ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Rural, Karnataka / Sowparnika Ashiyana Phase II

Registration approved No litigation declared Residential/Group Housing project

Sowparnika Ashiyana Phase II

By SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED

RG-KA-92433 · RERA PRM/KA/RERA/1250/304/PR/201215/003748 · Last updated on RERA Karnataka portal: 13 Jan 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2025Possession promisedno revision filed
18 of 18Construction stages doneevery applicable stage filed complete
3 of 422Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 100 documents Report an error

Sowparnika Ashiyana Phase II is a Residential/Group Housing project by SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/201215/003748 on 15 Dec 2020. Possession is promised by 31 Dec 2025. 419 of the 422 units on this registration are recorded sold or booked, and 18 of 18 construction stages are filed complete.

At a glance

Project

  • NameSowparnika Ashiyana Phase II
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1250/304/PR/201215/003748
  • ReraGenie IDRG-KA-92433

Builder

  • NameSOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • Authorized SignatoryMEENAKSHI RAMJI
  • OthersV SREENIVAS
  • Other registrations9 more →
  • Declared earlier projects8 →

Key dates

this monthRegisteredDec 2020PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Dec 2020
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed100 files

Current status

99%419 of 422 units booked
98.0%Of the estimated cost spent so far

Figures as on 13 Jan 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK B,D & E---4220422

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 13 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 18 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Painting100%
Elevation work100%
Internal and External work including landscapes as per santioned drawings100%

Progress on shared amenities41

As on 13 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes100%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes100%
Street LightingYes100%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes100%
Fire protection and fire safety requirementsYes100%
Education/Health/Other public amenitiesYes0%
Electricity supply transformer and substationYes100%
Emergency Evacuation servicesNoNot applicable
Storm water drainsYes100%
Use of renewable energyYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes100%
LiftsYes100%
Staircases and Lift lobbies, corridor,lobbies, corridorYes100%
Fire escapesNoNot applicable
Common entrance and exit for the building / common portico/foyer/verandahYes100%
BasementNoNot applicable
TerraceYes100%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffYes100%
Water conservation and renewable energyYes100%

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area17,705 sq m
Named landowners1
LandownerVillageDistrict
S R SHIVA KUMAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 85.50 cr
Cost incurredRs 83.80 cr
Spent of the estimate98.01%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 42.72 crRs 51.04 cr
On-site expenditure-Site OverheadRs 33.65 crRs 25.17 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 9.13 crRs 7.58 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKOWNIAN ZAHARA
EngineerVAIBHAV KUMAR J G

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed100

As listed on the registration, under the names the promoter filed them with; the newest 80 of 100 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/201215/003748 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Ashiyana II.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5 Architect Certificate QU Ashiyana Phase II Q3 compressed.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6 Ashiyana Phase II Eng Certificate QU Q3.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
Official Memorandum No 151-1992-93 - GirijammaFile: 1 Official Memorandum No 151-1992-93 - Girijamma.pdf7 Dec 2020
Saguvali Chit - GirijammaFile: 2 Saguvali Chit - Girijamma.pdf7 Dec 2020
Conversion Order 57-2File: 3 Conversion Order 57-2.pdf7 Dec 2020
Consolidated KathaFile: 4 Consolidated Katha Samethanahalli.pdf7 Dec 2020
RTC from 1974-75 to 2001-02File: 5 RTC from 1974-75 to 2001-02.pdf7 Dec 2020
EC for all the Survey Nos from 01-04-2019 to 05-11-2020File: 6 EC for all the Survey Nos from 01-04-2019 to 05-11-2020.pdf7 Dec 2020
Certificate of IncorporationFile: COI - Revised.pdf3 Dec 2020
Title Documents for Sy. No. 57-1& Sy. No. 277File: 2. Title Documents for Sy. No. 57-1& Sy. No. 277.pdf3 Dec 2020
RTC and Katha for Sy. No. 57-1& Sy. No. 277File: 3. RTC and Katha for Sy. No. 57-1& Sy. No. 277.pdf3 Dec 2020
Ongoing Project DetailsFile: Ongoing Projects.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 1 of 7 - Site PlanFile: Sowparnika Ashiyana Phase II - 1 of 7 - Site Plan.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 2 of 7 - Basement PlanFile: Sowparnika Ashiyana Phase II - 2 of 7 - Basement Plan.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 3 of 7 - Stilt Floor PlanFile: Sowparnika Ashiyana Phase II - 3 of 7 - Stilt Floor Plan.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 4 of 7 - Ground Floor PlanFile: Sowparnika Ashiyana Phase II - 4 of 7 - Ground Floor Plan.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 5 of 7 - Typical Floor - 1 to 7 FloorsFile: Sowparnika Ashiyana Phase II - 5 of 7 - Typical Floor - 1 to 7 Floors.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 6 of 7 - Terrace Floor PlanFile: Sowparnika Ashiyana Phase II - 6 of 7 - Terrace Floor Plan.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - 7 of 7 - Elevation PlanFile: Sowparnika Ashiyana Phase II - 7 of 7 - Elevation Plan.pdf3 Dec 2020
Sowparnika Ashiyana Phase II - Developement PlanFile: Sowparnika Ashiyana Phase II - Developement Plan.pdf3 Dec 2020
Registration Certificate - Ashiyana Phase IFile: Registration Certificate - Ashiyana Phase I.pdf3 Dec 2020
CertificateFile: COI - Revised.pdf-
Sowparnika Ashiyana Phase II - Commencement Certificate-Minimised-
Sowparnika Ashiyana Phase II - 1 of 7 - Site Plan-
Sowparnika Ashiyana Phase II - Developement Plan-
Sowparnika Ashiyana Phase II - Draft Sale Deed-
Sowparnika Ashiyana Phase II - Draft Sale Agreement-
Sowparnika Ashiyana Phase II - Sale Deed-
Sowparnika Ashiyana Phase II - 7 of 7 - Elevation Plan-
Sowparnika Ashiyana Phase II - Developement Plan-
Sowparnika Ashiyana Phase II - Draft Allotment Letter-
Sowparnika Ashiyana Phase II - Brochure-
Sowparnika Ashiyana Phase II - Project Specifications-
Sowparnika Ashiyana Phase II - EC-
Sowparnika Ashiyana Phase II - Form B - Affidavit Cum Declaration-
Sowparnika Ashiyana Phase II - JD Affidavit Cum Declaration-
Sowparnika Ashiyana Phase II - RTC & Khata-
Sowparnika Ashiyana Phase II - JDA and GPA-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Sowparnika Ashiyana Phase II - Relinquishment Deed-
Sowparnika Ashiyana Phase II - NOC - Fire Department-compressed-
Sowparnika Ashiyana Phase II - NOC - AAI-
Sowparnika Ashiyana Phase II - NOC - BESCOM-
Sowparnika Ashiyana Phase II - NOC - Water-Minimised-
Sowparnika Ashiyana Phase II - NOC - KSPCB-
Sowparnika Ashiyana Phase II - NOC - MOEF-
Sowparnika Ashiyana Phase II - NOC - BSNL-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Sowparnika Ashiyana Phase II - 7 of 7 - Elevation Plan-
Sowparnika Ashiyana Phase II - 1 of 7 - Site Plan-
Sowparnika Ashiyana Phase II - 5 of 7 - Typical Floor - 1 to 7 Floors-
Sowparnika Ashiyana Phase II - Combined Conversion Orders - Compressed-
Sowparnika Ashiyana Phase II - Legal Report-
Balance Sheet 2019 - 2020File: Balance Sheet - 19-20.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet - 18-19.pdf-
Balance Sheet 2017 - 2018File: Balance Sheet - 17-18.pdf-
Audited Profit and Loss Statement 2019 - 2020File: Audited Profit and Loss Statement - 19-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P & L Account - 18-19.pdf-
Audited Profit and Loss Statement 2017 - 2018File: P & L Account - 17-18.pdf-
Director's Report 2019 - 2020File: Director's Report - 19-20.pdf-
Director's Report 2018 - 2019File: Directors Report - 18-19 - Compressed.pdf-
Director's Report 2017 - 2018File: Directors Report - 17-18 - Compressed.pdf-

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 not delivered by the promised date
ProjectLocationStatusPromisedDelivered
SOWPARNIKA ASHIYANA PHASE I-OngoingJun 2025Not delivered
SOWPARNIKA COLUMNS-OngoingDec 2022Not delivered
SOWPARNIKA PRANATHI-OngoingSep 2022Not delivered
SOWPARNIKA PRAGATI-OngoingJun 2022Not delivered
SOWPARNIKA INDRAPRASTHA-OngoingMar 2022Not delivered
SOWPARNIKA FLAMENCO-OngoingDec 2021Not delivered
SOWPARNIKA UNNATHI-OngoingNov 2021Not delivered
SOWPARNIKA THE LANDMARK-OngoingSep 2021Not delivered

How this compares with Bengaluru Rural

99%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep Sowparnika Ashiyana Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

2 kmSowparnika Ashiyana PhasOther 22Dot size: filed unitsN

Filed coordinates, straight-line distance. 22 registered projects within 2 km.

Builder: SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED

SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED has 10 registrations on RERA Karnataka, including SOWPARNIKA INDRAPRASTHA and Sowparnika Ashiyana Phase I. Its filings declare 8 earlier projects, none of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if Sowparnika Ashiyana Phase II is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Sowparnika Ashiyana Phase II?

The registered promoter entity is SOWPARNIKA PROJECTS AND INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other RERA Karnataka registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Sowparnika Ashiyana Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Sowparnika Ashiyana Phase II?

The professionals named in the filing: Architect: KOWNIAN ZAHARA; Engineer: VAIBHAV KUMAR J G. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sowparnika Ashiyana Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sowparnika Ashiyana Phase II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sowparnika Ashiyana Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.