Home / Browse projects / Sumer Samaq Prime

Registration lapsed No litigation declared Residential / Group Housing project

Sumer Samaq Prime

By Samaq Builders Private Limited

RG-MH-04524 · RERA P51900022219 · Last updated on MahaRERA portal: 4 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 41 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jun 2026Possession promised4 months past this date
8 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
17 of 65Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

Sumer Samaq Prime is a Residential / Group Housing project by Samaq Builders Private Limited in Lower Parel, 400013, registered with MahaRERA as P51900022219 on 5 Sep 2019. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 41 months from the original filing. 48 of the 65 units on this registration are recorded sold or booked, and 8 of 22 construction stages are filed complete.

At a glance

Project

  • NameSumer Samaq Prime
  • TypeResidential / Group Housing
  • Location
    • N M Joshi Marg
    • Lower Parel
    • 400013
  • Pincode400013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900022219
  • ReraGenie IDRG-MH-04524

Builder

  • NameSamaq Builders Private Limited
  • Entity typeCompany
  • CINU45309MH2023PTC398021
  • GSTIN27ABKCS2427F1ZB
  • PartnersRahul Ramesh Shah, Pavan Ramesh Shah
  • Declared earlier projects1 →

Key dates

4 months past promisethis monthRegisteredSep 2019First promiseJan 2023Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Sep 2019
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Jan 2023)
  • Buildings2 building records
  • Documents filed103 files

Current status

74%48 of 65 units booked
54.9%Work done, per cost certificate

Figures as on 4 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sumer samaq Prime Sale BuildingNA242365065
Rehab BuildingNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

Sumer samaq Prime Sale Building80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Rehab Building80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 4 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed60

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots60
Closed/Covered60

Land and ownership3

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,008 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Sep 2024
LandownerVillageDistrict
Victoria Iron and Metal Warehousing Pvt. Ltd.-Mumbai City
Sumer Samaq Prime-Mumbai City
Samaq Builders Pvt. Ltd.KurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI5956.98
Proposed, not sanctioned5,842 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No - 6,7 Ground Floor Botawalla Bldg Horniman Circle Mumbai 400001
Estimated costRs 55.00 cr
Cost incurredRs 30.22 cr
Work done54.94%
BuildingWingEstimatedIncurred
Sumer samaq Prime Sale BuildingNARs 26.95 crRs 15.11 cr
Rehab BuildingNARs 26.95 crRs 15.11 cr
-NARs 1.10 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectID ASSOCIATES
EngineerSK Consultants & Engineers
Chartered AccountantPRANAV BHASKARAN & ASSOCIATES
PartnerRole in project
Samaq Builders Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900008911Jan 2023 → Dec 2023

Reason as filed by the promoterThe Project has been delayed on account of various reasons beyond our control and more particularly due to Lockdown announced on account of pandemic of Covid-19. Due to this unprecedented crises, we have witnessed the reverse migration of labourers and shortage of liquidity in the market. Moreover various private and Government offices have not been working at full strength and the complete supply chain has broken down. It appears that it is going to take a lot of time to normalize the real estate industry.

EXT51900024139Jan 2023 → Jun 2026

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 69.23% allottees for purpose of extension of RERA registration period of the said project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Jun 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement certificateFile: Revalidation issue letter.pdf4 Jun 2026
Withdrawal Update Form 1File: Form 1 (2).pdf4 Jun 2026
Withdrawal Update Form 1File: Form 1 Sept.pdf4 Jun 2026
Withdrawal Update Form 1File: Form 1 Sept.pdf4 Jun 2026
Withdrawal Update Form 2File: Sumer Samaq Form 2.pdf4 Jun 2026
Withdrawal Update Form 2File: Form 2 - Sumer Samaq Prime as on Sept 2025.pdf4 Jun 2026
Withdrawal Update Form 2File: Form 2 (Dec 25).pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3 - Sumer Samaq Prime 31st March 2026.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3 - Sumer Samaq Prime 30th September 2025.pdf4 Jun 2026
Withdrawal Update Form 3File: Form 3 (Dec 25).pdf4 Jun 2026
Building plan approvalFile: SumerSamaqPlans03092025.pdf20 Sep 2025
Building plan approvalFile: Amendment Letter SSP 28082025.pdf20 Sep 2025
Withdrawal Update Form 1File: Form 1 .pdf20 Sep 2025
Withdrawal Update Form 2File: Form 2 as on 30-06-2025.pdf20 Sep 2025
Withdrawal Update Form 3File: Form 3 as on 30-06-2025.pdf20 Sep 2025
Commencement Certificates / NA Order for plotted developmentFile: 2467722_FurtherCC_signed.pdf8 Mar 2025
Proforma of Agreement for saleFile: Agreement for Sale- Sumer Samaq Prime.pdf15 Nov 2024
Copy of the legal title reportFile: Title Certificate-Sumer Samaq Prime.pdf31 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sumer Samaq Prime (1).pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sumer Samaq Prime.pdf27 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Sumer Prime as on March 2024.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- December 2022.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- March 2023.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- June 2023.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- September 2023.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- December 2023.pdf15 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- March 2024.pdf15 Jun 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- December 2022_4_11zon.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- March 2023_6_11zon.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- June 2023_5_11zon.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- September 2023_2_11zon.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3-December 2023_3_11zon.pdf15 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- March 2024_1_11zon.pdf15 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf15 Jun 2024
Declaration about Commencement CertificateFile: Format D Declaration of Commencement Certificate.pdf11 Jun 2024
Declaration in FORM BFile: Form B-Affidavit Cum Declartion with Notary.pdf11 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A (2021-22).pdf11 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A (2022-23).pdf11 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A (2023-24).pdf11 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf3 Jun 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A.pdf3 Jun 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf3 Jun 2024
Layout approvalFile: SUMER SAMAQ PRIME_IOD 1-1.pdf6 May 2024
Layout approvalFile: SUMER SAMAQ PRIME_IOD 1-1.pdf6 May 2024
Building plan approvalFile: SUMER SAMAQ PRIME_IOD 1-1.pdf6 May 2024
Building plan approvalFile: SUMER SAMAQ PRIME_IOD 1-2.pdf6 May 2024
Building plan approvalFile: SUMER SAMAQ PRIME_IOD 1-3.pdf6 May 2024
Building plan approvalFile: SUMER SAMAQ PRIME_IOD 1-4.pdf6 May 2024
Building plan approvalFile: SUMER SAMAQ PRIME_IOD 1-5.pdf6 May 2024
Copy of Layout Approval (in case of layout)File: SUMER SAMAQ PRIME_IOD 1-1.pdf6 May 2024
Copy of Layout Approval (in case of layout)File: SUMER SAMAQ PRIME_IOD 1-1.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SUMER SAMAQ PRIME_IOD 1-1.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SUMER SAMAQ PRIME_IOD 1-2.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SUMER SAMAQ PRIME_IOD 1-3.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SUMER SAMAQ PRIME_IOD 1-4.pdf6 May 2024
Building Plan Approval / NA Order for plotted developmentFile: SUMER SAMAQ PRIME_IOD 1-5.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf6 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC - Sumer Prime.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 12 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Prime March 2022.pdf29 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Prime June 2022.pdf29 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Sumer Prime as on September 2022.pdf29 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Prime March 2022.pdf29 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Prime June 22.pdf29 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Sumer Prime as on September 2022.pdf29 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Sumer Prime Form 5.pdf12 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- ARCHITECT CERTIFICATE- SUMER PRIME.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sumer Prime.pdf4 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Prime June 2021_compressed.pdf20 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Prime Sept 2021_compressed.pdf20 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sumer Prime Dec 2021_compressed.pdf20 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 SUMER PRIME.pdf19 Apr 2022
CERSAI detailsFile: Sumer Prime.pdf19 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Prime 30th June 2021.pdf19 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Prime 30th September 2021.pdf19 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sumer Prime 31st December 2021.pdf19 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Sumer Prime FY 2019-2020_compressed.pdf27 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Sumer Prime FY 2020-21_compressed.pdf27 Sep 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SUMER ARMONIAP51900029518Mazgaon142Jun 2021OngoingJun 2025Not delivered

Keep Sumer Samaq Prime on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Lower Parel

2 kmSumer Samaq PrimeCompleted 22Lapsed / revoked 11Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: Samaq Builders Private Limited

Samaq Builders Private Limited has 1 registration on MahaRERA, including Sumer Samaq Prime. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record.

Frequently asked questions

What does it mean that Sumer Samaq Prime shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sumer Samaq Prime is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sumer Samaq Prime?

The registered promoter entity is Samaq Builders Private Limited, a company as per the filing. Its CIN U45309MH2023PTC398021 and GSTIN 27ABKCS2427F1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sumer Samaq Prime?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sumer Samaq Prime?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sumer Samaq Prime?

The professionals named in the filing: Architect: ID ASSOCIATES; Engineer: SK Consultants & Engineers; Chartered Accountant: PRANAV BHASKARAN & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sumer Samaq Prime?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sumer Samaq Prime. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sumer Samaq Prime to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.