CA - Dec 23 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 23.pdf23 Sep 2025
Form 1File: AR - March 24.pdf23 Sep 2025
Form 2File: ER march 24.pdf23 Sep 2025
Form 3File: CA - March 24 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - March 24.pdf23 Sep 2025
Form 1File: AR - June 24.pdf23 Sep 2025
Form 2File: ER june 24.pdf23 Sep 2025
Form 3File: CA - June 24 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - June 24.pdf23 Sep 2025
Form 1File: AR - Sep 24.pdf23 Sep 2025
Form 2File: ER sept 24.pdf23 Sep 2025
Form 3File: CA - Sep 24 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Sep 24.pdf23 Sep 2025
Form 1File: AR - Dec 24.pdf23 Sep 2025
Form 2File: ER dec 24.pdf23 Sep 2025
Form 3File: CA - Dec 24 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 24.pdf23 Sep 2025
Form 1File: AR - March 25.pdf23 Sep 2025
Form 2File: ER march 25.pdf23 Sep 2025
Form 3File: CA -March 25 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf23 Sep 2025
Form 1File: AR - June 25.pdf23 Sep 2025
Form 2File: ER june 25.pdf23 Sep 2025
Form 3File: CA - June 25 final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - June 25.pdf23 Sep 2025
Form 5 (FY 2024-2025)File: Sign RERA audit report 24 -25 Final.pdf22 Sep 2025
Form 5 (FY 2023-2024)File: RERA audit report 23-24 final.pdf18 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA Certificate By MuseLab.pdf21 Jun 2024
CERSAI detailsFile: CERSAI_Search_Report-Final.pdf23 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf16 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Plinth Certificate.pdf16 Oct 2023
Copy of the legal title reportFile: Title Report.pdf13 Oct 2023
Other - TechnicalFile: CC.pdf13 Oct 2023
Layout approvalFile: Plan 01.pdf6 Oct 2023
Layout approvalFile: Plan 02.pdf6 Oct 2023
Building plan approvalFile: Plan 01.pdf6 Oct 2023
Building plan approvalFile: Plan 02.pdf6 Oct 2023
Copy of the legal title reportFile: Land Purchase Deed (1).pdf6 Oct 2023
Copy of Layout Approval (in case of layout)File: Plan 01.pdf6 Oct 2023
Copy of Layout Approval (in case of layout)File: Plan 02.pdf6 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 01.pdf6 Oct 2023
Building Plan Approval / NA Order for plotted developmentFile: Plan 02.pdf6 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Scanned Copy.pdf6 Oct 2023
Proforma of Agreement for saleFile: AFS _ FINAL.pdf6 Oct 2023
PAN CardFile: Firm Pan Card.pdf5 Oct 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance-The Poetree Villa Resort.pdf5 Oct 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal-The Poetree Villa Resort.pdf5 Oct 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance-The Poetree Villa Resort.pdf5 Oct 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal-The Poetree Villa Resort.pdf5 Oct 2023
Declaration about Commencement CertificateFile: Form D - The Poetree Villa Resort.pdf5 Oct 2023
Declaration in FORM BFile: Form -B.pdf5 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf5 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf5 Oct 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations-The Poetree Villa Resort.pdf5 Oct 2023
Proforma of Allotment letterFile: Allotment Letter_1 (9 files merged) (1).pdf5 Oct 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Separate Bank Account Declaration-The Poetree Villa Resort_1 (2 files merged).pdf5 Oct 2023
Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter-The Poetree Villa Resort.pdf5 Oct 2023
Deviation Report with respect to model copy of AgreementFile: Deviation for AFS-The Poetree Villa Resort.pdf5 Oct 2023

How this compares with Nashik

6%of this project is bookeddistrict median 17%
10%of Nashik projects moved their completion datethis one has not
19%of Nashik registrations have lapsed or been cancelledthis one is on the register

Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.

Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep The Poetree Villa Resort on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kawanai, Igatpuri4,100+ in Nashik

Builder: Shiloh Holiday Homes Hospitalityy LLP

Shiloh Holiday Homes Hospitalityy LLP has 1 registration on MahaRERA, including The Poetree Villa Resort. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.

Frequently asked questions

What are my rights if The Poetree Villa Resort is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of The Poetree Villa Resort?

The registered promoter entity is Shiloh Holiday Homes Hospitalityy LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in The Poetree Villa Resort?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for The Poetree Villa Resort?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at The Poetree Villa Resort?

The professionals named in the filing: Architect: Huzefa Rangwala; Architect: AR Huzefa Rangwala; Engineer: Mangesh Khadse; Engineer: Nitin gunjal; Engineer: Aashlesh Rajesh Nyati; Engineer: Rajkumar kabra. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in The Poetree Villa Resort?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About The Poetree Villa Resort. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save The Poetree Villa Resort to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.