Home / Browse projects / Pune, Maharashtra / Sun City - Ambegaon Phase - III

Registration lapsed No litigation declared Residential / Group Housing project

Sun City - Ambegaon Phase - III

By Mittal Projects

RG-MH-96817 · RERA P52100051600 · Last updated on MahaRERA portal: 27 Apr 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 7 months past the filed date
  • 1 complaint at MahaRERA
  • Rs 32.00 crore secured on the land, in favour of Godrej Finance Limited

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2026Possession promised7 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 10%
91 of 276Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 89 documents Report an error

Sun City - Ambegaon Phase - III is a Residential / Group Housing project by Mittal Projects in Pune, Maharashtra, registered with MahaRERA as P52100051600 on 27 Jun 2023. Possession was promised by 31 Mar 2026 and is now 7 months past that date. 185 of the 276 units on this registration are recorded sold or booked, and 20 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSun City - Ambegaon Phase - III
  • TypeResidential / Group Housing
  • Location
    • -
    • AMBEGAON Bk
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051600
  • ReraGenie IDRG-MH-96817

Builder

  • NameMittal Projects
  • Entity typePartnership
  • PartnersNaresh Ramchandra Mittal, Ashok Ramchandra Mittal
  • Other registrations3 more →
  • Completed2 of 4
  • No longer live1 lapsed, de-registered or revoked

Key dates

7 months past promisethis monthRegisteredJun 2023PromisedMar 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 Jun 2023
  • Promised completion31 Mar 2026
  • Revised completionNone
  • Buildings2 building records
  • Documents filed89 files

Current status

67%185 of 276 units booked
92.8%Work done, per cost certificate

Figures as on 27 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ENA27231380138
FNA26231380138

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 10%.

E92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F92%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area8,107 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofGodrej Finance Limited
Secured amountRs 32.00 crore
CERSAI search filedYes
Declared on29 Jan 2026

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI28316.72
Proposed, not sanctioned24,611 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNanded City, Pune
Estimated costRs 100.47 cr
Cost incurredRs 93.27 cr
Work done92.84%
BuildingWingEstimatedIncurred
ENARs 50.23 crRs 46.64 cr
FNARs 50.23 crRs 46.64 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArch Prakash Kulkarni
EngineerDelcons Consultants India Private Limited
EngineerGAJANAN SATAPA SUTAR
Chartered AccountantCA Shivasnhi Deepak Mittal
PartnerRole in project
Mittal Projects-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500246Ram GawaliMittal Projects29/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 May 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed89

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form1.pdf27 Apr 2026
Withdrawal Update Form 1File: Form1.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf27 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf27 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf27 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf22 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf22 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf22 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf16 Dec 2025
Withdrawal Update Form 2File: FORM 2.pdf16 Dec 2025
Withdrawal Update Form 3File: FORM 3.pdf16 Dec 2025
Form 1File: FORM 1 PHASE III JULY 2025.pdf14 Jul 2025
Form 2File: Form 2 Phase III July 2025.pdf14 Jul 2025
Form 3File: Form 3 Phase III July 2025.pdf14 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Phase III July 2025.pdf14 Jul 2025
Self-declaration of Quarterly ProgressFile: Self Declaration Phase III July 2025.pdf14 Jul 2025
Form 1File: Form 1- Phase III - Q 4.pdf13 Jun 2025
Form 2File: Form 2 - Phase III Q 4.pdf13 Jun 2025
Form 3File: Form 3 Phase III March 2025.pdf13 Jun 2025
Disclosure of Sold and Booked InventoryFile: Sales Report Phase III March 2025.pdf13 Jun 2025
Self-declaration of Quarterly ProgressFile: Declaration - Phase III.pdf13 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase III.pdf19 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PHASE III.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Phase III.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Phase III.pdf20 Feb 2025
Layout approvalFile: 1-26.pdf15 Jan 2025
Building plan approvalFile: 2-26.pdf15 Jan 2025
Building plan approvalFile: 3-26.pdf15 Jan 2025
Building plan approvalFile: 4-26.pdf15 Jan 2025
Building plan approvalFile: 22-26.pdf15 Jan 2025
Building plan approvalFile: 23-26.pdf15 Jan 2025
Building plan approvalFile: 24-26.pdf15 Jan 2025
Building plan approvalFile: 25-26.pdf15 Jan 2025
Copy of Layout Approval (in case of layout)File: 1-26.pdf15 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: 26-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 4-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 25-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 24-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 23-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 22-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 3-26.pdf15 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: 2-26.pdf15 Jan 2025
Declaration about Commencement CertificateFile: Declaratin Phase III.pdf14 Jan 2025
Disclosure of sold/ booked inventoryFile: E SunCutyAmbegaon Sale.pdf13 Nov 2024
Disclosure of sold/ booked inventoryFile: F SUNCITYAMBEGAON SALES.pdf13 Nov 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Mortgage.pdf23 Oct 2024
Declaration in FORM BFile: Form B - Scan.pdf23 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Mortgage.pdf23 Oct 2024
Proforma of Agreement for saleFile: Agreement Draft Revised - Phas III - 23-10-2024.pdf23 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase 3.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase III.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase III.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Phase III.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 SunCityAmbegaonPhaseIII.pdf16 Aug 2024
Layout approvalFile: 1-26_SunCity_compressed.pdf30 Apr 2024
Copy of Layout Approval (in case of layout)File: 1-26_SunCity_compressed.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 3.pdf9 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Phase III - Sun City.pdf8 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Phase III - 19 Oct 2023.pdf8 Nov 2023
Other - TechnicalFile: Self Declaration - Account change - Suncity Phs 3.pdf2 Sep 2023
Other - TechnicalFile: Declaration cum Undertaking Bank Ac - Ph III.pdf2 Sep 2023
Other - FinanceFile: Declaration cum Undertaking Bank Ac - Ph III.pdf18 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sun City Phase III.pdf19 Jun 2023
CERSAI detailsFile: Self Declaration for Encumbrances_Sun City III.pdf31 May 2023
Proforma of Agreement for saleFile: Agreement Draft.pdf31 May 2023
Deviation Report with respect to Allotment letterFile: Deviation Report - Allotment.pdf31 May 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report - Agreement.pdf31 May 2023
Declaration about Commencement CertificateFile: Declaration Commencement.pdf20 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Naresh Mittal.pdf20 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Ashok Mittal.pdf20 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Account.pdf20 May 2023
Layout approvalFile: Layout.pdf19 May 2023
Building plan approvalFile: IOD 1.pdf19 May 2023
Building plan approvalFile: IOD 2.pdf19 May 2023
Building plan approvalFile: IOD 3.pdf19 May 2023
Building plan approvalFile: IOD 4.pdf19 May 2023
PAN CardFile: PAN - MITTAL PROJECTS.pdf19 May 2023
Copy of the legal title reportFile: Search Report.pdf19 May 2023
Details of encumbrances concerned to FinanceFile: Self Declaration for Encumbrances.pdf19 May 2023

How this compares with Pune

67%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sun City - Ambegaon Phase - III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near -13,700+ in Pune

2 kmSun City - Ambegaon PhasCompleted 84Lapsed / revoked 35Other 56Dot size: filed unitsN

Filed coordinates, straight-line distance. 175 registered projects within 2 km.

Builder: Mittal Projects

Mittal Projects has 4 registrations on MahaRERA, including Sun City - Ambegaon Phase-I and Sun City - Ambegaon Phase-II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Sun City - Ambegaon Phase - III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sun City - Ambegaon Phase - III is delayed beyond 31 Mar 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sun City - Ambegaon Phase - III?

The registered promoter entity is Mittal Projects, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sun City - Ambegaon Phase - III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Sun City - Ambegaon Phase - III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Sun City - Ambegaon Phase - III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sun City - Ambegaon Phase - III?

The professionals named in the filing: Architect: Arch Prakash Kulkarni; Engineer: Delcons Consultants India Private Limited; Engineer: GAJANAN SATAPA SUTAR; Chartered Accountant: CA Shivasnhi Deepak Mittal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sun City - Ambegaon Phase - III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sun City - Ambegaon Phase - III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sun City - Ambegaon Phase - III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.