Home / Browse projects / Pune, Maharashtra / THE LEAF PHASE V

Completed Litigation declared Plotted project

THE LEAF PHASE V

By SHREE PUSHKAR DEVELOPERS

RG-MH-31119 · RERA P52100079453 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Completion date moved by 36 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedregistration recorded completed
1 of 1Construction stages doneevery applicable stage filed complete
30 of 33Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

THE LEAF PHASE V is a Plotted project by SHREE PUSHKAR DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100079453 on 6 Mar 2025. The registration is recorded completed; possession was promised by 31 Dec 2028. The completion date has moved by 36 months from the original filing. 3 of the 33 units on this registration are recorded sold or booked, and 1 of 1 construction stages are filed complete.

At a glance

Project

  • NameTHE LEAF PHASE V
  • TypePlotted
  • Location
    • FJJGJHG
    • THE LEAF SITE
    • YAWALEWADI
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • RERA no.P52100079453
  • ReraGenie IDRG-MH-31119

Builder

  • NameSHREE PUSHKAR DEVELOPERS
  • Entity typePartnership
  • PartnersPRAMOD R AGARWAL, RAJEEV S TYAGI, NITIN B TYAGI, SANJAY S TYAGI, RADHESHYAM R AGARWAL, CHANDRAHSEKHAR U KOTHARI, MAHEDRA U KOTHARI
  • Other registrations2 more →
  • Completed3 of 3
  • Declared earlier projects2 →

Key dates

this monthRegisteredMar 2025First promiseDec 2025Revised toDec 2028Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Mar 2025
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 31 Dec 2025)
  • BuildingsNot stated in filing
  • Documents filed65 files

Current status

9%3 of 33 units booked
80.9%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 1 construction stage is filed complete.

NA Plot Without Structure: 100% average across the applicable activities

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyNo100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNo100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo100%
Solid Waste Management And DisposalNo100%
Water conservation /Rain water harvestingNo100%
Energy managemcntNo100%
Fire protection and fire safety requirementsNo100%
Electrical meter room, sub-station, receiving stationNo100%
Aggregate area of recreational Open SpaceNo100%
Open ParkingNo100%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,499 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on30 Apr 2026

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTHE UNITED WESTERN BANK LTD., VISHRANTWADI PUNE BRANCH,, S.N.39/3, SIDDHESHWARNAGAR, TINGRENAGAR ROAD,, PINCODE - 411015
Estimated costRs 1.53 cr
Cost incurredRs 1.23 cr
Work done80.88%
BuildingWingEstimatedIncurred
-NARs 1.53 crRs 1.23 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVOUSSOIRS
EngineerDNYANESHWAR AWHALE
Engineermujib siddiki
Chartered AccountantK G JHAMVAR & CO CA KUNAL JHAMVAR
Chartered Accountantsr birla associates
PartnerRole in project
SHREE PUSHKAR DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA05052620837Dec 2025 → Dec 2028

Reason as filed by the promoterDue to delays caused by material shortages, labor shortages, and insufficient funding, the project has been delayed. However, with the funding now available, we kindly request an extension until 31/03/2028 to complete the project

Litigation declared2

CaseCourtStatus
687/2018/2018Civil Judge Senior Division PunePending
4790/2020/2020Superintendent of Land RecordsPending

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Feb 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 13 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 May 2026

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1-ARCHITECT CERTIFICATE-31-3-2026-SPD.pdf20 Jul 2026
Withdrawal Update Form 1File: 1) Architect Certificat -Form 1.pdf20 Jul 2026
Withdrawal Update Form 2File: 3) Engineering certificate - Form 2B.pdf20 Jul 2026
Withdrawal Update Form 2File: 3) Engineering certificate - Form 2B.pdf20 Jul 2026
Withdrawal Update Form 3File: form 3- Q1 fy 2026-27-sign copy (1)_compressed.pdf20 Jul 2026
Withdrawal Update Form 3File: form 3- Q1 fy 2026-27-sign copy (1)_compressed.pdf20 Jul 2026
Completion CertificateFile: PMC - Completion Certificate.pdf29 May 2026
Completion CertificateFile: Inward Copy 35 Yewlewadi.pdf29 May 2026
Withdrawal Update Form 1File: FORM 1-ARCHITECT CERTIFICATE-31-3-2026-SPD.pdf22 May 2026
Withdrawal Update Form 2File: form 2.pdf22 May 2026
Withdrawal Update Form 3File: form 3.pdf22 May 2026
Form 1File: FORM 1.pdf19 Jan 2026
Form 2File: FORM 2.pdf19 Jan 2026
Form 3File: FORM 3.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf19 Jan 2026
Form 1File: Form 1 Q2 2025-26.pdf18 Oct 2025
Form 2File: Form 2 Q2 2025-26.pdf18 Oct 2025
Form 3File: Form 3 Q2 2025-26.pdf18 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Sold-Unsold-PLOTTING- 30-9-2025.pdf18 Oct 2025
Form 1File: arc.pdf8 Aug 2025
Form 2File: Form 2 Q1 2025-26.pdf8 Aug 2025
Form 3File: Form 3 CA CERTIFICATE SPD- Q-1 FY 2025-26.pdf8 Aug 2025
Disclosure of Sold and Booked InventoryFile: FORM C -POLT SPD.pdf8 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: The Leaf-Plotting Form-1 Q4.pdf7 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: The Leaf-Plotting Form-3 Q4_compressed.pdf7 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: The Leaf-Plotting Form-2 Q4.pdf7 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: The Leaf-Plotting Form-2A Q4.pdf7 May 2025
Declaration about Commencement CertificateFile: 1 Declaration about Commencement Certificate-10_page-0001 (2).pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: RERA FORM1 Architect Certificate_page-0001 (1).pdf27 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form 2 (1)_page-0001.pdf27 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 THE LEAF.pdf19 Feb 2025
Proforma of Agreement for saleFile: AGREEMENT R1.pdf19 Feb 2025
Copy of the legal title reportFile: 1-40 (1).pdf4 Feb 2025
Copy of the legal title reportFile: 41-80.pdf4 Feb 2025
Other - FinanceFile: 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)-14 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: 1 Declaration about all RERA Designated Bank Accounts (Format A)-13_page-0001.pdf1 Feb 2025
Details of encumbrances concerned to FinanceFile: 1 b Details of encumbrances concerned to Legal-1_page-0001.pdf20 Jan 2025
Details of encumbrances concerned to FinanceFile: 1 b Details of encumbrances concerned to Legal-2_page-0001.pdf20 Jan 2025
CERSAI detailsFile: 1 CERSAI details-2_page-0001.pdf20 Jan 2025
Details of encumbrances concerned to LegalFile: 1 b Details of encumbrances concerned to Legal-1_page-0001.pdf20 Jan 2025
Details of encumbrances concerned to LegalFile: 1 b Details of encumbrances concerned to Legal-2_page-0001.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D1.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D7.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D6.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D5.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D4.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D3.pdf20 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: D2.pdf20 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: CORRECT -BANK CONFIRMATION LEETTER FOR RERA AC OPENING - PLOTTING_page-0001.pdf20 Jan 2025
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT-PLOTTING.pdf11 Jan 2025
Proforma of Allotment letterFile: allotment.pdf17 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: secure unsecure.pdf17 Dec 2024
Layout approvalFile: Layout Sanction-1.pdf13 Dec 2024
Building plan approval or NA orderFile: PLAN 02.pdf13 Dec 2024
Building plan approval or NA orderFile: SHEET NO 01-1.pdf13 Dec 2024
PAN CardFile: 1 PAN Card.pdf13 Dec 2024
Details of encumbrances concerned to FinanceFile: Decleration of Encomburances concern to legal.pdf13 Dec 2024
Copy of Layout Approval (in case of layout)File: Layout Sanction-1.pdf13 Dec 2024
Declaration in FORM BFile: Affidavit cum declearation Form B.pdf13 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: CC-1.pdf13 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN 02.pdf13 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: SHEET NO 01-1.pdf13 Dec 2024
Details of encumbrances concerned to LegalFile: Decleration of Encomburances concern to legal.pdf13 Dec 2024
Other - TechnicalFile: Declearation cum undertaking Annexure A.pdf13 Dec 2024
Deviation Report with respect to model copy of AgreementFile: deviation agrrement.pdf13 Dec 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
The Leaf Building 2 Wing DEFS No. 35 Mouje Yewalewadi Katraj Kondhwa road Tal Haveli Dist Pune164CompletedDec 2017Late, Aug 2018
The Leaf Building 1 Wing ABCS No. 35 Mouje Yewalewadi Katraj Kondhwa road Tal Haveli Dist Pune144CompletedJun 2016Late, Dec 2016

How this compares with Pune

9%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 36 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep THE LEAF PHASE V on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THE LEAF SITE13,700+ in Pune

Builder: SHREE PUSHKAR DEVELOPERS

Shree Pushkar Developers has 3 registrations on MahaRERA, including The Leaf and The leaf Phase IV Building-04 Wing I,J. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if THE LEAF PHASE V is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of THE LEAF PHASE V?

The registered promoter entity is SHREE PUSHKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in THE LEAF PHASE V?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for THE LEAF PHASE V?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at THE LEAF PHASE V?

The professionals named in the filing: Architect: VOUSSOIRS; Engineer: DNYANESHWAR AWHALE; Engineer: mujib siddiki; Chartered Accountant: K G JHAMVAR & CO CA KUNAL JHAMVAR; Chartered Accountant: sr birla associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in THE LEAF PHASE V?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About THE LEAF PHASE V. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save THE LEAF PHASE V to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.