Home / Browse projects / Pune, Maharashtra / SP RESIDENCY PHASE III

Registration lapsed No litigation declared Residential / Group Housing project

SP RESIDENCY PHASE III

By Supra Warehousing Private Limited

RG-MH-43642 · RERA P52100015190 · Last updated on MahaRERA portal: 20 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 28 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2024Possession promised28 months past this date
5 of 11Construction stages donefurthest along: Staircases, 95%
0 of 112Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 109 documents Report an error

SP RESIDENCY PHASE III is a Residential / Group Housing project by Supra Warehousing Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100015190 on 7 Feb 2018. Possession was promised by 15 Jun 2024 and is now 28 months past that date. The completion date has moved by 24 months from the original filing. 112 of the 112 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSP RESIDENCY PHASE III
  • TypeResidential / Group Housing
  • Location
    • Pune Saswad Road
    • Hadapsar
    • Fursungi
    • Haveli
    • Pune
    • 412308
  • Pincode412308
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100015190
  • ReraGenie IDRG-MH-43642

Builder

  • NameSupra Warehousing Private Limited
  • Entity typeCompany
  • CINU45100MH2013PTC248193
  • DirectorSubodh Pagnis
  • Declared earlier projects1 →

Key dates

28 months past promisethis monthRegisteredFeb 2018First promiseJun 2022Revised toJun 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Feb 2018
  • Promised completion15 Jun 2024
  • Revised completionRevised to 15 Jun 2024 (originally 15 Jun 2022)
  • Buildings1 building record
  • Documents filed109 files

Current status

100%112 of 112 units booked

Figures as on 20 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1 - Wing 1 and Wing 2NA20141120112

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 95%.

B1 - Wing 1 and Wing 2: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.85%

Progress on shared amenities15

As on 20 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes65%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes95%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed146

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots146
Closed/Covered138
Open Space8

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area29,196 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority
Permissible FSI10127.85
Proposed, not sanctioned10,128 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAryan Centre, Pune Solapur Highway, Opposite Vaibhav Theatre, Hadapsar, Pune- 411408, Maharashtra, I

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectFourth Dimension Architects Pvt. Ltd
EngineerR R Jain Consultants Pvt Ltd
Chartered AccountantB R Nagda & Co
Chartered AccountantHarshad Doshi & Co
PartnerRole in project
Supra Warehousing Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012031Jun 2022 → Jun 2023

Reason as filed by the promoterWe are hereby submitting following documents for consideration of the Authority: (a) Commencement Certificate issued by PMRDA is enclosed under Tab No. 1 i.e., "Copy of the permission/ approval of competent authority". (b) Approval Letter along with project approved plans is enclosed under Tab No. 2 i.e., i.e., "Copy of the permission/ approval of competent authority". (c) 'Form E' Extension Application along with 'Annexure A' (State of existing development works), Annexure 'B' (Explanatory Note & Reasons for delay) and Annexure 'C' (Existing RERA Registration Certificate). The said document i

EXT52100016795Jun 2022 → Jun 2024

Reason as filed by the promoterDear Sir/ Madam, Please find enclosed herewith the MahaRERA order (Refer Tab No.2, Resolution of the Association of Allottees) along with our application for extension in "Form E" and the Annexures mentioned therein for your consideration. Request you to consider our application and grant the extended RERA Registration Certificate.

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000259149Amol Sambhaji PhadkeSUPRA WAREHOUSING PRIVATE LIMITED THROUGH DIRECTOR SUNITA KHANNA AND OTHERS19/07/2023
CC005000000259254KOMAL KUMBHAREPHENOMENON DEVELOPERS PVT LTD08/08/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 2 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jan 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jan 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jun 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed109

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1-(Q2-24-25)-Physical Progress Report.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Form 1- Sept 2024.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1-(Q3-24-25)-Physical Progress Report.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Form 1- Dec 2024.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1- Form 2- Sept 2024.pdf20 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1- Form 2- Dec 2024.pdf20 Feb 2025
Certificates of CA (Form 3)File: B1- CA Certificate- Mar 2024 (reduced).pdf20 Jan 2025
Certificates of CA (Form 3)File: B1- CA Certificate- June 2024 (reduced).pdf20 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: B1- Form 5- FY 23-24.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Architect Certificate- June 2024.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Physical Progress Report- June 2024.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1- Engineer's Certificate- June 2024.pdf19 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Physical Progress Report- Mar 2024.pdf6 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1-Architect Certificate- Mar 2024.pdf6 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1- Engineers Certificate- Mar 2024.pdf6 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Form 1- Dec 2023.pdf12 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- PPR- Dec 2023.pdf12 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: B1- Form 2- Dec 2023.pdf12 Mar 2024
Disclosure of sold/ booked inventoryFile: Supra- Inventory Report- Nov'23_signed.pdf13 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency- Physical Report- Sept 2023.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Physical Report- Jun 2023.pdf17 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Form 1-Architect Certificate- June 2023.pdf17 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Supra- Form 2- Engineer Certificate- June 2023.pdf17 Oct 2023
Certificates of CA (Form 3)File: Supra- Form 3- June 2023 (reduced).pdf17 Oct 2023
Certificates of CA (Form 3)File: Supra- No Withdrawals- Sept 2023.pdf17 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: SP Residency- Form 5 (FY 22-23).pdf30 Sep 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Supra- Form 2A Declaration_signed.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Supra- Form 2A Declaration_signed.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Supra- Form 2A Declaration_signed.pdf10 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Supra- Form 2A Declaration_signed.pdf10 Jul 2023
Certificates of CA (Form 3)File: Supra- Form 3- Sept 2022-signed.pdf10 Jul 2023
Certificates of CA (Form 3)File: Supra- Form 3- Mar 2023-signed.pdf10 Jul 2023
Certificates of CA (Form 3)File: No Withdrawal Declaration- June 2022.pdf27 Jun 2023
Certificates of CA (Form 3)File: No Withdrawal Declaration- Dec 2022.pdf27 Jun 2023
Commencement Certificates / NA Order for plotted developmentFile: CC- 2019.pdf14 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Form 1- Sept 2022.pdf30 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Form 1- Dec 2022.pdf30 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Physical Report- Dec 2022.pdf30 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Form 1- Mar 23.pdf30 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Supra- Physical Report- Mar 2023.pdf30 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Supra- Form 2- Sept 2022.pdf30 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Supra- Form 2- Sept 2022.pdf30 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Supra- Form 2- Dec 2022.pdf30 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Supra- Form 2- Mar 23.pdf30 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency- Physical Report- Sept 2022.pdf13 Oct 2022
Certificates of CA (Form 3)File: Supra- Form-3- Q4 FY 21-22 (reduced size).pdf12 Oct 2022
Certificates of CA (Form 3)File: Supra - Self Declaration for CA Certificate.pdf30 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Supra- Form-5 - FY 21-22.pdf30 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency- Physical Report- June 2022_signed.pdf26 Jul 2022
CERSAI detailsFile: SP Residency, B1- CERSAI Report.pdf16 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: PDPL-Form 5-SP Residency Phase III.pdf16 Jun 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Architect Certificate- Mar 2022.pdf14 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency- Physical Report- Mar 2022.pdf14 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP Residency- Form 2- Mar 22 (reduced size).pdf14 Apr 2022
Declaration about Commencement CertificateFile: SP Residency- Declaration under CC.pdf11 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- SP Residency- Dec 21.pdf11 Jan 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- SP Residency- Dec 21.pdf11 Jan 2022
Certificates of CA (Form 3)File: Form 3- SP Residency- Dec 21.pdf11 Jan 2022
Certificates of CA (Form 3)File: SP Residency- Financial Report- Dec 2021.pdf11 Jan 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency- Physical Report- Dec 2021.pdf7 Jan 2022
Certificates of CA (Form 5)File: B1- Financial Report- June 2021.pdf21 Dec 2021
Details of encumbrancesFile: SP Residency, B1- CERSAI Report.pdf16 Nov 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Physical Report- June 2021.pdf29 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: B1- Physical Report- Sept 2021.pdf29 Oct 2021
Certificates of CA (Form 3)File: B1- Financial Report- Sept 2021.pdf29 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency_Architect Certificate_Form 1_Sept 2021.pdf15 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP Residency_Engineer’s Certificate_Form 2_Sept 2021.pdf15 Oct 2021
Certificates of CA (Form 3)File: SP Residency_CA Certificate_Form 3_Sept 2021.pdf15 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Supra_Form 5_FY 20-21.pdf30 Sep 2021
Disclosure of sold/ booked inventoryFile: Supra- Disclosure of Sold Inventory_30th June 2021.pdf2 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SP Residency- Form 1- June 2021.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SP Residency- Form 2- June 2021.pdf14 Aug 2021
Certificates of CA (Form 3)File: SP Residency- Form 3- June 2021.pdf14 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Supra_Status of Society Formation_SP Residency SIGNED.pdf23 Jul 2021
Proforma of Allotment letterFile: SWPL RERA Agreement for sale PDF.pdf11 Jan 2021
Copy of the legal title reportFile: Title Report-PDPL-14-01-2019.pdf2 Nov 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SP Residency Phase III- Form 5- FY 2019-20.pdf30 Sep 2020
Declaration in FORM BFile: Form B Supra.pdf24 Sep 2020

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
SP RESIDENCY PHASE IINear Satyapuram society Pune Saswad road Phursungi Pune-412308.129CompletedFeb 2015Late, Jan 2016

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 24 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SP RESIDENCY PHASE III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Hadapsar13,700+ in Pune

2 kmSP RESIDENCY PHASE IIICompleted 51Lapsed / revoked 21Other 33Dot size: filed unitsN

Filed coordinates, straight-line distance. 105 registered projects within 2 km.

Builder: Supra Warehousing Private Limited

Supra Warehousing Private Limited has 1 registration on MahaRERA, including SP RESIDENCY PHASE III. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SP RESIDENCY PHASE III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SP RESIDENCY PHASE III is delayed beyond 15 Jun 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SP RESIDENCY PHASE III?

The registered promoter entity is Supra Warehousing Private Limited, a company as per the filing. Its CIN U45100MH2013PTC248193 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SP RESIDENCY PHASE III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SP RESIDENCY PHASE III?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SP RESIDENCY PHASE III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SP RESIDENCY PHASE III?

The professionals named in the filing: Architect: Fourth Dimension Architects Pvt. Ltd; Engineer: R R Jain Consultants Pvt Ltd; Chartered Accountant: B R Nagda & Co; Chartered Accountant: Harshad Doshi & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SP RESIDENCY PHASE III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SP RESIDENCY PHASE III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SP RESIDENCY PHASE III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.