Home / Browse projects / Pune, Maharashtra / TATHASTU PHASE-I

Completed No litigation declared Residential / Group Housing project

TATHASTU PHASE-I

By SHREE UMIYA BUILDCON

RG-MH-94200 · RERA P52100055321 · Last updated on MahaRERA portal: 13 Jun 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promisedregistration recorded completed
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 95%
13 of 95Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

TATHASTU PHASE-I is a Residential / Group Housing project by SHREE UMIYA BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100055321 on 14 Mar 2024. The registration is recorded completed; possession was promised by 30 Jun 2026. The completion date has moved by 6 months from the original filing. 82 of the 95 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameTATHASTU PHASE-I
  • TypeResidential / Group Housing
  • Location
    • NEAR REDCLIFF SCHOOL
    • SPINE ROAD PRADHIKARAN MOSHI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100055321
  • ReraGenie IDRG-MH-94200

Builder

  • NameSHREE UMIYA BUILDCON
  • Entity typePartnership
  • GSTIN27ACSFS7471B1ZP
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersHARESHKUMAR PACHANBHAI PATEL, MANISHKUMAR SHANKARAL PATEL, NASRI HARJI PATEL, MEHUL PRADIP RAMANI, GAURAV DINESHBHAI PATEL, JIGNEHKUMAR AMBALAL RAMJIYANI
  • Other registrations3 more →
  • Completed2 of 4

Key dates

this monthRegisteredMar 2024First promiseDec 2025Revised toJun 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on14 Mar 2024
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed85 files

Current status

86%82 of 95 units booked
99.8%Work done, per cost certificate

Figures as on 13 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
TATHASTU PHASE - INA141295095

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.

TATHASTU PHASE - I: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.5%

Progress on shared amenities15

As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed155

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots155
Closed/Covered155

Land and ownership50

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,200 sq m
Land owned byNot the promoter
Named landowners50
Encumbrance on the landDeclared none
Declared on8 Aug 2025
LandownerVillageDistrict
SUNIL SHANTARAM TAPKIRCHARHOLIPune
MANDAKINI SUNIL TAPKIRCHARHOLIPune
JAYESH SUNIL TAPKIRCHARHOLIPune
PRATHMESH SUNIL TAPKIRCHARHOLIPune
SACHIN SHANTARAM TAPKIRCHARHOLIPune
PRANJALI SACHIN TAPKIRCHARHOLIPune
SWASTIK SACHIN TAPIKIRCHARHOLIPune
ALKA SHANTARAM TAPKIRCHARHOLIPune
KANTARAM VISHNU TAPKIRCHARHOLIPune
ABHIJIT KANTARAM TAPKIRCHARHOLIPune
GOURI ABHIJIT TAPKIRCHARHOLIPune
ISHWARI ABHIJIT TAPKIRCHARHOLIPune
LAYANSH ABHIJIT TAPKIRCHARHOLIPune
ANUP KANTARAM TAPKIRCHARHOLIPune
KSHITIJA ANUP TAPKIRCHARHOLIPune
BALASAHEB VISHNU TAPKIRCHARHOLIPune
CHANDRAKALA BALASAHEB TAPKIRCHARHOLIPune
NIKHIL BALASAHEB TAPKIRCHARHOLIPune
ABHILASHA NIKHIL TAPKIRCHARHOLIPune
AANAY NIKHIL TAPKIRCHARHOLIPune
NEHA SOURABH SONPARATECHARHOLIPune
DATTRAYA DASHRATH TAPKIRCHARHOLIPune
VAISHALI DATTARAYA TAPKIRCHARHOLIPune
SHUBHAM DATTATRAYA TAPKIRCHARHOLIPune
SUBHADRA DASHRATH TAPKIRCHARHOLIPune
ANIL DASHRHTH TAPKIRCHARHOLIPune
MINA ANIL TAPKIRCHARHOLIPune
RHUSHIKESH ANIL TAPKIRCHARHOLIPune
ABHISHEK ANIL TAPKIRCHARHOLIPune
SANGITA SAMBHAJI HARPALECHARHOLIPune
ROHIDAS MAHADEO TAPKIRCHARHOLIPune
NIRMALA ROHIDAS TAPKIRCHARHOLIPune
PRIYANKA ROHIDAS TAPKIRCHARHOLIPune
PRAJAKATA RADHAKRUSHANA PANGACHARHOLIPune
PRAJWAL ROHIDAS TAPKIRCHARHOLIPune
DNYANESHWAR MAHADU TAPKIRCHARHOLIPune
UJWALA DNYANESHWAR TAPKIRCHARHOLIPune
AMIT DNYANESHWAR TAPKIRCHARHOLIPune
ABHILASHA AMIT TAPKIRCHARHOLIPune
ADITYA DNYAESHWAR TAPKIRCHARHOLIPune
SAMITA ALIES JANABAI ASHOK SORTECHARHOLIPune
URMILA BALASAHEB DEVKARCHARHOLIPune
SAGAR RAMDAS TAPKIRCHARHOLIPune
NIKITA SAGAR TAPKIRCHARHOLIPune
TANISH SAGAR TAPKIRCHARHOLIPune
ANUSHKA SAGAR TAPKIRCHARHOLIPune
AVDHUT SAGAR TAPKIRCHARHOLIPune
SITA RAMDAS TAPKIRCHARHOLIPune
SAMIR RAMDAS TAPKIRCHARHOLIPune
MANISHA SHRIKANT TAPKIRCHARHOLIPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI9671.61
Proposed, not sanctioned9,672 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1, MEZ FLOOR SILVANA COUNTRY, CHOVISAWADI, CHARHOLI, BUDRUK, 412101
Estimated costRs 25.11 cr
Cost incurredRs 25.07 cr
Work done99.82%
BuildingWingEstimatedIncurred
TATHASTU PHASE - INARs 24.22 crRs 24.22 cr
-NARs 88.79 lakhRs 84.35 lakh

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNITIN R. PATEL
ArchitectNITIN PATEL
EngineerGAURAV D PATEL
EngineerGAURAV D. PATEL
EngineerManoj Gopinath Shinde
Chartered AccountantH. V. PATEL AND ASSOCIATES
Chartered AccountantPRASANT PATEL
Chartered AccountantS V S V & Associates
PartnerRole in project
M/s Shree Umiya Buildcon-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24112518415Dec 2025 → Jun 2026

Reason as filed by the promoterWe have applied for the Occupancy Certificate (OC) with the Corporation; however, the process is expected to take additional time. Therefore, we are applying for an extension of the project validity till 30/06/2026.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Feb 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Aug 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Aug 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Completion Certificate Phase-I.pdf13 Jun 2026
Withdrawal Update Form 1File: Form_1_sign.pdf28 Apr 2026
Withdrawal Update Form 2File: Form_2_Sign.pdf28 Apr 2026
Withdrawal Update Form 3File: FORM 3 Shree Umiya Buildcon_Sign.pdf28 Apr 2026
Withdrawal Update Form 1File: Form 1 Dec 25.pdf25 Jan 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf25 Jan 2026
Withdrawal Update Form 3File: Form 3 Dec-25_compressed.pdf25 Jan 2026
Withdrawal Update Form 1File: DocScanner Nov 5, 2025 12-49 PM.pdf24 Nov 2025
Withdrawal Update Form 2File: Form 2 -30-09-2025.pdf24 Nov 2025
Withdrawal Update Form 3File: Form 3-30-09-2025_compressed.pdf24 Nov 2025
Form 2A (FY 2023-2024)File: Form 2 A Year End March 2024_compressed.pdf24 Nov 2025
Form 2A (FY 2024-2025)File: Form 2 A Year End March 2025_compressed.pdf24 Nov 2025
Form 5 (FY 2023-2024)File: Form 5.pdf24 Nov 2025
Form 5 (FY 2024-2025)File: Form 5 -01-04-204 to 31-03-2025.pdf24 Nov 2025
Form 1File: Phase-I Form-1- 30-06-2025.pdf14 Aug 2025
Form 2File: Phase-I Form-II- 30-06-2025.pdf14 Aug 2025
Form 3File: Form-3 -30-06-2025_compressed.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold-30-06-2025.pdf14 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I 31-03-2025.pdf16 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- 31-03-2025_compressed.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II 31-03-2025_compressed.pdf16 Apr 2025
Proforma of Agreement for saleFile: Draft Agreement to sale - Phase-I.pdf11 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I 31-12-2024.pdf19 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Rera.pdf19 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II 31-12-2024.pdf19 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventry 31-12-24_11zon.pdf19 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -30-09-2024.pdf15 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 -30-09-2024.pdf15 Oct 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf7 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf7 Oct 2024
Layout approvalFile: 01-5 Layout.pdf11 Aug 2024
Copy of Layout Approval (in case of layout)File: 01-5 Layout.pdf11 Aug 2024
Building plan approvalFile: 01-05.pdf9 Aug 2024
Building plan approvalFile: 02-05.pdf9 Aug 2024
Building plan approvalFile: 03-05.pdf9 Aug 2024
Building plan approvalFile: 04-05.pdf9 Aug 2024
Building plan approvalFile: 05-05.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 01-05.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 02-05.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 03-05.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 04-05.pdf9 Aug 2024
Building Plan Approval / NA Order for plotted developmentFile: 05-05.pdf9 Aug 2024
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE 07-08-24.pdf9 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf19 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30-06-2024_compressed.pdf19 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf19 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 30-6-2024_compressed.pdf19 Jul 2024
Details of encumbrances concerned to FinanceFile: Capri Global Loan.pdf28 May 2024
Details of encumbrances concerned to LegalFile: Capri Global Loan.pdf28 May 2024
Other - FinanceFile: Capri Global Loan.pdf28 May 2024
Other - FinanceFile: Capri Global Loan.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Q4.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Q4.pdf17 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Q4.pdf17 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Verification Email.pdf28 Feb 2024
Other - TechnicalFile: CC Verification Email.pdf28 Feb 2024
Copy of the legal title reportFile: Latest Search Report.pdf26 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: organized.pdf26 Feb 2024
Proforma of Agreement for saleFile: Final Rera Draft Umiya Bildcon Sr No 42 Chrholi.pdf26 Feb 2024
Details of encumbrances concerned to FinanceFile: No Encumbrances to Finance.pdf4 Feb 2024
Details of encumbrances concerned to FinanceFile: No Encumbrances To Legal.pdf4 Feb 2024
Details of encumbrances concerned to LegalFile: No Encumbrances to Finance.pdf4 Feb 2024
Details of encumbrances concerned to LegalFile: No Encumbrances To Legal.pdf4 Feb 2024
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf4 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked inventory.pdf4 Feb 2024
CERSAI detailsFile: Undertaking For Cersai Report.pdf4 Feb 2024
Proforma of Allotment letterFile: Annexure 1.pdf4 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Rera Bank Account.pdf4 Feb 2024
Deviation Report with respect to Allotment letterFile: Deviation Report For Allotment Letter.pdf4 Feb 2024
Deviation Report with respect to model copy of AgreementFile: Deviation Report For Agreement To sale.pdf4 Feb 2024
Other - LegalFile: PARTNERSHIP DEED.pdf4 Feb 2024
Other - TechnicalFile: Annexure A.pdf4 Feb 2024
Layout approvalFile: Layout 1.pdf3 Feb 2024
Building plan approvalFile: Layout 2.pdf3 Feb 2024
Building plan approvalFile: Layout 3.pdf3 Feb 2024
Building plan approvalFile: Layout 4_11zon.pdf3 Feb 2024
PAN CardFile: Pancard.pdf3 Feb 2024
Copy of Layout Approval (in case of layout)File: Layout 1.pdf3 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: Layout 2.pdf3 Feb 2024

How this compares with Pune

86%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep TATHASTU PHASE-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near SPINE ROAD PRADHIKARAN MOSHI13,700+ in Pune

2 kmTATHASTU PHASE-ICompleted 45Lapsed / revoked 21Other 81Dot size: filed unitsN

Filed coordinates, straight-line distance. 147 registered projects within 2 km.

Builder: SHREE UMIYA BUILDCON

SHREE UMIYA BUILDCON has 4 registrations on MahaRERA, including DATTA VIHAR and TATHASTU PHASE-I. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if TATHASTU PHASE-I is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of TATHASTU PHASE-I?

The registered promoter entity is SHREE UMIYA BUILDCON, a partnership as per the filing. Its GSTIN 27ACSFS7471B1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in TATHASTU PHASE-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for TATHASTU PHASE-I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at TATHASTU PHASE-I?

The professionals named in the filing: Architect: NITIN R. PATEL; Architect: NITIN PATEL; Engineer: GAURAV D PATEL; Engineer: GAURAV D. PATEL; Engineer: Manoj Gopinath Shinde; Chartered Accountant: H. V. PATEL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in TATHASTU PHASE-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About TATHASTU PHASE-I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save TATHASTU PHASE-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.