Home / Browse projects / Bengaluru Urban, Karnataka / Assetz Canvas & Cove 2.0 - Block B & C

Registration approved No litigation declared Residential/Group Housing project

Assetz Canvas & Cove 2.0 - Block B & C

By APG HABITAT PRIVATE LIMITED

RG-KA-23651 · RERA PRM/KA/RERA/1251/310/PR/071223/006454 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Oct 2028Possession promisedno revision filed
3 of 18Construction stages donefurthest along: Retaining wall (All types), 97%
4 of 373Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 178 documents Report an error

Assetz Canvas & Cove 2.0 - Block B & C is a Residential/Group Housing project by APG HABITAT PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/071223/006454 on 7 Dec 2023. Possession is promised by 31 Oct 2028. 369 of the 373 units on this registration are recorded sold or booked, and 3 of 18 construction stages are filed complete.

At a glance

Project

  • NameAssetz Canvas & Cove 2.0 - Block B & C
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560068
  • Pincode560068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/071223/006454
  • ReraGenie IDRG-KA-23651

Builder

  • NameAPG HABITAT PRIVATE LIMITED
  • Entity typeCompany
  • CINU70109KA2016PTC093453
  • GSTIN29AAOCA4442R1ZV
  • Authorized SignatorySomasundaram Thiruppathi
  • CeoAkshay Kishore Dewani
  • DirectorsSomasundaram Thiruppathi, Jagannath Laxman Shetty
  • Project HeadGurumoorthy N
  • Other registrations3 more →

Key dates

this monthRegisteredDec 2023PromisedOct 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on7 Dec 2023
  • Promised completion31 Oct 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed178 files

Current status

99%369 of 373 units booked
57.5%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLOCK -B---1620162
BLOCK-C---2110211

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 18 construction stages are filed complete. The stage furthest along is Retaining wall (All types), at 97%.

Building: 27% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)0%
Retaining wall (All types)97%
RCC or MS Framed structure90%
Masonry Construction0%
Plastering inside , outside & Ceiling0%
Joinery: Doors, Windows, Ventilators etc0%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing0%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)0%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes0%
Sewage and Drainage SystemYes35%
Water conservation/rain water harvesting/recharge of ground waterYes55%
Energy managementYes0%
Fire protection and fire safety requirementsYes0%
Solid waste management and disposalYes0%
Emergency Evacuation servicesYes0%
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes60%
Use of renewable energyYes0%
Sewage Treatment Plant (STP)Yes70%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes0%
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityYes0%
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningYes0%
StaircasesYes25%
LiftsYes0%
Corridor/LobbiesYes0%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes0%
BasementYes0%
TerraceYes0%
Outer WallYes0%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes0%
Common storage spacesYes0%

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area38,546 sq m
Named landowners5
LandownerVillageDistrict
N Arun Kumar--
Pankaja--
B.S.Somashekar--
Ramaiah--
Pradeep Krishnappa--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 228.25 cr
Cost incurredRs 131.25 cr
Spent of the estimate57.5%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 180.47 crRs 88.51 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 19.26 crRs 22.14 cr
On-site expenditure-Site OverheadRs 13.07 crRs 12.56 cr
Approval CostRs 11.45 crRs 5.69 cr
On-site expenditure-Consultants FeesRs 4.01 crRs 2.35 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKishore Panikkar
EngineerHITEN RAMANLAL MAHIMTURA
Chartered AccountantY S Shetty & Company

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed178

As listed on the registration, under the names the promoter filed them with; the newest 80 of 178 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/071223/006454 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove B & C.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove 2 0 Block B & C.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) - Canvas & Cove B&C.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KSPCB- MOEF (Above 50 Acres)14 Oct 2026
Q2 2026-27 Fire and Safety14 Oct 2026
Q2 2026-27 Airport Authority of India14 Oct 2026
Q2 2026-27 BSNL/Telecommunication Department14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove B & C.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove 2 Block B & C.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) - Canvas & Cove B&C.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)15 Jul 2026
Q1 2026-27 Fire and Safety15 Jul 2026
Q1 2026-27 Airport Authority of India15 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove B & C.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove B & C.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) - Canvas & Cove B&C.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove B & C.pdf11 Mar 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove B & C.pdf11 Mar 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6- Engineer Certificate Assetz C & C Block B & C.pdf11 Mar 2026
Q3 2025-26 Water supply and sewage board11 Mar 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)11 Mar 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)11 Mar 2026
Q3 2025-26 Fire and Safety11 Mar 2026
Q3 2025-26 Airport Authority of India11 Mar 2026
Q3 2025-26 BSNL/Telecommunication Department11 Mar 2026
Building LicenceFile: Annexure 1 - Building Licence.pdf5 Dec 2023
Site Plan, Combined Basement+Ground FloorPlan,Block C - from 1st to 13th Floor PlanFile: Annexure 2 -Site Plan, Combined Basement+Ground FloorPlan,Block C - from 1st to 13th Floor5 Dec 2023
Block C -from 14th to Terrace Floor Plan, Block B - 1st to 7th Floor PlanFile: Annexure 3 - Block C -from 14th to Terrace Floor Plan, Block B - 1st to 7th Floor Plan.pdf5 Dec 2023
Block B - from 8th to Terrace Floor PlanFile: Annexure 4 - Block B - from 8th to Terrace Floor Plan.pdf5 Dec 2023
Sections & ElevationFile: Annexure 5 - Sections & Elevation.pdf5 Dec 2023
Bank Statement and ClarificationFile: Annexure 1-Clarification regarding Loan and Bank Statement.pdf2 Dec 2023
Area DetailsFile: Annexure 2-Area Details.pdf2 Dec 2023
BHK Type Area detailsFile: Annexure 3-BHK Wise Inventory.pdf2 Dec 2023
Carpet areaFile: Annexure 4-Carpet Area Calculation.pdf2 Dec 2023
FAR SanctionFile: Annexure 5-FAR Sanctioned.pdf2 Dec 2023
Built Up areaFile: Annexure 6-Built up Area.pdf2 Dec 2023
Hieght of the BuildingFile: Annexure 7-Height of Building.pdf2 Dec 2023
Car Parking DetailsFile: Annexure 8-Car Park details.pdf2 Dec 2023
Carpet area CalculationFile: Annexure 9-Carpet Area Calculation.pdf2 Dec 2023
Sensative Area ClearanceFile: Annexure 10-BEGUR SENSITIVE ZONE CLR.pdf2 Dec 2023
SIEAA Noc ClarificationFile: Annexure 12-Clarification regarding SEIAA.pdf2 Dec 2023
KSPCB NOC ClarificationFile: Annexure 13-Clarification Regrading KSPCB.pdf2 Dec 2023
DP plan OrderFile: Annexure 14-DP order copy.pdf2 Dec 2023
Building License CopyFile: Annexure 15-Building Licence Copy.pdf2 Dec 2023
Architect CertificateFile: Annexure 16-Architect Certificate.pdf2 Dec 2023
Engineer CertificateFile: Annexure 17-Engineer Certificate.pdf2 Dec 2023
CA CertificateFile: Annexure 18-CA Certificate.pdf2 Dec 2023
Sanction PlanFile: Annexure 19-Sanction Drawings.pdf2 Dec 2023
Profit & Loss and Balance Sheet 2019-20File: Annexure 1-BS and P & L 2019-20.pdf9 Nov 2023
Profit & Loss and Balance Sheet 2020-21File: Annexure 2-BS and P & L 2020-21.pdf9 Nov 2023
Profit & Loss and Balance Sheet 2021--22File: Annexure 3-BS and P & L 2021-22.pdf9 Nov 2023
Bank statement 100File: Annexure 4-Bank statement 100.pdf9 Nov 2023
Bank statement 70File: Annexure 5-Bank Statement 70.pdf9 Nov 2023
Bank statement 30File: Annexure 6-Bank Statement 30.pdf9 Nov 2023
Clarification regarding FundsFile: Annexure 8-Clarification regarding Funds.pdf9 Nov 2023
the Source of funds to complete the Project.File: Annexure 9-Sources of Funds.pdf9 Nov 2023
the chartered accountant certificate in the prescribed format form -01File: Annexure 10-CA Certificate form 1.pdf9 Nov 2023
EC for sno 133/1 from 1/2/2018 to till dateFile: Annexure 11-EC Sy no 133-1.pdf9 Nov 2023
sno 134 from 25/1/2019 to till dateFile: Annexure 12-EC Sy no 134-1.pdf9 Nov 2023
RTC of sno 134/1File: Annexure 13-RTC Sy no 134-1.pdf9 Nov 2023
single EC from 1-10-2015 to till date for sno 134/1File: Annexure 14-EC Sy no 134-1.pdf9 Nov 2023
RTC of sno 134/1File: Annexure 15-RTC Sy no 134-1.pdf9 Nov 2023
single continuous EC for the period 1-4-2007 to till date for sno 134/3 6)File: Annexure 16-EC from 2007 to till date sy no 134-3.pdf9 Nov 2023
Non-Litigation AffidavitFile: Annexure 17-Non-Litigation Affidavit.pdf9 Nov 2023
Form BFile: Annexure 18-Form B.pdf9 Nov 2023
Joint AffidavitFile: Annexure 19-Joint Affidavit.pdf9 Nov 2023
Area DetailsFile: Annexure 20-Area Details.pdf9 Nov 2023
Clarification regarding carpet areaFile: Annexure 21 -Carpet Area.pdf9 Nov 2023
Clarification regarding Built AreaFile: Annexure 22 -Built Area.pdf9 Nov 2023

How this compares with Bengaluru Urban

99%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep Assetz Canvas & Cove 2.0 - Block B & C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmAssetz Canvas & Cove 2.0Other 27Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: APG HABITAT PRIVATE LIMITED

APG HABITAT PRIVATE LIMITED has 4 registrations on RERA Karnataka, including Assetz Canvas & Cove 2.0 - Block A and Assetz Canvas & Cove 2.0 - Block B & C. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if Assetz Canvas & Cove 2.0 - Block B & C is delayed beyond 31 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of Assetz Canvas & Cove 2.0 - Block B & C?

The registered promoter entity is APG HABITAT PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2016PTC093453 and GSTIN 29AAOCA4442R1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in Assetz Canvas & Cove 2.0 - Block B & C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at Assetz Canvas & Cove 2.0 - Block B & C?

The professionals named in the filing: Architect: Kishore Panikkar; Engineer: HITEN RAMANLAL MAHIMTURA; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Assetz Canvas & Cove 2.0 - Block B & C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Assetz Canvas & Cove 2.0 - Block B & C. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Assetz Canvas & Cove 2.0 - Block B & C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.