Home / Browse projects / Bengaluru Urban, Karnataka / CASAGRAND AMOR

Registration approved No litigation declared Residential/Group Housing project

CASAGRAND AMOR

By CASA GRANDE GARDEN CITY BUILDERS PVT LTD

RG-KA-85861 · RERA PRM/KA/RERA/1251/310/PR/140324/006701 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
Feb 2028Possession promisedno revision filed
3 of 18Construction stages donefurthest along: Sub-structure flooring (Parking Floor, 80%
144 of 480Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 130 documents Report an error

CASAGRAND AMOR is a Residential/Group Housing project by CASA GRANDE GARDEN CITY BUILDERS PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/140324/006701 on 14 Mar 2024. Possession is promised by 23 Feb 2028. 336 of the 480 units on this registration are recorded sold or booked, and 3 of 18 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCASAGRAND AMOR
  • TypeResidential/Group Housing
  • Location
    • Bengaluru South
    • Bengaluru Urban
    • 560068
  • Pincode560068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1251/310/PR/140324/006701
  • ReraGenie IDRG-KA-85861

Builder

  • NameCASA GRANDE GARDEN CITY BUILDERS PVT LTD
  • Entity typeCompany
  • GSTIN29AAGCC1577R1ZV
  • Authorized SignatorySethupathy G
  • MdARUN M N
  • DirectorsCG SATHISH, ARUN M N, T Jagmohan
  • Project HeadMANOJ KUMAR M
  • Other registrations16 more →
  • Declared earlier projects12 →

Key dates

this monthRegisteredMar 2024PromisedFeb 2028

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on14 Mar 2024
  • Promised completion23 Feb 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed130 files

Current status

70%336 of 480 units booked
3.5%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CASAGRAND AMOR---4800480

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 18 construction stages are filed complete. The stage furthest along is Sub-structure flooring (Parking Floor, at 80%.

Building: 41% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)80%
Retaining wall (All types)30%
RCC or MS Framed structure60%
Masonry Construction60%
Plastering inside , outside & Ceiling40%
Joinery: Doors, Windows, Ventilators etc20%
Basic work of Water supply, Sanitary and Electrification20%
Dadoing, Skirting, Flooring, Tiles work (All types)20%
Railing and Grill fixing20%
Electrification, Water supply and Sanitary Finishing30%
Painting0%
Fire prevention and fire fighting fitting and fixture with network0%
Weather Proof work(tile,concrete)20%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work20%
Internal and External work including landscapes as per sanctioned drawings10%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes30%
Sewage and Drainage SystemYes30%
Water conservation/rain water harvesting/recharge of ground waterYes30%
Energy managementYes30%
Fire protection and fire safety requirementsYes30%
Solid waste management and disposalYes30%
Emergency Evacuation servicesYes30%
Internal Roads & FootpathsYes30%
Electricity supply transformer and substationYes30%
Storm water drainsYes30%
Use of renewable energyYes30%
Sewage Treatment Plant (STP)Yes30%
Parks & Tree plantingYes30%
Street LightingYes30%
ElectricityYes30%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes30%
Club HouseYes30%
Community HallYes30%
Outdoor Sports facilityYes30%
Indoor Sports facilityYes30%
Swimming PoolYes30%
GymYes30%
ParksYes30%
Power BackupYes30%
Piped GasYes30%
Water and SanitationYes30%
Air ConditioningNoNot applicable
StaircasesYes30%
LiftsYes30%
Corridor/LobbiesYes30%
Fire escapesYes0%
Common entrance and exit for the building/common portico/foyer/verandahYes30%
BasementYes30%
TerraceYes30%
Outer WallYes30%
Open parking areasYes30%
Provision for lodging of management staff and security staffYes30%
Water conservation and renewable energyYes30%
Common storage spacesYes30%

Land and ownership3

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area31,628 sq m
Named landowners3
LandownerVillageDistrict
Babu Reddy--
Babu Reddy--
Babu Reddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 195.83 cr
Cost incurredRs 6.93 cr
Spent of the estimate3.54%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 195.83 crRs 6.93 cr

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectP S NAGESH
EngineerShivaraj G Naik
Chartered AccountantNARAYANA RAO M

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
01155/2024-CASA GRANDE GARDEN CITY BUILDERS PVT LTD13/11/2024

Documents filed130

As listed on the registration, under the names the promoter filed them with; the newest 80 of 130 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/140324/006701 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: RERA CA form 4 sep 2026 Amor.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: FORM 5.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: FORM 6.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf10 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Architect cert QU1 2026 27.pdf10 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Amor Jun 2026 qtr.pdf10 Jul 2026
Q1 2026-27 Water supply and sewage board10 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)10 Jul 2026
Q1 2026-27 KPTCL- BESCOM10 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf11 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Architect cert Proj Amor.pdf11 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Amor qtr.pdf11 Apr 2026
Q4 2025-26 Water supply and sewage board11 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)11 Apr 2026
Q4 2025-26 KPTCL- BESCOM11 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: CA Certificate.pdf9 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Architect cert Q3 25 Proj Amor.pdf9 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Engg Proj Amor dec 2025 qtr.pdf9 Jan 2026
Q3 2025-26 Water supply and sewage board9 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)9 Jan 2026
Q3 2025-26 KPTCL- BESCOM9 Jan 2026
Query ResponseFile: 1 Query Response.pdf12 Mar 2024
Cashflow statement 2022-23File: 2 Cashflow statement 2022-23.pdf12 Mar 2024
Cashflow statement 2021-22File: 3 Cashflow statement 2021-22.pdf12 Mar 2024
Cashflow statement 2020-21File: 4 Cashflow statement 2020-21.pdf12 Mar 2024
Source of fundsFile: 5 Source of funds.pdf12 Mar 2024
AMOR Affidavit RERAFile: 6 AMOR Affidavit RERA.pdf12 Mar 2024
7 CASAGRAND BOULEVARD - Recall - Withdraw Letter12 Mar 2024
CASAGRAND ORLENA - Recall - Withdraw LetterFile: 8 CASAGRAND ORLENA - Recall - Withdraw Letter.pdf12 Mar 2024
RTC, survey 21-
Mutation, survey 21-
Encumbrance Certificate, survey 21-
Conversion/Alienation Order, survey 21-
Sale/Title/Gift Deed, survey 21-
JDA, survey 21-
Khatha, survey 21-
RTC, survey 22-
Mutation, survey 22-
Encumbrance Certificate, survey 22-
Conversion/Alienation Order, survey 22-
Sale/Title/Gift Deed, survey 22-
JDA, survey 22-
Khatha, survey 22-
RTC, survey 23-
Mutation, survey 23-
Encumbrance Certificate, survey 23-
Conversion/Alienation Order, survey 23-
Sale/Title/Gift Deed, survey 23-
JDA, survey 23-
Khatha, survey 23-
Registration CertificateFile: Certificate of Incorporation.pdf-
Organization StructureFile: Organization Structure.pdf-
Certificate issued by CA Form 1File: Form-1 CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form-2 Architect Certificate.pdf-
Certificate issued by Engineer Form 3File: Form-3 Engineer Certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: Non-Litigation Affidavit.pdf-
Certificate from Chartered AccountFile: Form-1 CA Certificate.pdf-
Balance Sheet 2022 - 2023File: Financials 2022-23.pdf-
Balance Sheet 2021 - 2022File: Financials 2021-22.pdf-
Balance Sheet 2020 - 2021File: Financials 2020-21.pdf-
Audited Profit and Loss Statement 2022 - 2023File: Financials 2022-23.pdf-
Audited Profit and Loss Statement 2021 - 2022File: Financials 2021-22.pdf-
Audited Profit and Loss Statement 2020 - 2021File: Financials 2020-21.pdf-
Director's Report 2022 - 2023File: Financials 2022-23.pdf-
Director's Report 2021 - 2022File: Directors report 2021-22.pdf-
Director's Report 2020 - 2021File: Financials 2020-21.pdf-
Cash Flow Statement 2022 - 2023File: Financials 2022-23.pdf-
Cash Flow Statement 2021 - 2022File: Cashflow statement 2021-22.pdf-
Auditor's Report 2022 - 2023File: Financials 2022-23.pdf-
Auditor's Report 2021 - 2022File: Audit Report for March 22.pdf-
Auditor's Report 2020 - 2021File: Audit report 2020-21.pdf-
Income Tax Return Acknowledgement 2022 - 2023File: ITR Acknowledgement for FY 2023-24.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR ACK 2021-22.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR for 2020-21.pdf-

How this compares with Bengaluru Urban

70%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one has not
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep CASAGRAND AMOR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

2 kmCASAGRAND AMOROther 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 35 registered projects within 2 km.

Builder: CASA GRANDE GARDEN CITY BUILDERS PVT LTD

Casa Grande Garden City Builders Pvt ltd has 17 registrations on RERA Karnataka, including Casagrand Florella Phase 2 and CASAGRAND VIVACITY. Its filings declare 12 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if CASAGRAND AMOR is delayed beyond 23 Feb 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of CASAGRAND AMOR?

The registered promoter entity is CASA GRANDE GARDEN CITY BUILDERS PVT LTD, a company as per the filing. Its GSTIN 29AAGCC1577R1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in CASAGRAND AMOR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CASAGRAND AMOR?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at CASAGRAND AMOR?

The professionals named in the filing: Architect: P S NAGESH; Engineer: Shivaraj G Naik; Chartered Accountant: NARAYANA RAO M. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CASAGRAND AMOR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CASAGRAND AMOR. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CASAGRAND AMOR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.