ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SNN RAJ SERENITY

Registration approved No litigation declared Residential/Group Housing project

SNN RAJ SERENITY

By SNN Builders Private Limited

RG-KA-66499 · RERA PRM/KA/RERA/1251/310/PR/150622/004987 · Last updated on RERA Karnataka portal: 15 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 3 complaints at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Oct 2027Possession promisedno revision filed
16 of 17Construction stages donefurthest along: Internal and External work including..., 97%
63 of 594Units unsoldnot recorded sold or booked
3Complaints at RERA Karnatakaon this registration
Jump to the 212 documents Report an error

SNN RAJ SERENITY is a Residential/Group Housing project by SNN Builders Private Limited in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/150622/004987 on 15 Jun 2022. Possession is promised by 31 Oct 2027. 531 of the 594 units on this registration are recorded sold or booked, and 16 of 17 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameSNN RAJ SERENITY
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560068
  • Pincode560068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/150622/004987
  • ReraGenie IDRG-KA-66499

Builder

  • NameSNN Builders Private Limited
  • Entity typeCompany
  • CINU45202KA2009PTC051411
  • GSTIN29AANCS6172K1ZL
  • Authorized SignatoryNitin Agarwal
  • Managing DirectorRamesh Chandra Agarwal
  • DirectorsNitin Agarwal, NIKHIL AGARWAL, SHAH SANJAY, NEELU JAIN, SHIVA SHANKAR BHAT
  • Project HeadNIKHIL AGARWAL
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredJun 2022PromisedOct 2027

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on15 Jun 2022
  • Promised completion31 Oct 2027
  • Revised completionNone
  • Buildings9 building records
  • Documents filed212 files

Current status

89%531 of 594 units booked
94.3%Of the estimated cost spent so far

Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
G1---70070
G2---70070
G3---70070
G4---70070
G5---66066
G6---70070
G7---70070
G8---54054
G9---54054

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

16 of 17 construction stages are filed complete. The stage furthest along is Internal and External work including landscapes as per..., at 97%.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with network100%
Weather Proof work(tile,concrete)100%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation workNot applicable
Internal and External work including landscapes as per sanctioned drawings97%

Progress on shared amenities40

As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes100%
Solid waste management and disposalYes100%
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes98%
Electricity supply transformer and substationYes100%
Storm water drainsYes98%
Use of renewable energyYes100%
Sewage Treatment Plant (STP)Yes98%
Parks & Tree plantingYes98%
Street LightingYes98%
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes98%
Club HouseYes100%
Community HallYes100%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes100%
Swimming PoolYes100%
GymYes100%
ParksYes98%
Power BackupYes100%
Piped GasNoNot applicable
Water and SanitationYes100%
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahYes100%
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes98%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes98%
Common storage spacesNoNot applicable

Land and ownership12

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area28,145 sq m
Named landowners12
LandownerVillageDistrict
SNN Builders Private Limited--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--
SNN BUILDERS PVT LTD--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 332.40 cr
Cost incurredRs 313.34 cr
Spent of the estimate94.27%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 251.13 crRs 302.07 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 50.21 cr-
On-site expenditure-Site OverheadRs 29.47 crRs 11.27 cr
On-site expenditure-Consultants FeesRs 1.09 cr-
Payment of taxesRs 25.00 lakh-
Payment of cessRs 25.00 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJamuna Chalam
EngineerK VENKATESH BABU REDDY
Chartered AccountantRAMAKRISHNA KAMAT

Complaints filed with RERA Karnataka3

Case no.ComplainantRespondentFiled
00291/2025-SNN Builders Private Limited12/02/2025
00656/2025-SNN Builders Private Limited21/04/2025
00464/2026-SNN Builders Private Limited04/05/2026

Documents filed212

As listed on the registration, under the names the promoter filed them with; the newest 80 of 212 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/150622/004987 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RSTGB-Form 4 Final 26-27 Q2.pdf15 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: RSTGB-Architect Certificate 26-27 Q2.pdf15 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: RSTGB-Engineer Certificate 26-27 Q2.pdf15 Oct 2026
Q2 2026-27 Water supply and sewage board15 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Oct 2026
Q2 2026-27 KPTCL- BESCOM15 Oct 2026
Q2 2026-27 Fire and Safety15 Oct 2026
Q2 2026-27 Airport Authority of India15 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department15 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Serenity Gardens Form 4 Q1 26 27.pdf13 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: RSTGB-Architect Certificate 26-27 Q1.pdf13 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: RSTGB-Engineer Certificate 26-27 Q1 (1).pdf13 Jul 2026
Q1 2026-27 Water supply and sewage board13 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)13 Jul 2026
Q1 2026-27 KPTCL- BESCOM13 Jul 2026
Q1 2026-27 Fire and Safety13 Jul 2026
Q1 2026-27 Airport Authority of India13 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department13 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RSTGB-Form 4 Certificate 25 26 Q4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: RSTGB-Architect Certificate 25-26 Q4-Final.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: RSTGB-Engineer Certificate 25-26 Q4-Final.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Serenity Gardens Form 4 25-26 Q3.pdf13 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: RSTGB-Architect certificate 25-26 Q3.pdf13 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: RSTGB-Engineer Certificate 25-26 Q3.pdf13 Jan 2026
Q3 2025-26 Water supply and sewage board13 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)13 Jan 2026
Q3 2025-26 KPTCL- BESCOM13 Jan 2026
Q3 2025-26 Fire and Safety13 Jan 2026
Q3 2025-26 Airport Authority of India13 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department13 Jan 2026
RERA AOSFile: RERA FORMAT SALE AGREEMENT.pdf3 Jun 2022
EC 1 AcreFile: EC 1 ACRE.pdf23 May 2022
EC 40/2 4 5 6File: EC 40:2 4 5 6.pdf23 May 2022
EC 49/2 18 GuntaFile: EC 49:2 18 GUNTAS.pdf23 May 2022
EC 41/1 2 3 4 5 42/5File: EC SY NO 41:1 2 3 4 5 42:5.pdf23 May 2022
EC 41/7 & 42/5File: EC SY NO 41:7 & 42:5.pdf23 May 2022
New Commencement CertificateFile: New Commencement Certificate.pdf23 May 2022
No Litigation AffidavitFile: No Litigation Affidavit .pdf23 May 2022
Relinquishment DeedFile: RELINQUISHMENT DEED.pdf23 May 2022
RTC 49/2File: RTC.pdf23 May 2022
Sale Deed 49/2 18 GuntaFile: SALE DEED 49:2 18 GUNTAS.pdf23 May 2022
Site Plan and Area ClarificationFile: Site plan and Area calculation.pdf23 May 2022
Development Plan orderFile: Development plan order.pdf23 May 2022
Development PlanFile: Development plan.pdf23 May 2022
Site PlanFile: Site Plan.pdf6 May 2022
RTCFile: RTC.pdf6 May 2022
MRFile: MR EXTRACT PHODY.PDF6 May 2022
Conversion OrderFile: Conversion Order.pdf6 May 2022
Sale deedFile: Sale Deed.pdf6 May 2022
Title Deed 1File: Title Deed.pdf6 May 2022
Title Deed 2File: Title Deed 2.pdf6 May 2022
Title Deed 3File: Title Deed 3.pdf6 May 2022
No Litigation AffidavitFile: No Litigation Affidavit.PDF6 May 2022
ECFile: EC.pdf6 May 2022
Development planFile: Development plan.pdf6 May 2022
Development plan orderFile: Development plan order.pdf6 May 2022
Building sanction orderFile: Building Sanction order.pdf6 May 2022
Approved buildingFile: Approved Building Plan.pdf6 May 2022
Commencement undertaking letterFile: Commencement Undertaking letter.pdf6 May 2022
KSPCBFile: Upload KSPCB CFO Undertaking Letter.PDF6 May 2022
SEIAAFile: SEIAA NOC.PDF6 May 2022
Section 3 affidavitFile: Section 3 Affidavit.pdf6 May 2022
Agreement of SaleFile: Agreement of Sale.PDF6 May 2022
Form 3 Engineer CertificateFile: Form 3 Engineer Certificate.pdf6 May 2022
BESCOMFile: BESCOM NOC.PDF6 May 2022
BSNLFile: BSNL NOC.PDF6 May 2022
BWSSBFile: BWSSB .PDF6 May 2022
Architect PlanFile: Architect Plan.pdf6 May 2022
RTC, survey 40/2-
Mutation, survey 40/2-
Encumbrance Certificate, survey 40/2-
Conversion/Alienation Order, survey 40/2-
Sale/Title/Gift Deed, survey 40/2-
Khatha, survey 40/2-

How this compares with Bengaluru Urban

89%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SNN RAJ SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmSNN RAJ SERENITYOther 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: SNN Builders Private Limited

SNN Builders Private Limited has 2 registrations on RERA Karnataka, including SNN ESTATES FELICITY and SNN RAJ SERENITY. Its filings declare 1 earlier project, none of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SNN RAJ SERENITY is delayed beyond 31 Oct 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SNN RAJ SERENITY?

The registered promoter entity is SNN Builders Private Limited, a company as per the filing. Its CIN U45202KA2009PTC051411 and GSTIN 29AANCS6172K1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SNN RAJ SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SNN RAJ SERENITY?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SNN RAJ SERENITY?

The professionals named in the filing: Architect: Jamuna Chalam; Engineer: K VENKATESH BABU REDDY; Chartered Accountant: RAMAKRISHNA KAMAT. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SNN RAJ SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SNN RAJ SERENITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SNN RAJ SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.