SHREE MURLIDHAR PARK PHASE I
RG-MH-69540 · RERA P51600050334 · Last updated on MahaRERA portal: 31 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 21 months
- 2 extensions taken
- Rs 8.50 crore secured on the land, in favour of Bank of Maharashtra
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nashik registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE MURLIDHAR PARK PHASE I is a Residential / Group Housing project by RAJENDRA MADHUKAR KALE in Nashik, Maharashtra, registered with MahaRERA as P51600050334 on 5 Apr 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 21 months from the original filing. 38 of the 56 units on this registration are recorded sold or booked, and 19 of 20 construction stages are filed complete.
At a glance
Project
- NameSHREE MURLIDHAR PARK PHASE I
- TypeResidential / Group Housing
- Location
- STATION ROAD
- AT POST GHOTI BK
- Ghoti Bk. (CT)
- Igatpuri
- Nashik
- 422402
- Pincode422402
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51600050334
- ReraGenie IDRG-MH-69540
Builder
- NameRAJENDRA MADHUKAR KALE
- Entity typeIndividual
- Other registrations2 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Apr 2023
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 31 Mar 2025)
- Buildings2 building records
- Documents filed102 files
Current status
Figures as on 31 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE MURLIDHAR PARK PHASE I- WING A AND B | WING A | 8 | 7 | 28 | 0 | 28 |
| SHREE MURLIDHAR PARK PHASE I- WING A AND B | WING B | 8 | 7 | 28 | 0 | 28 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 20 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.
SHREE MURLIDHAR PARK PHASE I- WING A AND B · wing WING A91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
SHREE MURLIDHAR PARK PHASE I- WING A AND B · wing WING B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 60% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 70% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed110
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SHREE MURLIDHAR PARK PHASE I- WING A AND B WING A | 47 | 47 |
| SHREE MURLIDHAR PARK PHASE I- WING A AND B WING B | 63 | 63 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHREE MURLIDHAR PARK PHASE I- WING A AND B | WING A | Rs 6.67 cr | Rs 6.67 cr |
| - | NA | Rs 20.00 lakh | Rs 17.00 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | UMESH BAGUL |
| Engineer | SAGAR S SHAH |
| Engineer | Amey Dhalkari |
| Chartered Accountant | PRASHANT PATHAK ASSOCIATES |
| Chartered Accountant | Nandkumar Yashwantrao Deshmukh |
| Partner | Role in project |
|---|---|
| RAJENDRA MADHUKAR KALE | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRespected Sir, our construction work is not yet completed, hence we request you to kindly extend the proposed date of project completion till 31/03/2026
Reason as filed by the promoterWith reference to the above subject, we hereby submit that the construction work of the project has been completed in accordance with the sanctioned building plan and as certified by the Project Architect through the Work Completion Certificate.We further submit that an application for issuance of the Occupancy/Completion Certificate has already been filed with the concerned Planning Authority. The approval is presently awaited.In view of the above and considering that the delay is procedural and beyond our control, we request your good office to kindly grant extension of the project registrat
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Feb 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Mar 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: FORM 2A I.PDF | 31 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 - PHASE - I.PDF | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Phase 1.PDF | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 - Phase I_Sign.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Ar Cretificate Phase - I.PDF | 28 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 PHASE I.PDF | 28 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 CA CERTI PHASE I.pdf | 28 Apr 2026 |
| Form 1File: ARCHITECT CERTI PHASE - 1 murlidhar park.pdf | 10 Feb 2026 |
| Form 2File: ENGI CERTIFICATE PHASE 1.PDF | 10 Feb 2026 |
| Form 3File: CA Certificate Phase I.PDF | 10 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: BOOK INVENTARY PHASE 1.PDF | 10 Feb 2026 |
| OthersFile: Phase I Form 2A.PDF | 10 Feb 2026 |
| Form 1File: Phase 1.PDF | 13 Jan 2026 |
| Form 2File: ENGINEER CERTIFICATE Q2 PHASE - 1.PDF | 13 Jan 2026 |
| Form 3File: Form 3 - ShreeMurlidhar Park Phase- I.PDF | 13 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Phase I - Sold and Booked Inventory .PDF | 13 Jan 2026 |
| OthersFile: Phase I Form 2A.PDF | 13 Jan 2026 |
| Form 1File: Form 1 -Phase I.PDF | 26 Nov 2025 |
| Form 2File: FORM 2 PHASE 1.PDF | 26 Nov 2025 |
| Form 3File: Form 3 PHASE I.PDF | 26 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: PHASE I.PDF | 26 Nov 2025 |
| Form 5 (FY 2024-2025)File: Phase I - Form 5.PDF | 3 Oct 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate Phase I.pdf | 3 May 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unit - Phase I.pdf | 3 May 2025 |
| Other - TechnicalFile: PERT CHART - PHASE I.pdf | 3 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 PHASE I.PDF | 2 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Certi.pdf | 30 Apr 2025 |
| Declaration in FORM BFile: Form B RM Kale - Phase I.pdf | 20 Mar 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PHASE 1 CA Certificate Form 3.PDF | 14 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PHASE 1 Engg.PDF | 14 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 PHASE 1.PDF | 28 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED PHASE 1.PDF | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PHASE 1 FORM 1.PDF | 3 Dec 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: PHASE 1 FORM 3.PDF | 3 Dec 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PHASE 1 FORM 2.PDF | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Shree Murlidhar Park Phase-I.PDF | 7 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHREE MURLIDHAR PARK PH-1.PDF | 28 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PHASE 1.PDF | 28 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Q1.pdf | 28 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHREEBRAMHAND.PDF | 20 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 1.PDF | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PHASE I.PDF | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A PHASE I.PDF | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Phase I.pdf | 20 Apr 2024 |
| CERSAI detailsFile: CERSAI merged.pdf | 12 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHREE MURLIDHAR PHASE 1.PDF | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.PDF | 25 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Phase I.PDF | 25 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Phase I Reduce.pdf | 25 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE PHASE I.PDF | 3 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CHARTERED ACCOUNTANTS PHASE I.PDF | 3 Nov 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECH CERTIFICATE PHASE I.PDF | 21 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A PHASE I.PDF | 21 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD BOOKED INVENTORY PHASE I.PDF | 21 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.PDF | 31 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A.PDF | 31 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: DISCOLSURE OF SOLD.PDF | 31 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed- Murlidhar Park Phase 1.pdf | 22 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ShreeMurlidhar park Phase I.PDF | 21 Jul 2023 |
| Building plan approvalFile: DECLARATION ABOUT PLOT AREA1.pdf | 23 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: DECLARATION ABOUT PLOT AREA1.pdf | 23 Mar 2023 |
| Building plan approvalFile: Plan 3-highlighted.pdf | 2 Mar 2023 |
| Building plan approvalFile: Plan 4-Highlighted_compressed.pdf | 2 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 3-highlighted.pdf | 2 Mar 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan 4-Highlighted_compressed.pdf | 2 Mar 2023 |
| Layout approvalFile: Layout - Mojani Nakasha.pdf | 17 Feb 2023 |
| Layout approvalFile: SANAD.PDF | 17 Feb 2023 |
| Building plan approvalFile: Plan 1.pdf | 17 Feb 2023 |
| Building plan approvalFile: Plan 2.pdf | 17 Feb 2023 |
| Building plan approvalFile: Plan 3.pdf | 17 Feb 2023 |
| Building plan approvalFile: Plan 4-1.pdf | 17 Feb 2023 |
| Building plan approvalFile: Plan 5-1.pdf | 17 Feb 2023 |
| Building plan approvalFile: Plan 6-1.pdf | 17 Feb 2023 |
| Building plan approvalFile: Plan 7-1.pdf | 17 Feb 2023 |
| PAN CardFile: Pan Card.PDF | 17 Feb 2023 |
| Copy of the legal title reportFile: Legal Title Report.PDF | 17 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: Self Declaration Undertaking.pdf | 17 Feb 2023 |
| Details of encumbrances concerned to FinanceFile: no any Legal and Litigation encumbranc.PDF | 17 Feb 2023 |
| Details of encumbrances concerned to LegalFile: Self Declaration Undertaking.pdf | 17 Feb 2023 |
| Details of encumbrances concerned to LegalFile: no any Legal and Litigation encumbranc.PDF | 17 Feb 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nashik
Computed across the 4,100+ Nashik projects on ReraGenie, from their own filings.
Free monthly report: Nashik on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHREE MURLIDHAR PARK PHASE I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near AT POST GHOTI BK4,100+ in Nashik
Filed coordinates, straight-line distance. 4 registered projects within 2 km.
Hanging Eden
Ishanya Buildcon
SHREEMURLIDHAR PARK PHASE II
RAJENDRA MADHUKAR KALE
AEROSOL
PARIVAR DEVELOPERS
KAWNAI KALM HOMES AND RESORT
JAYESH MAHESH AGRAWAL
SHREEMURLIDHAR PARK PHASE IV
RAJENDRA MADHUKAR KALE
The Poetree Villa Resort
Shiloh Holiday Homes Hospitalityy LLP
See every Nashik project, with the district possession charts
Builder: RAJENDRA MADHUKAR KALE
RAJENDRA MADHUKAR KALE has 3 registrations on MahaRERA, including SHREE MURLIDHAR PARK PHASE I and SHREEMURLIDHAR PARK PHASE II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nashik district page.
Frequently asked questions
What are my rights if SHREE MURLIDHAR PARK PHASE I is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE MURLIDHAR PARK PHASE I?
The registered promoter entity is RAJENDRA MADHUKAR KALE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE MURLIDHAR PARK PHASE I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREE MURLIDHAR PARK PHASE I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE MURLIDHAR PARK PHASE I?
The professionals named in the filing: Architect: UMESH BAGUL; Engineer: SAGAR S SHAH; Engineer: Amey Dhalkari; Chartered Accountant: PRASHANT PATHAK ASSOCIATES; Chartered Accountant: Nandkumar Yashwantrao Deshmukh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE MURLIDHAR PARK PHASE I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.