Home / Browse projects / Pune, Maharashtra / Tanishq Vlasta

Registered No litigation declared Residential / Group Housing project

Tanishq Vlasta

By Tanishq Realities

RG-MH-11299 · RERA P52100002155 · Last updated on MahaRERA portal: 15 Jul 2026

Source: official MahaRERA filing

Red flags

  • 15 complaints at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken
  • Rs 30.00 crore secured on the land, in favour of State Bank of India
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
26 of 33Construction stages doneacross 3 buildings; furthest along: Basement (if any), 0%
48 of 217Units unsoldnot recorded sold or booked
15Complaints at MahaRERAon this registration
Jump to the 151 documents Report an error

Tanishq Vlasta is a Residential / Group Housing project by Tanishq Realities in Pune, Maharashtra, registered with MahaRERA as P52100002155 on 31 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 169 of the 217 units on this registration are recorded sold or booked, and 26 of 33 construction stages are filed complete. 15 complaints are on record with the regulator.

At a glance

Project

  • NameTanishq Vlasta
  • TypeResidential / Group Housing
  • Location
    • Sr no 22/9
    • Alandi Rural
    • Khed
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002155
  • ReraGenie IDRG-MH-11299

Builder

  • NameTanishq Realities
  • Entity typePartnership
  • PartnersBalasaheb Dnyanoba Talekar, Ramesh Dnyanoba Talekar, Amol Mohan Mate, Sneha Amol Mate

Key dates

this monthRegisteredJul 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings3 building records
  • Documents filed151 files

Current status

78%169 of 217 units booked
98.7%Work done, per cost certificate

Figures as on 15 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DNA121165065
ENA121165065
FNA121187087

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Basement (if any), at 0%.

D73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes92%
Landscaping & Tree PlantingYes92%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed401

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots401
Closed/Covered283
Open Space118
BuildingClosed/CoveredOpen SpaceTotal
D8740127
E8740127
F10938147

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area20,200 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofState Bank of India
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on16 Jul 2025
LandownerVillageDistrict
Bharat Ramchandra AndreAlandi RuralPune
Maruti Bharat AndreAlandi RuralPune
Sunanda Maruti AndreAlandi RuralPune

Approvals and building plan

Sanctioning authorityUPAVIBHAK ADHIKARI KHED
Permissible FSI10598.35
Proposed, not sanctioned10,598 sq m
Buildings approved6
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCommercial Branch Tilak Road Office No 101 and 102 First Floor Next Gen Avenue Bahiratwadi Opp Senap
Estimated costRs 74.00 cr
Cost incurredRs 73.02 cr
Work done98.68%
BuildingWingEstimatedIncurred
DNARs 20.00 crRs 20.00 cr
ENARs 20.00 crRs 20.00 cr
FNARs 20.00 crRs 20.00 cr
-NARs 14.00 crRs 13.02 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMangesh Gotal
EngineerNikhil Mudholkar
EngineerAjit Dattattray Gavhane
EngineerShraddha Ajit Ghule
Chartered AccountantM CHAUDHARI & ASSOCIATES
Chartered AccountantNITISH VAIDYA & ASSOCIATES
Chartered AccountantMs Sumit Abattini & Company
PartnerRole in project
Tanishq Realities-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100013439Dec 2022 → Dec 2023

Reason as filed by the promoterDUE TO COVID 19 AND NON AVAILABILITY OF RESOURCES.

EXT52100018163Dec 2022 → Dec 2025

Reason as filed by the promoterDue to Covid - 19 and shortage of manpower resources.

EA09122518579Dec 2022 → Dec 2026

Reason as filed by the promoterThe project completion has been delayed due to the pending final NOC and Occupancy Certificate (OC) related to the lift installation. Except for this approval, all construction activities have been completed and the project is in the final stage of completion.

Complaints filed with MahaRERA15

Case no.ComplainantRespondentFiled
CC005000000054015Rajesh Ramchandra BhideRamesh Dhondiba Talekar06/02/2020
CC005000000064685Mr. Nandkishor Sudhakar KharadM/s. Tanishq Realities Through its Partner & Authorised Signatory Mr. Ramesh Dnyanoba Talekar17/10/2020
CC005000000064716Rajesh Vishwanath RautM/s. Tanishq Realities Through its Partner & Authorized Signatory Mr. Ramesh Dnyanoba Talekar12/10/2020
CC005000000157262Sunil Ramchandra RathodM/s Tanishq Realities09/09/2022
CC005000000106503Sumit Sajjan WaghmareTanishq Realities Thr its Partner's a) Ramesh Talekar b) Balasaheb Talekar c) Amol Mate d)Sneha Mate20/01/2022
CC005000000106653Mr. Nitin Giridhar FirkeM/s.Tanishq Realities Thr.its Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d)Sneha Mate23/02/2022
CC005000000106741Mr. Bhaskar Sarjerao PatilM/s Tanishq Realities Thro. Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d) Sneha Mate08/03/2022
CC005000000269323Mr. Purushottam Manphoolsingh RanjanM/s.Tanishq Realities Thr its Partners a)Ramesh Talekar b)Balasaheb Talekar c)Amol Mate d)Sneha Mate25/08/2023
CC005000000289985V.T. Palresha &co. PRIVATE LIMITEDTANISHQ REALITIES30/12/2023
CC005000000289986ENVIIRO BUILDMATE PVTLTDTanishq Realities30/12/2023
CC12501338Roshani Swapnil RawaleTanishq Realities22/04/2025
CC12501881Chandan Kumar JhaTanishq Realities09/06/2025
CC12502451Rajasekhar Rao GaneTanishq Realities18/07/2025
CC12600981Archana PundTanishq Realities23/02/2026
CC12604200Neelkanth Basappa KanikeriTanishq Realities04/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed151

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 151 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Signed.pdf15 Jul 2026
Withdrawal Update Form 2File: Form 2 Signed.pdf15 Jul 2026
Withdrawal Update Form 3File: Form 3 Q1 FY 2026-27 Final_compressed.pdf15 Jul 2026
Withdrawal Update Form 1File: Form 1 Architects Certificate.pdf19 May 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate.pdf19 May 2026
Withdrawal Update Form 3File: Form 3 Q4 FY 25-26 Final_compressed.pdf19 May 2026
Withdrawal Update Form 1File: Form 1 Q3 FY 25-26.pdf4 Feb 2026
Withdrawal Update Form 2File: Form 2 Q3 FY 25-26.pdf4 Feb 2026
Withdrawal Update Form 3File: Form 3 Q3 FY 25-26.pdf4 Feb 2026
Form 5 (FY 2023-2024)File: Form-5- 23-24.pdf7 Jan 2026
Form 5 (FY 2024-2025)File: Form-5- 24-25.pdf7 Jan 2026
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf13 Nov 2025
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf13 Nov 2025
Withdrawal Update Form 3File: Withdrawal Application Form3_compressed.pdf13 Nov 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf10 Nov 2025
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf10 Nov 2025
Withdrawal Update Form 3File: Withdrawal Application Form3_compressed.pdf10 Nov 2025
Layout approvalFile: Layout Approval Plan.pdf14 Sep 2025
Layout approvalFile: Layout Approval Plan.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-1.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-11.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-12.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-13.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-14.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-15.pdf14 Sep 2025
Building plan approvalFile: Sancationed Approval Plan-16.pdf14 Sep 2025
Form 1File: Form 1 FY 2023-2024 Q1.pdf6 Aug 2025
Form 2File: Form 2 FY 2023-2024 Q1.pdf6 Aug 2025
Form 3File: Form 3 FY 2023-2024 Q1.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2023-2024 Q1.pdf6 Aug 2025
Form 1File: Form 1 FY 2023-2024 Q2.pdf6 Aug 2025
Form 2File: Form 2 FY 2023-2024 Q2.pdf6 Aug 2025
Form 3File: Form 3 FY 2023-2024 Q2.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2023-2024 Q2.pdf6 Aug 2025
Form 1File: Form 1 FY 2023-2024 Q3.pdf6 Aug 2025
Form 2File: Form 2 FY 2023-2024 Q3.pdf6 Aug 2025
Form 3File: Form 3 FY 2023-2024 Q3.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2023-2024 Q3.pdf6 Aug 2025
Form 1File: Form 1 FY 2023-2024 Q4.pdf6 Aug 2025
Form 2File: Form 2 FY 2023-2024 Q4.pdf6 Aug 2025
Form 3File: Form 3 FY 2023-2024 Q4.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2023-2024 Q4.pdf6 Aug 2025
Form 1File: Form 1 FY 2024-2025 Q1.pdf6 Aug 2025
Form 2File: Form 2 FY 2024-2025 Q1.pdf6 Aug 2025
Form 3File: Form 3 FY 2024-2025 Q1.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2024-2025 Q1.pdf6 Aug 2025
Form 1File: Form 1 FY 2024-2025 Q2.pdf6 Aug 2025
Form 2File: Form 2 FY 2024-2025 Q2.pdf6 Aug 2025
Form 3File: Form 3 FY 2024-2025 Q2.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2024-2025 Q2.pdf6 Aug 2025
Form 1File: Form 1 FY 2024-2025 Q3.pdf6 Aug 2025
Form 2File: Form 2 FY 2024-2025 Q3.pdf6 Aug 2025
Form 3File: Form 3 FY 2024-2025 Q3.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2024-2025 Q3.pdf6 Aug 2025
Form 1File: Form 1 FY 2021-22 Q4.pdf6 Aug 2025
Form 2File: Form 2 FY 2021-22 Q4.pdf6 Aug 2025
Form 3File: Form 3 FY 2021-2022 Q4.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2021-2022 Q4.pdf6 Aug 2025
Form 1File: Form 1 FY 2022-2023 Q 1.pdf6 Aug 2025
Form 2File: Form 2 FY 2022-2023 Q 1.pdf6 Aug 2025
Form 3File: Form 3 FY 2022-2023 Q1.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2022-2023 Q1.pdf6 Aug 2025
Form 1File: Form 1 FY 2022-2023 Q2.pdf6 Aug 2025
Form 2File: Form 2 FY 2022-2023 Q2.pdf6 Aug 2025
Form 3File: Form 3 FY 2022-2023 Q2.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2022-2023 Q2.pdf6 Aug 2025
Form 1File: Form 1 FY 2022-2023 Q3.pdf6 Aug 2025
Form 2File: Form 2 FY 2022-2023 Q3.pdf6 Aug 2025
Form 3File: Form 3 FY 2022-2023 Q3.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2022-2023 Q3.pdf6 Aug 2025
Form 1File: Form 1 FY 2022-2023 Q4.pdf6 Aug 2025
Form 2File: Form 2 FY 2022-2023 Q4.pdf6 Aug 2025
Form 3File: Form 3 FY 2022-2023 Q4.pdf6 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2022-2023 Q4.pdf6 Aug 2025
Form 1File: Form 1 FY 2024-2025 Q4.pdf1 Aug 2025
Form 2File: Form 2 FY 2024-2025 Q4.pdf1 Aug 2025
Form 3File: Form 3 FY 2024-2025 Q4.pdf1 Aug 2025
Disclosure of Sold and Booked InventoryFile: Sold Circular FY 2024-2025 Q4.pdf1 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Q2 (FY 24-25)_compressed.pdf19 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Q2 (FY 24-25).pdf19 Dec 2024

How this compares with Pune

78%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Tanishq Vlasta on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Alandi Rural13,700+ in Pune

2 kmTanishq VlastaCompleted 64Lapsed / revoked 33Other 98Dot size: filed unitsN

Filed coordinates, straight-line distance. 195 registered projects within 2 km.

Builder: Tanishq Realities

Tanishq Realities has 1 registration on MahaRERA, including Tanishq Vlasta. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Tanishq Vlasta is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Tanishq Vlasta?

The registered promoter entity is Tanishq Realities, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Tanishq Vlasta?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Tanishq Vlasta?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Tanishq Vlasta?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Tanishq Vlasta?

The professionals named in the filing: Architect: Mangesh Gotal; Engineer: Nikhil Mudholkar; Engineer: Ajit Dattattray Gavhane; Engineer: Shraddha Ajit Ghule; Chartered Accountant: M CHAUDHARI & ASSOCIATES; Chartered Accountant: NITISH VAIDYA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Tanishq Vlasta?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Tanishq Vlasta. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Tanishq Vlasta to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.