ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SOLITAIRE EMPIRE

Registered No litigation declared Residential / Group Housing project

SOLITAIRE EMPIRE

By NAGESHWAR ASSOCIATES

RG-MH-64906 · RERA P52100050700 · Last updated on MahaRERA portal: 8 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 12 months from the original
24 of 44Construction stages doneacross 4 buildings; furthest along: Sanitary Fittings within the flats /..., 70%
19 of 98Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 92 documents Report an error

SOLITAIRE EMPIRE is a Residential / Group Housing project by NAGESHWAR ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100050700 on 28 Apr 2023. Possession is promised by 31 Dec 2026. The completion date has moved by 12 months from the original filing. 79 of the 98 units on this registration are recorded sold or booked, and 24 of 44 construction stages are filed complete.

At a glance

Project

  • NameSOLITAIRE EMPIRE
  • TypeResidential / Group Housing
  • Location
    • MOSHI
    • Haveli
    • Pune
    • 412105
  • Pincode412105
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100050700
  • ReraGenie IDRG-MH-64906

Builder

  • NameNAGESHWAR ASSOCIATES
  • Entity typePartnership
  • PartnersYOGESH GORAKHANATH ALHAT, SAGAR BABAN MARANE, SHARAD MAHADU JADHAV

Key dates

this monthRegisteredApr 2023First promiseDec 2025Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Apr 2023
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2025)
  • Buildings4 building records
  • Documents filed92 files

Current status

81%79 of 98 units booked
86.0%Work done, per cost certificate

Figures as on 8 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA9728028
Wing BNA9728028
Wing CNA9728028
Wing DNA9714014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 8 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 70%.

Wing A64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B70%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D45%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed199

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots199
Closed/Covered89
Open Space110
BuildingClosed/CoveredOpen SpaceTotal
Wing A252853
Wing B252853
Wing C252752
Wing D142741

Land and ownership28

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners28
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Jul 2025
LandownerVillageDistrict
VISHAL VASUDEV ALHATMoshiPune
SEEMA GORAKH ALHATMoshiPune
PARVATI BALU DUDHALEMoshiPune
HIRABAI DATTATRAY PHULECHARHOLIPune
HAUSABAI VITTHAL SASANEPimpri Chinchawad (M Corp.)Pune
MUKTABAI RAMHARI SASANEMoshiPune
LAXMI RAGHUNATH SASANEMoshiPune
ALKA CHANDRAKANT JADHAVMoshiPune
BHANUDAS BHIKU ALHATMoshiPune
NAVNATH BHIKU ALHATMoshiPune
TUSHAR BALASAHEB VIDHATEMoshiPune
KISHOR BALASAHEB VIDHATEMoshiPune
VAISHALI SANTOSH KUDALIMoshiPune
VASUDEV MURALIDHAR ALHATMoshiPune
GORAKH MURALIDHAR ALHATMoshiPune
SHANTABAI BHIKU ALHATMoshiPune
RAKHAMABAI MURALIDHAR ALHATMoshiPune
SWATI VINOD JADHAVMoshiPune
SONALI SURYAKANT JADHAVChikhaliPune
AKSHADA GORAKH ALHATMoshiPune
CHETANGORAKH ALHATMoshiPune
PAYAL KISHOR VIDHATEMoshiPune
NIKHIL BHANUDAS ALHATMoshiPune
PRANALI ABHIJIT SATAVMoshiPune
PRATIK NAVNATH ALHATMoshiPune
ASHA BHANUDAS ALHATMoshiPune
SEEMA NAVNATH ALHATMoshiPune
LATA VASUDEV ALHATMoshiPune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI6735.89
Proposed, not sanctioned6,736 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMOSHI PRADHIKARAN PUNE 412105
Estimated costRs 24.11 cr
Cost incurredRs 20.73 cr
Work done85.98%
BuildingWingEstimatedIncurred
Wing ANARs 7.07 crRs 7.00 cr
Wing BNARs 7.07 crRs 6.89 cr
Wing CNARs 5.65 crRs 3.91 cr
Wing DNARs 2.83 crRs 1.98 cr
-NARs 1.50 crRs 94.62 lakh

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYOGESH MANKSHE
EngineerPARAG CHOPADA
EngineerSwamiraj Project Management Consultancy
EngineerYash Rathod
Chartered AccountantAZAM MULANI AND ASSOCIATES
Chartered AccountantAkib Ikbal Modi
Chartered AccountantPratik Navlakha
Chartered AccountantA I Modi and Co
Chartered AccountantJyoti
PartnerRole in project
NAGESHWAR ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA30102518201Dec 2025 → Dec 2026

Reason as filed by the promoterThe extension is primarily due to significant delays in obtaining timely sanction of the revised plan from the relevant authority. Although we approached the authority promptly, the approval of the revised sanction plan was delayed. As a result, additional time is necessary to address these delays and complete the required tasks. Hence, additional time is required to address the delays, requesting you to grant us the same.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Sep 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed92

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 92 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Q 1 Form 1.pdf8 Aug 2026
Withdrawal Update Form 2File: Q 1 form 2.pdf8 Aug 2026
Withdrawal Update Form 3File: Q 1 Form 3.pdf8 Aug 2026
Withdrawal Update Form 1File: Form 1N A EMPIRE Q3.pdf17 Apr 2026
Withdrawal Update Form 1File: Q4 March Form 1.pdf17 Apr 2026
Withdrawal Update Form 2File: FORM 2 NAGESHWAR ASSOCIATE Q3 _QPR.pdf17 Apr 2026
Withdrawal Update Form 2File: Q4 March form 2.pdf17 Apr 2026
Withdrawal Update Form 3File: from 3-1-9_11zon.pdf17 Apr 2026
Withdrawal Update Form 3File: Q4 Mar form 3.pdf17 Apr 2026
Form 1File: Form 1 - Q4 23-24.pdf2 Dec 2025
Form 2File: Form 2 Q4 23-24.pdf2 Dec 2025
Form 3File: Form 3 Q4 23-24.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure Of Sold Booked Inventory.pdf2 Dec 2025
Form 1File: Form 1 - Q4 23-24.pdf2 Dec 2025
Form 2File: Form 2 Q4 23-24.pdf2 Dec 2025
Form 3File: Form 3 Q4 23-24.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure Of Sold Booked Inventory.pdf2 Dec 2025
Form 1File: Form 1 - Q4 23-24.pdf2 Dec 2025
Form 2File: Form 2 Q4 23-24.pdf2 Dec 2025
Form 3File: Form 3 Q4 23-24.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure Of Sold Booked Inventory.pdf2 Dec 2025
Form 1File: Form 1 - Q4 23-24.pdf2 Dec 2025
Form 2File: Form 2 Q4 23-24.pdf2 Dec 2025
Form 3File: Form 3 Q4 23-24.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure Of Sold Booked Inventory.pdf2 Dec 2025
Form 1File: Form 1 Q1 24-25.pdf2 Dec 2025
Form 2File: Form 2 Q1 24-25.pdf2 Dec 2025
Form 3File: Form 3 Q1 24-25.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q1 Disclosure Of Sold _ Booked Inventory (Building Wise).pdf2 Dec 2025
Form 1File: Form 1 Q2 24-25.pdf2 Dec 2025
Form 2File: Form 2 Q2 24-25.pdf2 Dec 2025
Form 3File: Form 3 Q2 24-25.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q2 Disclosure Of Sold _ Booked Inventory (Building Wise).pdf2 Dec 2025
Form 1File: Form 1 Q3 24-25.pdf2 Dec 2025
Form 2File: Form 2 Q3 24-25.pdf2 Dec 2025
Form 3File: Form 3 Q3 24-25.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q3 Disclosure Of Sold _ Booked Inventory (Building Wise).pdf2 Dec 2025
Form 1File: Form 1 Q4 24-25.pdf2 Dec 2025
Form 2File: Form 2 Q4 24-25.pdf2 Dec 2025
Form 3File: Form 3 Q4 24-25.pdf2 Dec 2025
Disclosure of Sold and Booked InventoryFile: Q4 Disclosure Of Sold _ Booked Inventory (Building Wise).pdf2 Dec 2025
Form 2A (FY 2024-2025)File: Form 2A 24-25.pdf2 Dec 2025
Form 2A (FY 2023-2024)File: Form 2A 23-24 (1).pdf2 Dec 2025
Form 5 (FY 2023-2024)File: Form 5 23-24 (1).pdf2 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 24-25.pdf2 Dec 2025
Withdrawal Update Form 1File: form 1.pdf18 Oct 2025
Withdrawal Update Form 2File: Form 2.pdf18 Oct 2025
Withdrawal Update Form 3File: Form 3_compressed.pdf18 Oct 2025
Building plan approvalFile: 1 (1).pdf4 Sep 2025
Building plan approvalFile: 2 (2).pdf4 Sep 2025
Building plan approvalFile: 3 (1).pdf4 Sep 2025
Building plan approvalFile: 4 (1).pdf4 Sep 2025
Building plan approvalFile: 5_rotated.pdf4 Sep 2025
Building plan approvalFile: 6_rotated.pdf4 Sep 2025
Withdrawal Update Form 1File: Form 1.pdf22 Jul 2025
Withdrawal Update Form 2File: Form 2.pdf22 Jul 2025
Withdrawal Update Form 3File: Form 3 (6).pdf22 Jul 2025
Building plan approvalFile: Building Plan.pdf3 Jul 2025
Layout approvalFile: 1 (2)_compressed.pdf24 Oct 2024
Building plan approvalFile: 3.pdf24 Oct 2024
Building plan approvalFile: 6.pdf24 Oct 2024
Building plan approvalFile: 5.pdf24 Oct 2024
Building plan approvalFile: 4.pdf24 Oct 2024
Building plan approvalFile: 2.pdf24 Oct 2024
Copy of Layout Approval (in case of layout)File: 1 (2)_compressed.pdf24 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 3.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 6.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 5.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 4.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 2.pdf24 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE - NEW.pdf24 Apr 2023
CERSAI detailsFile: CERSAI RECEIPT.pdf13 Apr 2023
Proforma of Agreement for saleFile: DRAFT AGREEMENT.pdf13 Apr 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf13 Apr 2023
Declaration in FORM BFile: Form B of Promoter.pdf11 Apr 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclousure - Yogesh Alhat.pdf11 Apr 2023
Building plan approvalFile: HPSC0627.pdf7 Apr 2023
Building plan approvalFile: HPSC0626.pdf7 Apr 2023
Layout approvalFile: HPSC0629.pdf7 Apr 2023

How this compares with Pune

81%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SOLITAIRE EMPIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MOSHI13,700+ in Pune

2 kmSOLITAIRE EMPIRECompleted 80Lapsed / revoked 48Other 79Dot size: filed unitsN

Filed coordinates, straight-line distance. 207 registered projects within 2 km.

Builder: NAGESHWAR ASSOCIATES

NAGESHWAR ASSOCIATES has 1 registration on MahaRERA, including SOLITAIRE EMPIRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SOLITAIRE EMPIRE is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SOLITAIRE EMPIRE?

The registered promoter entity is NAGESHWAR ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SOLITAIRE EMPIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SOLITAIRE EMPIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SOLITAIRE EMPIRE?

The professionals named in the filing: Architect: YOGESH MANKSHE; Engineer: PARAG CHOPADA; Engineer: Swamiraj Project Management Consultancy; Engineer: Yash Rathod; Chartered Accountant: AZAM MULANI AND ASSOCIATES; Chartered Accountant: Akib Ikbal Modi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SOLITAIRE EMPIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SOLITAIRE EMPIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SOLITAIRE EMPIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.