Red flags
- 1 complaint at MahaRERA
- Completion date moved by 31 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
THE BUSINESS GATE is a Commercial project by Kesar Vasudev Properties in Pune, Maharashtra, registered with MahaRERA as P52100029275 on 10 May 2021. Possession is promised by 31 Oct 2026. The completion date has moved by 31 months from the original filing. 113 of the 280 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameTHE BUSINESS GATE
- TypeCommercial
- Location
- GAT 32
- JADHAV ESTATE
- BHARAT MATA CHOWK
- PUNE- NASHIK HIGHWAY
- MOSHI
- PUNE - 412105
- MOSHI
- PUNE
- Moshi
- Haveli
- Pune
- 412105
- Pincode412105
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029275
- ReraGenie IDRG-MH-17276
Builder
- NameKesar Vasudev Properties
- Entity typePartnership
- PartnersDILIP MANILAL PATEL, NILESH MADHUKAR NEVALE, VINODKUMAR MANILAL PATEL, SANTOSH DATTOBA BORATE, RAKESH BABULAL PATEL, SWAPNIL VASUDEV JADHAV, MOHIT VASUDEO JADHAV
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on10 May 2021
- Promised completion31 Oct 2026
- Revised completionRevised to 31 Oct 2026 (originally 31 Mar 2024)
- Buildings1 building record
- Documents filed112 files
Current status
Figures as on 4 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| THE BUSINESS GATE | NA | 9 | 0 | 0 | 280 | 280 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
THE BUSINESS GATE: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 4 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed693
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| SANTOSH RAMCHANDRA JADHAV | Pimpri Chinchawad (M Corp.) | Pune |
| SWAPNIL VASUDEV JADHAV / MOHIT VASUDEV JADHAV | Moshi | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| THE BUSINESS GATE | NA | Rs 19.19 cr | Rs 15.85 cr |
| - | NA | Rs 2.15 cr | - |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S S WALI AND ASSOCIATES |
| Engineer | HEMANT NIMBKAR |
| Engineer | NIKHIL PARASRAM SHINDE |
| Chartered Accountant | SUDHIRPATEL AND ASSOCIATES |
| Chartered Accountant | BHAVIK JAYANTILAL VELANI |
| Partner | Role in project |
|---|---|
| Kesar Vasudev Properties | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe, Kesar Vasudev Properties, hereby apply for extension of the registered project bearing vide no P52100029275. Due to site conditions and unavailability of labors during Covid 19 lockdown the project got delayed. The project is 80% complete as of today and we are confident to complete the project and acquire full occupancy certificate within a year. We hereby request you to please allow extension of the project till date 30/03/2025. Thanking You
Reason as filed by the promoter2. Regulatory and Developmental Constraints: o As per UDCPR Regulation No. 11.11.2.7 and Table 6-G of Regulation No. 6.3, the permissible Transferable Development Rights (TDR) usage mandates a minimum of 30% and a maximum of 50% to be sourced from Slum TDR/URT/Amenity TDR (wherever applicable). o However, due to the limited availability of Slum TDR/URT/Amenity TDR within the municipal area, we, as developers, faced restrictions in procuring TDR, consequently affecting the project's progress.
Reason as filed by the promoterThe original completion date of the project was 30/09/2025, and accordingly, an extension application was filed on 29/09/2025. During the scrutiny of the said application, it was observed that consent of the allottees was required. We made sincere efforts to contact the allottees for obtaining such consent; however, the same could not be completed as the project had already substantially achieved completion. Further, due to local elections and the resulting administrative delays, the process of obtaining the Completion Certificate/Occupation Certificate (CC/OC) was delayed, which significantly
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000095987 | Hanumant Baban Saste | Swapnil Vasudev Saste | 09/09/2021 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 Feb 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 15 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Oct 2026
Documents filed112
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: 24 - 25.pdf | 4 Aug 2026 |
| Form 5 (FY 2024-2025)File: 24 - 25.pdf | 4 Aug 2026 |
| Form 5 (FY 2024-2025)File: 24 - 25.pdf | 4 Aug 2026 |
| Form 2A (FY 2021-2022)File: 21 - 22.pdf | 30 Jul 2026 |
| Form 2A (FY 2022-2023)File: 22 - 23.pdf | 30 Jul 2026 |
| Form 2A (FY 2023-2024)File: 23 - 24.pdf | 30 Jul 2026 |
| Form 2A (FY 2024-2025)File: 23 - 24.pdf | 30 Jul 2026 |
| Form 2A (FY 2025-2026)File: 23 - 24.pdf | 30 Jul 2026 |
| Form 5 (FY 2023-2024)File: 23 - 24.pdf | 30 Jul 2026 |
| Form 5 (FY 2022-2023)File: 22 - 23.pdf | 30 Jul 2026 |
| Form 5 (FY 2021-2022)File: 21 - 22.pdf | 30 Jul 2026 |
| Withdrawal Update Form 1File: Form 1_Qtr 3_11zon.pdf | 13 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 13 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 13 Jul 2026 |
| Withdrawal Update Form 2File: Form 2_Qtr 3.pdf | 13 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 13 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 13 Jul 2026 |
| Withdrawal Update Form 3File: Form 3_Qtr 3.pdf | 13 Jul 2026 |
| Withdrawal Update Form 3File: Form 3_Qtr 3.pdf | 13 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 13 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 9 Jul 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 9 Jul 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 9 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Qtr 2.pdf | 31 Jan 2026 |
| Withdrawal Update Form 2File: Form 2_Qtr 2.pdf | 31 Jan 2026 |
| Withdrawal Update Form 3File: Form 3_Qtr 2.pdf | 31 Jan 2026 |
| Form 1File: Form 1 .pdf | 16 Aug 2025 |
| Form 2File: Form 2.pdf | 16 Aug 2025 |
| Form 3File: Form 3.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold_Unslod Inventory.pdf | 16 Aug 2025 |
| Declaration in FORM BFile: Form B Scan.pdf | 18 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_KVP_Q4_signed formfull_compressed.pdf | 6 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory QTR 4_31032025.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Architech letter_Upload_compressed.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3_upload_compressed.pdf | 17 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rcc Consultant_ Form 2_compressed.pdf | 17 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: QTR1SOLD BOOKEDUNSOLD INNVENTORY.pdf | 17 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: QTR3SOLD BOOKEDUNSOLD INNVENTORY.pdf | 17 Feb 2025 |
| Disclosure of sold/ booked inventoryFile: QTR2SOLD BOOKEDUNSOLD INNVENTORY.pdf | 17 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: KVPFORM5.pdf | 19 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: KVPFORM5.pdf | 19 Nov 2024 |
| Building plan approvalFile: Basement 1-2 Floor_2-11.pdf | 18 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Basement 1-2 Floor_2-11.pdf | 18 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory.pdf | 31 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate Form 2A FY 23-24.pdf | 30 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate Form 2A FY 23-24.pdf | 30 May 2024 |
| Details of encumbrancesFile: Rera Encumbrance Letter_Bajaj Finance (1).pdf | 28 May 2024 |
| Declaration in FORM BFile: Business gate form b.pdf | 4 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_Form 1.pdf | 2 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 2 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer_Form 2A_2020-21.pdf | 2 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer_Form 2A_2021-22.pdf | 2 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer_Form 2A_2022-23.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inv june 22.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inv Sept 22.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inve Dec 22.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inv March 23.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inv june 23.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inv Sept 23.pdf | 2 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inv Dec 23.pdf | 2 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Form 3_compressed.pdf | 2 Apr 2024 |
| Proforma of Agreement for saleFile: Shop Agreement Draft.pdf | 2 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KESAR VASUDEV PROPERTIES.pdf | 27 Mar 2024 |
| Copy of the legal title reportFile: search report.pdf | 16 Feb 2024 |
| Building plan approvalFile: First Floor Plan_5-11_compressed.pdf | 15 Feb 2024 |
| Building plan approvalFile: Elevation Plan_11-11_compressed.pdf | 15 Feb 2024 |
| Building plan approvalFile: Second Floor Plan_6-11_compressed_attached.pdf | 15 Feb 2024 |
| Building plan approvalFile: Third Floor Plan_7-11_compressed_attached.pdf | 15 Feb 2024 |
| Building plan approvalFile: Fourth Floor Plan_8-11_compressed_attached.pdf | 15 Feb 2024 |
| Building plan approvalFile: Fifth Floor Plan_9-11_compressed.pdf | 15 Feb 2024 |
| Building plan approvalFile: Terrace Floor Plan_10-11_compressed.pdf | 15 Feb 2024 |
| Layout approvalFile: Layout_1-11_compressed.pdf | 15 Feb 2024 |
| Building plan approvalFile: Ground Floor_3-11_compressed.pdf | 15 Feb 2024 |
| Building plan approvalFile: Mezzanine Floor_4-11_compressed.pdf | 15 Feb 2024 |
| Building plan approvalFile: Ground Floor_3-11_compressed.pdf | 15 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: Layout_1-11_compressed.pdf | 15 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Ground Floor_3-11_compressed.pdf | 15 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Mezzanine Floor_4-11_compressed.pdf | 15 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Ground Floor_3-11_compressed.pdf | 15 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: First Floor Plan_5-11_compressed.pdf | 15 Feb 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 112 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep THE BUSINESS GATE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MOSHI, PUNE13,700+ in Pune
Filed coordinates, straight-line distance. 194 registered projects within 2 km.
TANISH PARK
TANISH DEVELOPERS
Ajinkya Towers
APAK Bussiness Innovation Pvt Ltd
SILVER GARDENIA
SILVER PROMOTERS AND DEVELOPERS
Mangalam Life Park
Mangalam Buildcorp
SingaPune Ph 3
Xrbia Mirth Properties LLP
SingaPune Ph 2
Xrbia Mirth Properties LLP
Builder: Kesar Vasudev Properties
Kesar Vasudev Properties has 1 registration on MahaRERA, including THE BUSINESS GATE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if THE BUSINESS GATE is delayed beyond 31 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of THE BUSINESS GATE?
The registered promoter entity is Kesar Vasudev Properties, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in THE BUSINESS GATE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against THE BUSINESS GATE?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for THE BUSINESS GATE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at THE BUSINESS GATE?
The professionals named in the filing: Architect: S S WALI AND ASSOCIATES; Engineer: HEMANT NIMBKAR; Engineer: NIKHIL PARASRAM SHINDE; Chartered Accountant: SUDHIRPATEL AND ASSOCIATES; Chartered Accountant: BHAVIK JAYANTILAL VELANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in THE BUSINESS GATE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback