Home / Browse projects / Mumbai Suburban, Maharashtra / Sultanabad Apartment

Registration lapsed No litigation declared Residential / Group Housing project

Sultanabad Apartment

By S. E. BUILDERS

RG-MH-97815 · RERA P51800019309 · Last updated on MahaRERA portal: 15 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 99%
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

Sultanabad Apartment is a Residential / Group Housing project by S. E. BUILDERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800019309 on 23 Jan 2019. Possession was promised by 25 Dec 2024 and is now 22 months past that date. The completion date has moved by 48 months from the original filing.

At a glance

Project

  • NameSultanabad Apartment
  • TypeResidential / Group Housing
  • Location
    • Beside Sultanabad Darshan Bldg
    • Village Oshivara
    • Taluka Andheri
    • Andheri
    • Mumbai Suburban
    • 400102
  • Pincode400102
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800019309
  • ReraGenie IDRG-MH-97815

Builder

  • NameS. E. BUILDERS
  • Entity typePartnership
  • PartnersAbdul Khalique Tannvar, Arif Akbar Hussain Khatri

Key dates

22 months past promisethis monthRegisteredJan 2019First promiseDec 2020Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Jan 2019
  • Promised completion25 Dec 2024
  • Revised completionRevised to 25 Dec 2024 (originally 25 Dec 2020)
  • Buildings1 building record
  • Documents filed67 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Sultanabad ApartmentsNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 99%.

Sultanabad Apartments: 100% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises99%
Sanitary Fittings within the flats / premises99%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks99%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.99%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.99%

Progress on shared amenities15

As on 15 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes99%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes99%
Storm Water DrainsYes99%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes99%
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes99%
Electrical meter room, sub-station, receiving stationYes99%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered18

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area655 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Sultanabad Apartment CHS LtdAndheriMumbai Suburban

Approvals and building plan

Permissible FSI1769.18
Proposed, not sanctioned1,760 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGr Floor, Jamuna Amrut CHS Ltd, Near MTNL, S V Road, Jogeshwari West, Mumbai 400102

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectChandrashekhar Vinayak Oak
EngineerSanjay Rane
EngineerSK Consultants & Engineers
Chartered AccountantGaurav S Rajpal & Co
Chartered AccountantVidya S. Bhure & Co.
PartnerRole in project
S. E. BUILDERS-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013021Dec 2020 → Dec 2024

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 92.86% allottees for purpose of extension of RERA registration period of the said project.

EXT51800002446Dec 2020 → Dec 2021

Reason as filed by the promoterThe Work has got delayed in the initial construction stage. Keeping the time as an essence in the agreement, we felt the need to extend the completion date by 1 year. The construction work is in full flow right now. Also, we would like to mention that till date there is one allottee with whom we have entered into the agreement.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jan 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf15 Feb 2025
Certificates of CA (Form 3)File: 17 Certificates of CA (Form 3).pdf15 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf15 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf16 Jul 2024
Certificates of CA (Form 3)File: 16 Certificates of CA (Form 3).pdf16 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sultanabad Apartment as on December 2023.pdf26 Feb 2024
Certificates of CA (Form 3)File: Form 3 Sultanabad Apartment as on 31-12-2023.pdf26 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Sultanabad Apartment as on 16-10-2023.pdf17 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sultanabad Apartment as on September 2023.pdf17 Oct 2023
Certificates of CA (Form 3)File: Form 3- Sultanabad Apartment as on 30-09-2023.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Sultanabad Apartment for FY 2022-23.pdf30 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sultanabad Apartment as on June 2023.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sultanabad Apartment as on 31-03-2023.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sultanabad Apartment as on June 2023.pdf21 Jul 2023
Certificates of CA (Form 3)File: Form 3- Sultanabad Apartment as on 31-03-2023.pdf21 Jul 2023
Certificates of CA (Form 3)File: Form 3- Sultanabad Apartment as on 30-06-2023.pdf21 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2- Sultanabad Apartment as on December 2022.pdf28 Jun 2023
Certificates of CA (Form 3)File: Form 3- Sultanabad Apartment as on December 2022.pdf28 Jun 2023
Declaration about Commencement CertificateFile: Format D Sultanabad.pdf5 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20 Sultanabad.pdf5 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21 Sultanabad.pdf5 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22 Sultanabad.pdf5 Dec 2022
Disclosure of sold/ booked inventoryFile: Circular 29 Sultanabad.pdf5 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sultanabad Apartment Form 2- September 2022.pdf10 Oct 2022
Certificates of CA (Form 3)File: Form 3 as on September 2022.pdf10 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Sultanabad Apartment Form 2 as on June 2022.pdf4 Oct 2022
Certificates of CA (Form 3)File: Form 3 as on June 2022_compressed.pdf4 Oct 2022
Certificates of CA (Form 3)File: Form 3 as on June 2022_compressed.pdf4 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sultanabad Apt March 2022_compressed.pdf15 Jun 2022
CERSAI detailsFile: Sultanabad Apartment.pdf15 Jun 2022
Certificates of CA (Form 3)File: Form 3 Sultanabad Marrch 2022.pdf15 Jun 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sultanabad Apt Sept 2021.pdf18 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sultanabad Apt Dec 2021.pdf18 Jan 2022
Certificates of CA (Form 3)File: Form 3 Certificate 258.pdf18 Jan 2022
Certificates of CA (Form 3)File: Form 3 Certificate 257.pdf18 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sultanabad Apartment Mar 2021.pdf28 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 SE Builders -June 2021.pdf28 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sultanabad Apartment Dec 2020_compressed.pdf28 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Sultanabad Apartment Sept 2020 (1)_compressed.pdf28 Jul 2021
Certificates of CA (Form 3)File: Form 3 Sultanabad Apartment June2021_compressed.pdf28 Jul 2021
Certificates of CA (Form 3)File: Form 3 Sultanabad Apartment sept.pdf28 Jul 2021
Certificates of CA (Form 3)File: Form 3 Sultanabad Apartment Dec 2020.pdf28 Jul 2021
Certificates of CA (Form 3)File: Form 3 Sultanabad Apartment March 2021.pdf28 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: 2278268_FurtherCC_signed (1).pdf26 Jul 2021
Layout approvalFile: Aarifbhai layout 01.pdf17 Jan 2019
Layout approvalFile: Aarifbhai layout 02-converted.pdf17 Jan 2019
Copy of Layout Approval (in case of layout)File: Aarifbhai layout 01.pdf17 Jan 2019
Copy of Layout Approval (in case of layout)File: Aarifbhai layout 02-converted.pdf17 Jan 2019
Certificates of CA (Form 3)File: Arifbhai Final C A Certificate 119.pdf17 Jan 2019
Building plan approvalFile: Arifbhai_IOD.pdf30 Dec 2018
Layout approvalFile: p02.pdf30 Dec 2018
Layout approvalFile: p03.pdf30 Dec 2018
Layout approvalFile: p04.pdf30 Dec 2018
PAN CardFile: Pancard-converted.pdf30 Dec 2018
Copy of the legal title reportFile: Arifbhai_Certificate of title.pdf30 Dec 2018
Details of encumbrancesFile: Arifbhai_Non encumbrance.pdf30 Dec 2018
Copy of Layout Approval (in case of layout)File: p02.pdf30 Dec 2018
Copy of Layout Approval (in case of layout)File: p03.pdf30 Dec 2018
Copy of Layout Approval (in case of layout)File: p04.pdf30 Dec 2018
Building Plan Approval (IOD)File: Arifbhai_IOD.pdf30 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Arifbhai-CC.pdf30 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Further cc certificate.pdf30 Dec 2018
Declaration in FORM BFile: Arifbhai-affidavit.pdf30 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arifbhai_Architect certificate.pdf30 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate for Maha RERA for SE builders.pdf30 Dec 2018
Proforma of Allotment letterFile: Arifbhai_agreement for sale.pdf30 Dec 2018

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sultanabad Apartment on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Oshivara, Taluka Andheri6,700+ in Mumbai Suburban

2 kmSultanabad ApartmentCompleted 122Lapsed / revoked 55Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 255 registered projects within 2 km.

Builder: S. E. BUILDERS

S. E. BUILDERS has 1 registration on MahaRERA, including Sultanabad Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Sultanabad Apartment shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Sultanabad Apartment is delayed beyond 25 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sultanabad Apartment?

The registered promoter entity is S. E. BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sultanabad Apartment?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sultanabad Apartment?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sultanabad Apartment?

The professionals named in the filing: Architect: Chandrashekhar Vinayak Oak; Engineer: Sanjay Rane; Engineer: SK Consultants & Engineers; Chartered Accountant: Gaurav S Rajpal & Co; Chartered Accountant: Vidya S. Bhure & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sultanabad Apartment?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sultanabad Apartment. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sultanabad Apartment to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.