ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SPRING GARDENS PHASE II

Registration lapsed No litigation declared Residential / Group Housing project

SPRING GARDENS PHASE II

By Achalare Realtors Private Limited

RG-MH-78001 · RERA P52100047086 · Last updated on MahaRERA portal: 1 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 20.00 crore secured on the land, in favour of Achalare Realtors Pvt Ltd

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 94%
14 of 166Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 96 documents Report an error

SPRING GARDENS PHASE II is a Residential / Group Housing project by Achalare Realtors Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100047086 on 3 Oct 2022. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 152 of the 166 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameSPRING GARDENS PHASE II
  • TypeResidential / Group Housing
  • Location
    • DEHU ALANDI ROAD
    • BORHADEWADI
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100047086
  • ReraGenie IDRG-MH-78001

Builder

  • NameAchalare Realtors Private Limited
  • Entity typeCompany
  • Managing DirectorRajendra Jindatt Achalare
  • Other registrations4 more →
  • Completed3 of 5
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

10 months past promisethis monthRegisteredOct 2022First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Oct 2022
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed96 files

Current status

92%152 of 166 units booked

Figures as on 1 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B BUILDINGNA17141660166

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 1 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 94%.

B BUILDING: 83% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises76%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks87%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.94%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.60%

Progress on shared amenities15

As on 1 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes35%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes35%
Street LightingYes10%
Community BuildingsYes85%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes35%
Water conservation /Rain water harvestingYes30%
Energy managemcntYes25%
Fire protection and fire safety requirementsYes45%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed166

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots166
Closed/Covered166

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,286 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofAchalare Realtors Pvt Ltd
Secured amountRs 20.00 crore
CERSAI search filedYes
Declared on9 Jul 2025
LandownerVillageDistrict
NIVRUTTI TUKARAM BORATE AND OTHERSPimpri Chinchawad (M Corp.)Pune
MANGESH SAKHARAM BORATE AND OTHERSPimpri Chinchawad (M Corp.)Pune
PANDIT GENUBAHU BORATE AND OTHERSPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPCMC
Permissible FSI15591.28
Proposed, not sanctioned15,591 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSB ROAD PUNE

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIKAS ACHALKAR
EngineerMILIND DEO
EngineerPRADIP G GURAV
EngineerMILIND D DEO
EngineerAMARSINGH PATIL SITE ENGINEER
Chartered AccountantGANESH SUNIL MANDLECHA
Chartered AccountantV N LAHOTI
PartnerRole in project
Achalare Realtors Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017211Dec 2024 → Dec 2025

Reason as filed by the promoterRegistration No.P52100047086

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 22 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed96

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: from-1.pdf1 Jan 2026
Form 2File: from-b.pdf1 Jan 2026
Form 3File: from-3.pdf1 Jan 2026
Disclosure of Sold and Booked InventoryFile: 4.pdf1 Jan 2026
OthersFile: from-5.pdf1 Jan 2026
Form 1File: form 1.pdf27 Oct 2025
Form 2File: form 2.pdf27 Oct 2025
Form 3File: form 3.pdf27 Oct 2025
Disclosure of Sold and Booked InventoryFile: discloser.pdf27 Oct 2025
OthersFile: society registration Certificate.pdf27 Oct 2025
Form 1File: B form 1.pdf30 Jul 2025
Form 2File: form 2.pdf30 Jul 2025
Form 3File: II form 3_compressed.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Discloser Sprng PH II.pdf30 Jul 2025
Form 1File: B form 1.pdf30 Jul 2025
Form 2File: form 2.pdf30 Jul 2025
Form 3File: II form 3_compressed.pdf30 Jul 2025
Disclosure of Sold and Booked InventoryFile: Discloser Sprng PH II.pdf30 Jul 2025
Form 2A (FY 2024-2025)File: Spring Gardens Ph II 2A.pdf14 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2024 -25 Spring Gardens PH II.pdf12 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 sprng ph II.pdf28 Apr 2025
Disclosure of sold/ booked inventoryFile: discloser sprng ph II till 31 march 25.pdf25 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1 Spring Garden PH II.pdf5 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2 Sprng II.pdf5 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SprngII.pdf24 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sprng II_compressed (1).pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold B Bldg compressed.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sprng phII_compressed.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 PH 2 31 12 24.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sprng II.pdf9 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Architect Certificate 30 09 2024.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 sprng 2.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer Certificate form 2.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: annual report 2023 24.pdf17 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure B Building 11 10 2024.pdf14 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 Architect Certificate spring Gardens ph2.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: discloser 3 7 24 Spring Gardens B.pdf4 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: spring gardens B RERA Form2 Engineer certificates.pdf3 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 CA Certificate 20 04 2024.pdf25 May 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Application for Reservation of Name for Proposed Co Op Hsg Soc.pdf16 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: GetUserDocumentFileContent.pdf7 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf3 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A spring gardens 2.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: B building disclosure.pdf3 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Spring Gardens PH 2_compressed.pdf2 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sprng 2 7 11 23.pdf6 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sprng 2 10 11 23.pdf6 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf2 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf2 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure B Bldg.pdf2 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 sprng ph 2 dt 30 9 23.pdf25 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 3 spring gardens ph 2.pdf16 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: RERA Spring Gardens B.pdf6 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf12 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 spring gardens ph 2.pdf9 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Spring Gardens ph II dt 30 06 2023.pdf8 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 Spring Gardens II dt 10 04 2023.pdf10 Jul 2023
Disclosure of sold/ booked inventoryFile: B bldg Spring Gardens Dsclr.pdf5 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SPRING GARDENS PH 2.pdf30 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 1 Engineers Certificate on Quality Assurance.pdf21 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Spring Gardens ph2 22 23.pdf19 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 sprng ph 2.pdf17 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure Spring Garden Ph II.pdf21 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate spring gardens ph 2 dtd 30 01 2023.pdf21 Feb 2023
Disclosure of sold/ booked inventoryFile: dISCCLOSURE PHASE 2.pdf21 Jan 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Modification 27 9 2022.pdf27 Sep 2022
Deviation Report with respect to model copy of AgreementFile: 1.pdf27 Sep 2022
Deviation Report with respect to model copy of AgreementFile: 2.pdf27 Sep 2022
Proforma of Allotment letterFile: Allotment Letter Phase ii.pdf20 Sep 2022
Details of encumbrances concerned to LegalFile: Self Declaration regarding encumbrances.pdf19 Sep 2022
Other - LegalFile: Self Declaration regarding encumbrances.pdf19 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Spring Gardens.pdf6 Sep 2022
PAN CardFile: Pancard.PDF26 Aug 2022
Other - FinanceFile: ENCUMBRANCE.PDF26 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FROM A BANK DECLRATION.pdf23 Aug 2022
Deviation Report with respect to Allotment letterFile: Deviation Modification sheet in Allotment Letter.pdf23 Aug 2022
Layout approvalFile: LAYOUT.pdf22 Aug 2022
Building plan approvalFile: B TYPE 1.pdf22 Aug 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SPRING GARDENS PHASE - Ip52100026121MOSHI DEHU RASTA143CompletedJun 2024Jan 1970
Shreephal HomesPlot No E2-E3 S.no. 17-1-2 Ajinkya Park Pancard Road Baner Pune 4520CompletedDec 2016Late, Jan 2017
ApricotS.No.17-1-2 Ajinkya Park Pan card Road Baner Pune -457CompletedSep 2015Late, Mar 2016

How this compares with Pune

92%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SPRING GARDENS PHASE II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BORHADEWADI13,700+ in Pune

2 kmSPRING GARDENS PHASE IICompleted 45Lapsed / revoked 24Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 96 registered projects within 2 km.

Builder: Achalare Realtors Private Limited

Achalare Realtors Private Limited has 5 registrations on MahaRERA, including OLYMPIA and Amber. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SPRING GARDENS PHASE II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SPRING GARDENS PHASE II is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SPRING GARDENS PHASE II?

The registered promoter entity is Achalare Realtors Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SPRING GARDENS PHASE II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SPRING GARDENS PHASE II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SPRING GARDENS PHASE II?

The professionals named in the filing: Architect: VIKAS ACHALKAR; Engineer: MILIND DEO; Engineer: PRADIP G GURAV; Engineer: MILIND D DEO; Engineer: AMARSINGH PATIL SITE ENGINEER; Chartered Accountant: GANESH SUNIL MANDLECHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SPRING GARDENS PHASE II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SPRING GARDENS PHASE II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SPRING GARDENS PHASE II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.