Registration lapsed No litigation declared Residential / Group Housing project

Swapna Nagari

By Anjum Parvej Shiakh

RG-MH-13520 · RERA P52200025792 · Last updated on MahaRERA portal: 28 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 40 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Ahmednagar registration emailed to you, free during the pilot beta.
Jun 2023Possession promised40 months past this date
40 of 55Construction stages doneacross 5 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 46 documents Report an error

Swapna Nagari is a Residential / Group Housing project by Anjum Parvej Shiakh in Ahmednagar, Maharashtra, registered with MahaRERA as P52200025792 on 16 Jul 2020. Possession was promised by 30 Jun 2023 and is now 40 months past that date.

At a glance

Project

  • NameSwapna Nagari
  • TypeResidential / Group Housing
  • Location
    • Weston Chowk
    • Shrirampur
    • Bhairavnathnagar
    • Ahmednagar
    • 413709
  • Pincode413709
  • RERA no.P52200025792
  • ReraGenie IDRG-MH-13520

Builder

  • NameAnjum Parvej Shiakh
  • Entity typeIndividual

Key dates

40 months past promisethis monthRegisteredJul 2020PromisedJun 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Jul 2020
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings5 building records
  • Documents filed46 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building HNA20000
Building GNA20000
Building LNA20000
Building FNA20000
Building K1 and K2NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 28 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 0%.

Building H73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building G73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building L73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building F73%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Building K1 and K273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,889 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2614.02
Proposed, not sanctioned2,614 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWard no 2 Shrirampur

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPirzadeZS
EngineerAr. Zaheeruddin S. Pirjade
Chartered AccountantSANJAY V PAGARE & Co
PartnerRole in project
Anjum Parvej Shiakh-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jul 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jul 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 23 Apr 2025

Documents filed46

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Jun 2024.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Dec 2024.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Sep 2024.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Mar 2024.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf28 Apr 2025
Other - LegalFile: Declaration of Occupancy.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory_Swapna Nagari 30-6-23.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory_Swapna Nagari 31-12-23.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory_Swapna Nagari 30-9-23.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: Inventory_Swapna Nagari 31-3-24.pdf28 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_Swapna Nagari_2-merged.pdf23 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Apana Ghar.pdf9 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Swapna Nagari.pdf9 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Apana Ghar.pdf9 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: From 2_Swapna Nagari.pdf9 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: From 2A_March 2021_Swapna Nagari.pdf9 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: From 2A_March 2022_Swapna Nagari.pdf9 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: From 2A_March 2023_Swapna Nagari.pdf9 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3CA_Apana Ghar.pdf9 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3CA_Swapna Nagari.pdf9 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf6 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf6 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: form 5 -Final.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: form 5 Final.pdf6 Mar 2023
Copy of the legal title reportFile: Search Report1.pdf10 Jul 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Certificate of CA1.pdf6 Jul 2020
Layout approvalFile: building plan3.pdf4 Jul 2020
Building plan approvalFile: building plan3.pdf4 Jul 2020
PAN CardFile: Pan -Anjum Parvej Shikah.pdf4 Jul 2020
Details of encumbrancesFile: Self Declaration.pdf4 Jul 2020
Copy of Layout Approval (in case of layout)File: building plan3.pdf4 Jul 2020
Building Plan Approval / NA Order for plotted developmentFile: building plan3.pdf4 Jul 2020
Commencement Certificates / NA Order for plotted developmentFile: Paravana1.pdf4 Jul 2020
Declaration in FORM BFile: Affidavit cum Declaration.pdf4 Jul 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architecht Certificate.pdf4 Jul 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Cerificate.pdf4 Jul 2020
Proforma of Allotment letterFile: Allotment Letter.pdf4 Jul 2020
Proforma of Allotment letterFile: Agreement for Sales3.pdf4 Jul 2020

How this compares with Ahmednagar

7%of Ahmednagar projects moved their completion datethis one has not
28%of Ahmednagar registrations have lapsed or been cancelledthis one is among them

Computed across the 490+ Ahmednagar projects on ReraGenie, from their own filings.

Keep Swapna Nagari on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shrirampur490+ in Ahmednagar

Builder: Anjum Parvej Shiakh

Anjum Parvej Shiakh has 1 registration on MahaRERA, including Swapna Nagari. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Ahmednagar district page.

Frequently asked questions

What does it mean that Swapna Nagari shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Swapna Nagari is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Swapna Nagari?

The registered promoter entity is Anjum Parvej Shiakh, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Swapna Nagari?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Swapna Nagari?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Swapna Nagari?

The professionals named in the filing: Architect: PirzadeZS; Engineer: Ar. Zaheeruddin S. Pirjade; Chartered Accountant: SANJAY V PAGARE & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Swapna Nagari?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Swapna Nagari. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Swapna Nagari to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.