Home / Browse projects / Dakshina Kannada, Karnataka / SUNSHINE SAPLING
SUNSHINE SAPLING
By SAPLING MULTI VENTURES PRIVATE LIMITED
RG-KA-08498 · RERA PRM/KA/RERA/1257/334/PR/100823/006136 · Last updated on RERA Karnataka portal: 8 Aug 2023
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
SUNSHINE SAPLING is a Mixed Development project by SAPLING MULTI VENTURES PRIVATE LIMITED in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/100823/006136 on 10 Aug 2023. Possession is promised by 31 Dec 2029.
At a glance
Project
- NameSUNSHINE SAPLING
- TypeMixed Development
- Location
- Mangalore
- Dakshina Kannada
- 574142
- Pincode574142
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1257/334/PR/100823/006136
- ReraGenie IDRG-KA-08498
Builder
- NameSAPLING MULTI VENTURES PRIVATE LIMITED
- Entity typeCompany
- CINU70109MH2022PTC382230
- GSTIN27ABICS4597C1Z0
- Authorized SignatoryPRAMILA CRASTA
- Managing DirectorPRAMILA CRASTA
- DirectorALWYN DINESH CRASTA
- Project HeadDHEERAJ MITHRA
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on10 Aug 2023
- Promised completion31 Dec 2029
- Revised completionNone
- Buildings1 building record
- Documents filed82 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUNSHINE SAPLING | - | - | - | - | - | 42 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 8 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | - |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 8 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | Yes | - |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | No | Not applicable |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | - |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | No | Not applicable |
| Water and Sanitation | No | Not applicable |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | No | Not applicable |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership5
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SAPLING MULTI VENTURES PVT.LTD | - | - |
| SAPLING MULTI VENTURES PVT LTD | - | - |
| SAPLING MULTI VENTURES PVT LTD | - | - |
| SAPLING MULTI VENTURES PVT LTD | - | - |
| SAPLING MULTI VENTURES PVT LTD | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 11.61 cr | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PRAVEEN SALDANHA |
| Engineer | DHEERAJ MITHRA |
| Chartered Accountant | VITTAL CHATHRE M |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed82
As listed on the registration, under the names the promoter filed them with; the newest 80 of 82 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/100823/006136 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| SANCTION PLAN REVISEDFile: sanction approved plan revised.pdf | 8 Aug 2023 |
| REVISED APPROVED PLAN 1File: approved plan 1_compressed.pdf | 8 Aug 2023 |
| REVISED APPROVED PLAN 2File: approved plan 2_compressed.pdf | 8 Aug 2023 |
| LICENCE ORDER COPY-TALUK PANCHAYATH TECHINCAL ORDERFile: licence order copy.pdf | 8 Aug 2023 |
| REVISED LICENCE ORDER COPY FROM GRAM PANCHAYATHFile: Building Licence revised.pdf | 8 Aug 2023 |
| SEARCH REPORTFile: search report.pdf | 8 Aug 2023 |
| KATHA-COMMERCIAL PLOTFile: Khata Site 37- Sapling.pdf | 25 Jul 2023 |
| APPROVED LAYOUT PLANFile: approved layout plan - highlighted commerical plot.pdf | 25 Jul 2023 |
| CLARIFICATION ON CONVERSIONFile: clarification on conversion.pdf | 25 Jul 2023 |
| PLLOUTION NOC CHALLANFile: KSPCB challan.pdf | 25 Jul 2023 |
| AFFIDAVIT FOR POLLUTION NOCFile: affidavit for pollution noc.pdf | 25 Jul 2023 |
| FEE PAYMENT CHALLAN-FOR REGISTARTION FEEFile: challan-sapling.pdf | 25 Jul 2023 |
| CLARIFICATIONFile: clarification.pdf | 25 Jul 2023 |
| RTC, survey 151100300100222494 | - |
| Mutation, survey 151100300100222494 | - |
| Encumbrance Certificate, survey 151100300100222494 | - |
| Conversion/Alienation Order, survey 151100300100222494 | - |
| Sale/Title/Gift Deed, survey 151100300100222494 | - |
| Khatha, survey 151100300100222494 | - |
| Registration CertificateFile: Certificate of Incorporation SMVPL.pdf | - |
| Organization StructureFile: organization chart.pdf | - |
| Certificate issued by CA Form 1File: Form 1 CA cert RERA_compressed.pdf | - |
| Certificate issued by Architect Form 2File: Architect certificate.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer Certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit No litigation on the land.pdf | - |
| Certificate from Chartered AccountFile: Form 1 CA cert RERA_compressed.pdf | - |
| Balance Sheet 2021 - 2022File: BS 2023.pdf | - |
| Audited Profit and Loss Statement 2021 - 2022File: PL 20223.pdf | - |
| Cash Flow Statement 2021 - 2022File: Schedule on BS 2023.pdf | - |
| Auditor's Report 2021 - 2022File: AR 2023.pdf | - |
| Building License_compressed | - |
| Approved sanction Plan | - |
| approved layout plan | - |
| Approved sanction Plan | - |
| Approved sanction Plan | - |
| Approved sanction Plan | - |
| specification | - |
| approved layout plan | - |
| approved layout plan | - |
| Structural stability Certificate | - |
| title deed | - |
| conversion residential | - |
| conversion residential | - |
| mother deed | - |
| proforma AOS | - |
| proforma allotment letter | - |
| Brochure | - |
| form b | - |
| affidavit 3(1) | - |
| Electricity -NOC | - |
| water noc | - |
| Unnamed document | - |
| Unnamed document | - |
| FIRE NOC | - |
| Airport - NOC_compressed | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| danapatra order copy | - |
| STP drawing | - |
| guidance value | - |
| Approved Plan- 1 | - |
| Approved Plan - 2 | - |
| estimation cost by engineer | - |
| Electricity NOC-challan | - |
| certified area statement | - |
| village map | - |
| Occupancy CertificateFile: OC.pdf | - |
| Architect certificate for having completed the work(in format no 5)File: architect certificate-completion.pdf | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Dakshina Kannada
Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.
Keep SUNSHINE SAPLING on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dakshina Kannada620+ in Dakshina Kannada
FORTUNE GALAXY
FORTUNE PROMOTERS
LYCORIS AMIN CENTRE
ABDUL RAHIMAN ZUBAIR AND DAYANAND SOMAPPA
ROHAN CITY
ROHAN CORPORATION INDIA PRIVATE LIMITED
Bearys Turning Point
Bearys Properties and Developments Private
YAMUNA SKY CITY
YAMUNA HOMES AND DESIGN PRIVATE LIMITED
The Marian Park
Marian Projects Pvt Ltd
See every Dakshina Kannada project, with the district possession charts
Builder: SAPLING MULTI VENTURES PRIVATE LIMITED
SAPLING MULTI VENTURES PRIVATE LIMITED has 1 registration on RERA Karnataka, including SUNSHINE SAPLING. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.
Frequently asked questions
What are my rights if SUNSHINE SAPLING is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SUNSHINE SAPLING?
The registered promoter entity is SAPLING MULTI VENTURES PRIVATE LIMITED, a company as per the filing. Its CIN U70109MH2022PTC382230 and GSTIN 27ABICS4597C1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SUNSHINE SAPLING?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SUNSHINE SAPLING?
The professionals named in the filing: Architect: PRAVEEN SALDANHA; Engineer: DHEERAJ MITHRA; Chartered Accountant: VITTAL CHATHRE M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUNSHINE SAPLING?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.
Report an error Share feedback