Home / Browse projects / Bengaluru Urban, Karnataka / SRI NANJUNDESHWARA RESIDENCY
SRI NANJUNDESHWARA RESIDENCY
By SRI NANJUNDESHWARA INFRATECH
RG-KA-99885 · RERA PRM/KA/RERA/1251/310/PR/220125/007410 · Last updated on RERA Karnataka portal: 7 Nov 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Nothing adverse is on this record. The buyer report still lays out every unit as filed and places this filing against every project registered within 2 km.
See what the report covers Free either way: .Saved.
SRI NANJUNDESHWARA RESIDENCY is a Residential/Group Housing project by SRI NANJUNDESHWARA INFRATECH in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/220125/007410 on 22 Jan 2025. Possession is promised by 31 Dec 2027.
At a glance
Project
- NameSRI NANJUNDESHWARA RESIDENCY
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560060
- Pincode560060
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/220125/007410
- ReraGenie IDRG-KA-99885
Builder
- NameSRI NANJUNDESHWARA INFRATECH
- Entity typePartnership Firm
- GSTIN29AEYFS8839K1ZM
- Authorized SignatorySHREESHA R S
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on22 Jan 2025
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed90 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SRI NANJUNDESHWARA RESIDENCY | - | - | - | 16 | 0 | 16 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 7 Nov 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
Building:
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | - |
| Foundation footing work | - |
| Upto Plinth Level | - |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | - |
| Retaining wall (All types) | - |
| RCC or MS Framed structure | - |
| Masonry Construction | - |
| Plastering inside , outside & Ceiling | - |
| Joinery: Doors, Windows, Ventilators etc | - |
| Basic work of Water supply, Sanitary and Electrification | - |
| Dadoing, Skirting, Flooring, Tiles work (All types) | - |
| Railing and Grill fixing | - |
| Electrification, Water supply and Sanitary Finishing | - |
| Painting | - |
| Fire prevention and fire fighting fitting and fixture with network | Not applicable |
| Weather Proof work(tile,concrete) | Not applicable |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | Not applicable |
| Internal and External work including landscapes as per sanctioned drawings | Not applicable |
Progress on shared amenities40
As on 7 Nov 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | - |
| Sewage and Drainage System | Yes | - |
| Water conservation/rain water harvesting/recharge of ground water | Yes | - |
| Energy management | Yes | - |
| Fire protection and fire safety requirements | No | Not applicable |
| Solid waste management and disposal | No | Not applicable |
| Emergency Evacuation services | No | Not applicable |
| Internal Roads & Footpaths | No | Not applicable |
| Electricity supply transformer and substation | Yes | - |
| Storm water drains | Yes | - |
| Use of renewable energy | Yes | - |
| Sewage Treatment Plant (STP) | No | Not applicable |
| Parks & Tree planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Electricity | Yes | - |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | No | Not applicable |
| Club House | No | Not applicable |
| Community Hall | No | Not applicable |
| Outdoor Sports facility | No | Not applicable |
| Indoor Sports facility | No | Not applicable |
| Swimming Pool | No | Not applicable |
| Gym | No | Not applicable |
| Parks | No | Not applicable |
| Power Backup | Yes | - |
| Piped Gas | Yes | - |
| Water and Sanitation | Yes | - |
| Air Conditioning | No | Not applicable |
| Staircases | Yes | - |
| Lifts | Yes | - |
| Corridor/Lobbies | Yes | - |
| Fire escapes | No | Not applicable |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | - |
| Basement | Yes | - |
| Terrace | Yes | - |
| Outer Wall | Yes | - |
| Open parking areas | No | Not applicable |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | No | Not applicable |
| Common storage spaces | No | Not applicable |
Land and ownership1
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SRI NANJUNDESHWARA INFRATECH | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 5.45 cr | - |
| On-site expenditure-Salaries of workers | Rs 55.00 lakh | - |
| On-site expenditure-Site Overhead | Rs 50.60 lakh | - |
| On-site expenditure-Consultants Fees | Rs 22.00 lakh | - |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SUNIL BG |
| Engineer | SOURABH D C |
| Chartered Accountant | Jagarlamudi Dinesh |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed90
As listed on the registration, under the names the promoter filed them with; the newest 80 of 90 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/220125/007410 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA - QU JUNE 26 - SRI NANJUNDESHWARA RESIDENCY.pdf | 7 Nov 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - QU JUNE 26 - SRI NANJUNDESHWARA RESIDENCY.pdf | 7 Nov 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - QU JUNE 26 - SRI NANJUNDESHWARA RESIDENCY.pdf | 7 Nov 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA - QU DEC 25 - SRI NANJUNDESHWARA RESIDENCY.pdf | 21 Sep 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - QU DEC 25 - SRI NANJUNDESHWARA RESIDENCY.pdf | 21 Sep 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - QU DEC 25 - SRI NANJUNDESHWARA RESIDENCY.pdf | 21 Sep 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: FORM 4 CA - QU MARCH 26 - SRI NANJUNDESHWARA RESIDENCY.pdf | 21 Sep 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 ARCH - QU MARCH 26 - SRI NANJUNDESHWARA RESIDENCY.pdf | 21 Sep 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: FORM 6 ENGR - QU MARCH 26 - SRI NANJUNDESHWARA RESIDENCY.pdf | 21 Sep 2026 |
| BANK AFFIDAVITFile: Bank Affidavit.pdf | 9 Jan 2025 |
| SOURCES OF FUNDSFile: Source of funds.pdf | 9 Jan 2025 |
| ARCHITECTS LICENSEFile: Arc license.pdf | 9 Jan 2025 |
| ARCHITECTS CERTIFICATE FORM 2File: Form 2 Arc.pdf | 9 Jan 2025 |
| ENGINEER KYCFile: Engineer adhar.pdf | 9 Jan 2025 |
| ENGINEER CERTIFICATEFile: Engineer certificate.pdf | 9 Jan 2025 |
| ENGINEER LICENSEFile: Engineer licensce.pdf | 9 Jan 2025 |
| COMMENCEMENT CERTIFICATEFile: Commencement certificate.pdf | 9 Jan 2025 |
| APPROVAL ALL TYPE OF PLANFile: PLAN NANJU.pdf | 9 Jan 2025 |
| CHARTERED ACCOUNTANT CERTIFICATEFile: CA certificate form 1.pdf | 9 Jan 2025 |
| SURVEY SKETCHFile: SITE SURVEY.pdf | 9 Jan 2025 |
| MASTER PLANFile: Master plan kengeri.pdf | 9 Jan 2025 |
| VILLAGE MAPFile: KENGERI.png | 9 Jan 2025 |
| CHARTERED ACCOUNTANT MEMBERSHIP CERTIFICATEQFile: CA membership certificate.jpeg | 10 Dec 2024 |
| PROFORMA OF AGREEMENT OF SALEFile: Agreement of Sale Proforma.pdf | 10 Dec 2024 |
| MODEL FORM OF ALLOTMENT LETTERFile: MODEL FORM OF ALLOTMENT LETTER.pdf | 10 Dec 2024 |
| BWSSB NOCFile: BWSSB NOC.pdf | 10 Dec 2024 |
| COMMENCEMENT CERTIFICATEFile: Commencement certificate.pdf | 10 Dec 2024 |
| ECFile: EC 1.pdf | 10 Dec 2024 |
| ECFile: EC.pdf | 10 Dec 2024 |
| ENGINEER CERTIFICATEFile: Engineer Certificate - B V Sadananda Reddy P1.pdf | 10 Dec 2024 |
| RTCFile: RTC.jpeg | 10 Dec 2024 |
| SOURCES OF FUNDFile: Source of funds.pdf | 10 Dec 2024 |
| STRUCURAL SAFETYFile: Structural Safety.jpg | 10 Dec 2024 |
| Financials 2024-25 with UDIN Profit and loss account, balance sheet, and ITRFile: Financials 2024-25 with UDIN.pdf | 23 Oct 2024 |
| Advocates Search ReportFile: Advocates Search Report.pdf | 23 Oct 2024 |
| ECFile: EC.pdf | 23 Oct 2024 |
| BWSSB NOCFile: BWSSB NOC.pdf | 23 Oct 2024 |
| BWSSB Fee ReceiptFile: BWSSB Fee receipt.pdf | 23 Oct 2024 |
| BESCOM Fee ReceiptFile: BESCOM fee receipt.jpeg | 23 Oct 2024 |
| CA Self-attested membership copyFile: Dinesh J - CA Membership Copy.jpg | 23 Oct 2024 |
| Updated Form-BFile: Form - B - Notarized.pdf | 23 Oct 2024 |
| Updated Non-LitigationFile: Non-Litigation - SRI.pdf | 23 Oct 2024 |
| Registration CertificateFile: Company Registration.pdf | - |
| GST Certificate | - |
| Partnership DeedFile: Partnership Deed - Sri Nanjundeshwara Infratech.pdf | - |
| Partner Details | - |
| Partner Details | - |
| Certificate issued by CA Form 1File: CA certificate form 1.pdf | - |
| Certificate issued by Architect Form 2File: Form 2 Arc.pdf | - |
| Certificate issued by Engineer Form 3File: Engineer certificate.pdf | - |
| Project Chartered Accountant | - |
| Project Engineer | - |
| Project Architect | - |
| AffidavitFile: Affidavit Cum Declaration - Notarized.pdf | - |
| Balance Sheet 2022 - 2023File: SNI_Financials_2023-24.pdf | - |
| Audited Profit and Loss Statement 2022 - 2023File: SNI_Financials_2023-24.pdf | - |
| Income Tax Return Acknowledgement 2022 - 2023File: SNI_ITR-V-AY-2024-25 (1).pdf | - |
| Building Licence - Mylsandra | - |
| Electricity Permission Copy | - |
| Water Permission Letter | - |
| Approved Plan - Mylasandra | - |
| Approved Plan - Mylasandra | - |
| Approved Plan - Mylasandra | - |
| Approved Plan - Mylasandra | - |
| Approved Plan - Mylasandra | - |
| Approved Plan - Mylasandra | - |
| Declaration for Area Development | - |
| DC Conversion Copy | - |
| DC Conversion Copy | - |
| Declaration for Brochure | - |
| Form - B - Notarized | - |
| Affidavit - Notarized | - |
| Electricity Permission Copy | - |
| BWSSB NOC with Challen Receipt | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
| Unnamed document | - |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Free monthly report: Bengaluru on RERA Karnataka, month by month. What registered each month, the flat types and carpet areas being built, the taluks and the completion pipeline, from these same filings.
Buyer report
Built from this project's RERA Karnataka filing, in plain language.
- Red flags and clear checks, the possession story and who you are dealing with
- Every unit as filed, tower by tower: carpet area, undivided share of the land and parking, with the sizes placed against the other projects of the taluk
- Joined against every project registered within 2 km, which the register never shows together
- What to check before you book, drawn from this filing
Not included: the filed documents themselves (the report lists which are on file and does not read them) and a project watch.
Keep SRI NANJUNDESHWARA RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 12 registered projects within 2 km.
JITO RANKA NAGAR
Essence Realty LLP
Provident Equinox 4
Provident Housing Limited
Provident Equinox 6
Provident Housing Limited
KOMMAGHATTA NPKL PHASE-1
Bangalore Development Authority
VBHC Haven of Joy
VBHC Mumbai Value Homes Pvt Ltd
Provident Equinox 5
Provident Housing Limited
See every Bengaluru Urban project, with the district possession charts
Builder: SRI NANJUNDESHWARA INFRATECH
SRI NANJUNDESHWARA INFRATECH has 1 registration on RERA Karnataka, including SRI NANJUNDESHWARA RESIDENCY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if SRI NANJUNDESHWARA RESIDENCY is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of SRI NANJUNDESHWARA RESIDENCY?
The registered promoter entity is SRI NANJUNDESHWARA INFRATECH, a partnership firm as per the filing. Its GSTIN 29AEYFS8839K1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in SRI NANJUNDESHWARA RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at SRI NANJUNDESHWARA RESIDENCY?
The professionals named in the filing: Architect: SUNIL BG; Engineer: SOURABH D C; Chartered Accountant: Jagarlamudi Dinesh. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SRI NANJUNDESHWARA RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.