STAR PLAZA

By SEVENSTAR DEVELOPERS

RG-MH-25492 · RERA P51800006698 · Last updated on MahaRERA portal: 21 Jul 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 48 months from the original
16 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 90%
169 of 273Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 158 documents Report an error

STAR PLAZA is a Others project by SEVENSTAR DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800006698 on 16 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 104 of the 273 units on this registration are recorded sold or booked, and 16 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSTAR PLAZA
  • TypeOthers
  • Location
    • carter cross road no 1
    • borivali east
    • Borivali
    • Mumbai Suburban
    • 400066
  • Pincode400066
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800006698
  • ReraGenie IDRG-MH-25492

Builder

  • NameSEVENSTAR DEVELOPERS
  • Entity typePartnership
  • PartnersBHARAT PREMJI PUROHIT, PRATAP UTTAM PUROHIT, RAJU OMPRAKASH BANSAL, PIYUSH MORARJIBHAI SHAH

Key dates

this monthRegisteredAug 2017First promiseDec 2022Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on16 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed158 files

Current status

38%104 of 273 units booked
80.5%Work done, per cost certificate

Figures as on 21 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
COMPOSITE BUILDING WING A REHABNA18151140114
COMPOSITE BUILDING WING B SALENA25230159159

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 21 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 90%.

COMPOSITE BUILDING WING A REHAB89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
COMPOSITE BUILDING WING B SALE89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 21 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed185

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots185
Closed/Covered185
BuildingClosed/CoveredTotal
COMPOSITE BUILDING WING A REHAB9393
COMPOSITE BUILDING WING B SALE9292

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,279 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jul 2025

Approvals and building plan

Sanctioning authoritySRA
Permissible FSI11510.24
Proposed, not sanctioned5,473 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch BORIVALI WEST
Estimated costRs 52.65 cr
Cost incurredRs 42.36 cr
Work done80.46%
BuildingWingEstimatedIncurred
COMPOSITE BUILDING WING A REHABNARs 25.80 crRs 20.73 cr
COMPOSITE BUILDING WING B SALENARs 25.80 crRs 20.73 cr
-NARs 1.05 crRs 91.01 lakh

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJITENDRA PATEL
EngineerFRAMES
Chartered AccountantNEHALI DOSHI
PartnerRole in project
SEVENSTAR DEVELOPERS-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011766Dec 2022 → Dec 2023

Reason as filed by the promoterDue to covid- 19 Effect the project was not able to get completed in time. we would like to request you to further grant us extension for 12 month i.e. upto 30-12-2023.

EXT51800019030Dec 2022 → Dec 2024

Reason as filed by the promoterdue to shortage of martiral and labour not able to complete the project please grant us extension till 31/12/2024

EXT51800027281Dec 2022 → Jun 2025

Reason as filed by the promoterWe are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons- (1) The Development Control and Promotion Regulations 2034 has updated the Floor Space Index (FSI) guidelines, allowing promoters to seek additional FSI allocations. (2) In light of these updated guidelines, the promoter submitted a request to take advantage of the additional FSI provisions outlined in the new Development. Control and Promotion Regulations 2034. (3) The opportunity to access additional FSI necessitat

EA29072502232Dec 2022 → Dec 2025

Reason as filed by the promoterWe are making an application to extend the project registration with Maharashtra Real Estate Regulatory Authority. We have to revise the project timeline due to following reasons (1) The Development Control and Promotion Regulations 2034 has updated the Floor Space Index (FSI) guidelines, allowing promoters to seek additional FSI allocations. (2) In light of these updated guidelines, the promoter submitted a request to take advantage of the additional FSI provisions outlined in the new Development Control and Promotion Regulations 2034. 3) The opportunity to access additional FSI necessitated

EA20012619517Dec 2022 → Dec 2026

Reason as filed by the promoterWe, Seven Star Developers, are the developers of the project Star Plaza, bearing RERA Registration No. P51800006698, situated at C.T.S. No. 65, 66, 66/1 to 12, 67, 67/1 to 24, 68(pt), 68/1 to 6, F.P. No. 15 & 16(pt) TPS-II, of village Kanheri at Borivali (E), Mumbai.We respectfully submit that the construction work of the above-mentioned project has been fully completed in all respects in accordance with the approved plans. Upon completion of the construction, we have started the process to fulfil the compliances for application of the Occupation Certificate to the competent authority. The del

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400023Vivekanand B ShuklaSEVENSTAR DEVELOPERS04/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Oct 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed158

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 158 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1.pdf21 Jul 2026
Withdrawal Update Form 2File: form 2.pdf21 Jul 2026
Withdrawal Update Form 3File: form 3.pdf21 Jul 2026
Withdrawal Update Form 1File: FORM 1.pdf18 May 2026
Withdrawal Update Form 2File: FORM 2.pdf18 May 2026
Withdrawal Update Form 3File: FORM 3.pdf18 May 2026
Withdrawal Update Form 1File: FORM 1.pdf16 May 2026
Withdrawal Update Form 2File: FORM 2.pdf16 May 2026
Withdrawal Update Form 3File: FORM 3.pdf16 May 2026
Withdrawal Update Form 1File: form 1 (architect certificate) (1)-1.pdf31 Jan 2026
Withdrawal Update Form 2File: Frames Certificate.pdf31 Jan 2026
Withdrawal Update Form 3File: SIgned CA Certificate - Seven Stars dec 25.pdf31 Jan 2026
Withdrawal Update Form 1File: form 1.pdf4 Nov 2025
Withdrawal Update Form 2File: form 2.pdf4 Nov 2025
Withdrawal Update Form 3File: Signed CA Certificate - Seven Stars sept25.pdf4 Nov 2025
Certificates of CA (Form 3)File: Signed CA Certificate - Seven Stars mar 25-1.pdf17 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf17 Apr 2025
Declaration in FORM BFile: FORM B - STAMP PAPER AND NOTARISED.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: disclosure of inventory.pdf22 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 23-24.pdf20 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf18 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf10 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf23 Oct 2024
Certificates of CA (Form 3)File: Signed_CA Certificate - Seven Stars June '24-SIGNED.pdf26 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf24 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf22 Apr 2024
Certificates of CA (Form 3)File: Signed CA Certificate - Seven Stars mar'241.pdf22 Apr 2024
Certificates of CA (Form 3)File: CA form 3.pdf9 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf9 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf9 Mar 2024
Disclosure of sold/ booked inventoryFile: INVENTORY.pdf5 Mar 2024
Certificates of CA (Form 3)File: CA form 3 Revised signed.pdf5 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A DOI.pdf17 Feb 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank details letter.pdf17 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer form 2A 22-23.pdf31 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1.pdf27 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf27 Jan 2024
Certificates of CA (Form 3)File: CA form 3.pdf27 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: CA Form 5 21-22.pdf27 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CA Form 5 22-23.pdf27 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf4 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1.pdf10 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer form 2.pdf20 Jul 2023
Certificates of CA (Form 3)File: Signed CA Certificate june 23.pdf19 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf20 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Frame Signed Certificate_18-04-2023_1.pdf18 Apr 2023
Certificates of CA (Form 3)File: form 3.pdf18 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1.pdf13 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A.pdf12 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf9 Jan 2023
Certificates of CA (Form 3)File: FORM 3.pdf9 Jan 2023
Layout approvalFile: 1 star plaza.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_1-2.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_3-4.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_5-7.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_8-9.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_10-11.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_12-13.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_14-15.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_16-17.pdf22 Oct 2022
Layout approvalFile: 2 (2)-merged_18-end.pdf22 Oct 2022
Building plan approvalFile: IOA.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 1 star plaza.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_1-2.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_3-4.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_5-7.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_8-9.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_10-11.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_12-13.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_14-15.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_16-17.pdf22 Oct 2022
Copy of Layout Approval (in case of layout)File: 2 (2)-merged_18-end.pdf22 Oct 2022
Building Plan Approval (IOD)File: IOA.pdf22 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf22 Oct 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf13 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf12 Jul 2022
Certificates of CA (Form 3)File: CA Certificate.pdf11 Jul 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A.pdf27 Apr 2022

How this compares with Mumbai Suburban

38%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 48 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep STAR PLAZA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near borivali east6,700+ in Mumbai Suburban

2 kmSTAR PLAZACompleted 118Lapsed / revoked 72Other 178Dot size: filed unitsN

Filed coordinates, straight-line distance. 368 registered projects within 2 km.

Builder: SEVENSTAR DEVELOPERS

SEVENSTAR DEVELOPERS has 1 registration on MahaRERA, including STAR PLAZA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if STAR PLAZA is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of STAR PLAZA?

The registered promoter entity is SEVENSTAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in STAR PLAZA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against STAR PLAZA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for STAR PLAZA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at STAR PLAZA?

The professionals named in the filing: Architect: JITENDRA PATEL; Engineer: FRAMES; Chartered Accountant: NEHALI DOSHI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in STAR PLAZA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About STAR PLAZA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save STAR PLAZA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.