Home / Browse projects / Aurangabad, Maharashtra / SWAPNABAN PHASE 2

Completed No litigation declared Residential / Group Housing project

SWAPNABAN PHASE 2

By BHAISHREE VENTURES LLP

RG-MH-08232 · RERA P51500018457 · Last updated on MahaRERA portal: 26 Mar 2022

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
90 of 99Construction stages doneacross 9 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

SWAPNABAN PHASE 2 is a Residential / Group Housing project by BHAISHREE VENTURES LLP in Aurangabad, Maharashtra, registered with MahaRERA as P51500018457 on 2 Nov 2018. The registration is recorded completed; possession was promised by 30 Dec 2022.

At a glance

Project

  • NameSWAPNABAN PHASE 2
  • TypeResidential / Group Housing
  • Location
    • MAIN ROAD
    • KUMBHEFAL
    • Kubhephal
    • Aurangabad
    • 431201
  • Pincode431201
  • RERA no.P51500018457
  • ReraGenie IDRG-MH-08232

Builder

  • NameBHAISHREE VENTURES LLP
  • Entity typePartnership
  • PartnersBHAVESH RAMESHBHAI PATEL, DEEPAK INDERCHAND LUNKAD
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredNov 2018PromisedDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on2 Nov 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings9 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RH NO 1 TO 8NA10000
RH NO 9 TO 16NA10000
RH NO 17 TO 23NA10000
RH NO 24 TO 29NA10000
RH NO 30 TO 37NA10000
RH NO 38 TO 45NA10000
RH NO 50 TO 52NA10000
RH NO 53NA20000
RH NO46 TO 49NA10000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 26 Mar 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

90 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Podiums (if any), at 0%.

RH NO 1 TO 891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 9 TO 1691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 17 TO 2391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 24 TO 2991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 30 TO 3791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 38 TO 4591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 50 TO 5291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO 5391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RH NO46 TO 4991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 26 Mar 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
COMPOUND WALL ENTRANCE GATEYes100%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,110 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2135.57
Proposed, not sanctioned2,136 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGARKHEDA, AURANGABAD

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMILIND WADEKAR
EngineerRAJESH WARAGANTWAR
Chartered AccountantP S MUNDADA
PartnerRole in project
BHAISHREE VENTURES LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Oct 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 1 Feb 2022

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: Q-1 F-3 FINAL_Compressed.pdf26 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: From5_2021_Swapnaban P-II.pdf12 Mar 2022
Architect’s Certificate on Completion of Project (Form 4)File: F-4 SB-2.pdf22 Feb 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD JUN-21 FULL_Compressed.pdf9 Feb 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD SEPT-21_Compressed.pdf9 Feb 2022
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD DEC-21_Compressed.pdf9 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: occupancy approved plan sb-2_Compressed.pdf1 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Plan No-1_Compressed.pdf1 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Plan No-2_Compressed.pdf1 Feb 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FIRST OCCUPANCY SB-2.pdf31 Jan 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: SECOND OCCUPANCY SB-2-compressed.pdf31 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects certificate k332 311221.pdf29 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate K 332 SB II 030421.pdf29 May 2021
Certificates of CA (Form 3)File: CA Certificate 260521.pdf29 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate SB2.pdf15 May 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate SB2.pdf15 May 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 332 FORM 5.pdf29 Sep 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf20 Aug 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate.pdf20 Aug 2020
Certificates of CA (Form 3)File: CA Certificate.pdf20 Aug 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect 332_compressed (1).pdf30 Nov 2019
Certificates of CA (Form 3)File: CA Certificate.pdf19 Nov 2019
Annual Audit Report of Statutory CA (Form 5)File: K-332 Form 5_compressed.pdf5 Oct 2019
Building plan approvalFile: Building Permission -ilovepdf-compressed.pdf18 Oct 2018
Layout approvalFile: Final Sanction Layout Plan .pdf18 Oct 2018
PAN CardFile: Bhaishree Ventures LLP Pan Card.pdf18 Oct 2018
Copy of the legal title reportFile: Search Report K 332.pdf18 Oct 2018
Details of encumbrancesFile: Certificatee of Encumbarance K 332.pdf18 Oct 2018
Copy of Layout Approval (in case of layout)File: Final Sanction Layout Plan .pdf18 Oct 2018
Building Plan Approval (IOD)File: Building Permission -ilovepdf-compressed.pdf18 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Building Permission -ilovepdf-compressed.pdf18 Oct 2018
Declaration in FORM BFile: Affidavit Form B K 332.pdf18 Oct 2018
Certificates of CA (Form 3)File: CA Certificate Gut No 332.pdf18 Oct 2018
Proforma of Allotment letterFile: Allotment Letter K 332.pdf18 Oct 2018

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 not delivered by the promised date
ProjectLocationRegisteredStatusPromisedDelivered
BHAISHREE NISARGBANP51500030937NAKSHATRAWADI, AurangabadSep 2021OngoingApr 2026Not delivered
GEETABAN RESIDENCY PHASE-2P51500025486LASUR STATION, AurangabadJun 2020OngoingMar 2024Registered original: Sep 2023Not delivered
SWAPNABANP51500016418NEAR GRAMPANCHAYAT OFFICE, AurangabadMay 2018CompletedDec 2022Dec 2019
GEETABAN RESIDENCYP51500016327Near Railway Station, AurangabadMay 2018CompletedDec 2021Jul 2020

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is completed

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep SWAPNABAN PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KUMBHEFAL1,400+ in Aurangabad

Builder: BHAISHREE VENTURES LLP

BHAISHREE VENTURES LLP has 3 registrations on MahaRERA, including SWAPNABAN PHASE 2 and GEETABAN RESIDENCY PHASE-2. Its filings disclose 5 earlier MahaRERA projects: declares 3 of 3 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What are my rights if SWAPNABAN PHASE 2 is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SWAPNABAN PHASE 2?

The registered promoter entity is BHAISHREE VENTURES LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SWAPNABAN PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SWAPNABAN PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SWAPNABAN PHASE 2?

The professionals named in the filing: Architect: MILIND WADEKAR; Engineer: RAJESH WARAGANTWAR; Chartered Accountant: P S MUNDADA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SWAPNABAN PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SWAPNABAN PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SWAPNABAN PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.