Home / Browse projects / Gandhinagar, Gujarat / Suparn Residency

Valid until 31 Mar 2023 Residential/Group Housing project

Suparn Residency

By Suparn Developers

RG-GJ-66384 · RERA PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09111/290921 · Last updated on GujRERA portal: 2 Nov 2022

Source: official GujRERA filing

Red flags

  • No red flags in this filing

Clear

  • Completion date never moved
  • Separate project account declared
Mar 2023Possession promisedno revision filed
7 of 7Construction stages doneevery applicable stage filed complete
0 of 42Units unsoldnot recorded sold or booked
Jump to the 40 documents Report an error

Suparn Residency is a Residential/Group Housing project by Suparn Developers in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09111/290921 on 29 Sep 2021. Possession is promised by 31 Mar 2023. 42 of the 42 units on this registration are recorded sold or booked, and 7 of 7 construction stages are filed complete.

At a glance

Project

  • NameSuparn Residency
  • TypeResidential/Group Housing
  • Location
    • Suparn Residency
    • Opp Vaijnath Avenue
    • B/h D- Mart
    • Kalol.
    • Kalol
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09111/290921
  • ReraGenie IDRG-GJ-66384

Builder

  • NameSuparn Developers
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredSep 2021PromisedMar 2023

Key facts

Registration and timeline

  • StatusValid until 31 Mar 2023
  • Registered on29 Sep 2021
  • Promised completion31 Mar 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed40 files

Current status

100%42 of 42 units booked
100.0%Of the estimated cost spent so far

Figures as on 2 Nov 2022, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block-A---42042

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 2 Nov 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 7 construction stages are filed complete.

Block-A: 100% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats100%
Sanitary fittings within the flats100%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing100%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing100%

Progress on shared amenities19

As on 2 Nov 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes100%
Water supplyYes100%
Sewerage (chamber, lines, septic tank, STP)Yes100%
Storm water drainsNoNot applicable
Landscaping and tree plantingYes100%
Street lightingYes100%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalNoNot applicable
Water conservation, rain water harvestingYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationNoNot applicable
Fire fightingYes100%
Drinking water facilitiesYes100%
Emergency evacuationNoNot applicable
Use of renewable energyNoNot applicable
SecurityYes100%
Letter boxNoNot applicable

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area856 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 2.70 cr
Cost incurredRs 2.70 cr
Spent of the estimate100.0%
BuildingWingEstimatedIncurred
Block-ANARs 2.70 crRs 2.70 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectK C Patel
EngineerAarti Patel

Documents filed40

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/KALOL/AUDA/RAA09111/290921 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect's certificate (Form 1)2 Nov 2022
Engineer's certificate (Form 2)2 Nov 2022
Engineer's certificate annexure2 Nov 2022
Accountant's certificate (Form 3)2 Nov 2022
Site photograph, Block-A2 Nov 2022
RERA registration certificate29 Sep 2021
Proforma agreement for sale-
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Proforma allotment letter-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

100%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one has not

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep Suparn Residency on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSuparn ResidencyOther 68Dot size: filed unitsN

Filed coordinates, straight-line distance. 68 registered projects within 2 km.

Builder: Suparn Developers

Suparn Developers has 1 registration on GujRERA, including Suparn Residency. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if Suparn Residency is delayed beyond 31 Mar 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of Suparn Residency?

The registered promoter entity is Suparn Developers, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in Suparn Residency?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Suparn Residency?

The professionals named in the filing: Architect: K C Patel; Engineer: Aarti Patel. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Suparn Residency?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Suparn Residency. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Suparn Residency to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.