Home / Browse projects / Bengaluru Urban, Karnataka / Assetz Canvas & Cove - Phase 1 Wing A & B
Assetz Canvas & Cove - Phase 1 Wing A & B
By APG HABITAT PRIVATE LIMITED
RG-KA-83088 · RERA PRM/KA/RERA/1251/310/PR/251023/006347 · Last updated on RERA Karnataka portal: 14 Oct 2026
Source: official RERA Karnataka filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Assetz Canvas & Cove - Phase 1 Wing A & B is a Residential/Group Housing project by APG HABITAT PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/251023/006347 on 25 Oct 2023. Possession is promised by 30 Apr 2027. 272 of the 273 units on this registration are recorded sold or booked, and 17 of 18 construction stages are filed complete.
At a glance
Project
- NameAssetz Canvas & Cove - Phase 1 Wing A & B
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560068
- Pincode560068
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/251023/006347
- ReraGenie IDRG-KA-83088
Builder
- NameAPG HABITAT PRIVATE LIMITED
- Entity typeCompany
- CINU70109KA2016PTC093453
- GSTIN29AAOCA4442R1ZV
- Authorized SignatorySomasundaram Thiruppathi
- CeoAkshay Kishore Dewani
- DirectorsSomasundaram Thiruppathi, Jagannath Laxman Shetty
- Project HeadGurumoorthy N
- Other registrations3 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on25 Oct 2023
- Promised completion30 Apr 2027
- Revised completionNone
- Buildings2 building records
- Documents filed188 files
Current status
Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING A | - | - | - | 140 | 0 | 140 |
| WING B | - | - | - | 133 | 0 | 133 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
17 of 18 construction stages are filed complete. The stage furthest along is Internal and External work including landscapes as per..., at 85%.
Building: 99% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 100% |
| Upto Plinth Level | 100% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 100% |
| Retaining wall (All types) | 100% |
| RCC or MS Framed structure | 100% |
| Masonry Construction | 100% |
| Plastering inside , outside & Ceiling | 100% |
| Joinery: Doors, Windows, Ventilators etc | 100% |
| Basic work of Water supply, Sanitary and Electrification | 100% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 100% |
| Railing and Grill fixing | 100% |
| Electrification, Water supply and Sanitary Finishing | 100% |
| Painting | 100% |
| Fire prevention and fire fighting fitting and fixture with network | 100% |
| Weather Proof work(tile,concrete) | 100% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 100% |
| Internal and External work including landscapes as per sanctioned drawings | 85% |
Progress on shared amenities40
As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 100% |
| Sewage and Drainage System | Yes | 100% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 100% |
| Energy management | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Solid waste management and disposal | Yes | 100% |
| Emergency Evacuation services | Yes | 100% |
| Internal Roads & Footpaths | Yes | 95% |
| Electricity supply transformer and substation | Yes | 100% |
| Storm water drains | Yes | 95% |
| Use of renewable energy | Yes | 95% |
| Sewage Treatment Plant (STP) | Yes | 95% |
| Parks & Tree planting | Yes | 90% |
| Street Lighting | Yes | 90% |
| Electricity | Yes | 100% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 85% |
| Club House | Yes | 100% |
| Community Hall | Yes | 80% |
| Outdoor Sports facility | Yes | 100% |
| Indoor Sports facility | Yes | 100% |
| Swimming Pool | Yes | 100% |
| Gym | Yes | 100% |
| Parks | Yes | 98% |
| Power Backup | Yes | 100% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 100% |
| Air Conditioning | Yes | 100% |
| Staircases | Yes | 100% |
| Lifts | Yes | 100% |
| Corridor/Lobbies | Yes | 100% |
| Fire escapes | Yes | 100% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 100% |
| Basement | Yes | 100% |
| Terrace | Yes | 100% |
| Outer Wall | Yes | 100% |
| Open parking areas | Yes | 90% |
| Provision for lodging of management staff and security staff | No | Not applicable |
| Water conservation and renewable energy | Yes | 100% |
| Common storage spaces | Yes | 100% |
Land and ownership10
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Savithramma | - | - |
| Pradeep Krishnappa | - | - |
| Pankaja M S | - | - |
| Vijay | - | - |
| Pradeep Krishnappa | - | - |
| Pradeep Krishnappa | - | - |
| Raju | - | - |
| N Arun Kumar | - | - |
| Savithramma | - | - |
| Pradeep Krishnappa | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 104.25 cr | Rs 85.06 cr |
| Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC) | Rs 16.71 cr | Rs 17.03 cr |
| On-site expenditure-Site Overhead | Rs 12.30 cr | Rs 11.23 cr |
| Approval Cost | Rs 5.51 cr | Rs 3.86 cr |
| On-site expenditure-Consultants Fees | Rs 1.40 cr | Rs 1.93 cr |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Kishore Panikkar |
| Engineer | B E Pruthviraja |
| Chartered Accountant | Y S Shetty & Company |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed188
As listed on the registration, under the names the promoter filed them with; the newest 80 of 188 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/251023/006347 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 CA - Canvas & Cove Ph 1 A&B.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove Block A & B.pdf | 14 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) - Canvas & Cove A&B.pdf | 14 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 14 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 14 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 14 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 14 Oct 2026 |
| Q2 2026-27 Fire and Safety | 14 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 14 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 14 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove A&B.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove Block A & B.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) - Canvas & Cove A&B.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove A&B.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove A & B.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer (QU) - Canvas & Cove A&B.pdf | 15 Apr 2026 |
| Q4 2025-26 Water supply and sewage board | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 15 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 15 Apr 2026 |
| Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Accountant - canvas & Cove A&B.pdf | 11 Mar 2026 |
| Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect (QU) Canvas & Cove A & B.pdf | 11 Mar 2026 |
| Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Engineer Certificate Assetz Canvas & Cove Ph 1 wing A& B.pdf | 11 Mar 2026 |
| Q3 2025-26 Water supply and sewage board | 11 Mar 2026 |
| Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 11 Mar 2026 |
| Q3 2025-26 KSPCB- MOEF (Above 50 Acres) | 11 Mar 2026 |
| Q3 2025-26 KPTCL- BESCOM | 11 Mar 2026 |
| Q3 2025-26 Fire and Safety | 11 Mar 2026 |
| Q3 2025-26 Airport Authority of India | 11 Mar 2026 |
| Q3 2025-26 BSNL/Telecommunication Department | 11 Mar 2026 |
| EC obtained from sub-registrar for the period from 1-4-2007 to till date for all sno of the projectFile: Annexure 1-EC.pdf | 18 Oct 2023 |
| title deed in favour of savithramma & pradeep krishna for s no 149/1File: Annexure 2-Clarification Regarding sy no 149-1.pdf | 18 Oct 2023 |
| title deed in favour of savithramma & pradeep krishna for s no 150File: Annexure 3-Clarification regarding sy no 150.pdf | 18 Oct 2023 |
| Notarized non litigation affidavitFile: Annexure 4-Non -Litigation affidavit.pdf | 18 Oct 2023 |
| Notarized form -B affidavitFile: Annexure 5-Form B.pdf | 18 Oct 2023 |
| Notarized JA cum DECLARATIONFile: Annexure 6-JA Affidavit.pdf | 18 Oct 2023 |
| Affidavit of ViolationFile: Annexure 7-Affidavit of Violation.pdf | 18 Oct 2023 |
| all sanctioned drawings Floor plans, sectional drawings and elevations.(No signature digital signatFile: Annexure 8-Site Plan and all Floor Plan.pdf | 18 Oct 2023 |
| Carpet Area CalculationFile: Annexure 9-Carpet Area Calculation.pdf | 18 Oct 2023 |
| Architect CertificateFile: Annexure 10 - Kishore COA Certificate.pdf | 18 Oct 2023 |
| Covering LetterFile: Covering Letter.pdf | 12 Oct 2023 |
| Bank Statement of 100File: Annexure 1-Bank Statement 100 account.pdf | 12 Oct 2023 |
| Bank Statement of 70File: Annexure 2-Bank Statement 70 account.pdf | 12 Oct 2023 |
| Bank Statement of 30File: Annexure 3-Bank Statemnet 30 Account.pdf | 12 Oct 2023 |
| profit & Loss account and balance sheet 2019-20File: Annexure 4-BS and P & L 2019-20.pdf | 12 Oct 2023 |
| profit & Loss account and balance sheet 2020-21File: Annexure 5-BS and P & L 2020-21.pdf | 12 Oct 2023 |
| profit & Loss account and balance sheet 2021-22File: Annexure 6-BS and P & L 2021-22.pdf | 12 Oct 2023 |
| Chartered accountant certificateFile: Annexure 8-CA Certificate Form 1.pdf | 12 Oct 2023 |
| Encumbrance CertificateFile: Annexure 10-Updated EC.pdf | 12 Oct 2023 |
| title deed in favour of savithramma & pradeep krishna for s no 149/1File: Annexure 11-Clarification Regarding sy no 149-1.pdf | 12 Oct 2023 |
| title deed in favour of savithramma & pradeep krishna for s no 149/1File: Annexure 12-Clarification regarding sy no 150.pdf | 12 Oct 2023 |
| Katha extract obtained from BBMPFile: Annexure 13- Khata.pdf | 12 Oct 2023 |
| Area details the project detailsFile: Annexure 17-Area Detail clarification.pdf | 12 Oct 2023 |
| Number of parking DetailsFile: Annexure 18-CAR Parking.pdf | 12 Oct 2023 |
| All sanctioned drawings Floor plans, sectional drawings, and elevations.File: Annexure 19-Site plan and All floor Plans.pdf | 12 Oct 2023 |
| KSPCB CFEFile: Annexure 20-KSPCB NOC.pdf | 12 Oct 2023 |
| Certified Carpet area calculationFile: Annexure 21-Architect certificate for Carpet Area.pdf | 12 Oct 2023 |
| CDP map showing the proposed site.File: Annexure 22-CDP Map.pdf | 12 Oct 2023 |
| Village map showing the proposed siteFile: Annexure 23-VILLAGE MAP.pdf | 12 Oct 2023 |
| Commencement certificate.File: Annexure 24- Clarification regarding CC.pdf | 12 Oct 2023 |
| Building License.File: Annexure 25-Building Licence.pdf | 12 Oct 2023 |
| Development Plan OrderFile: Annexure 26-DP Work Order.pdf | 12 Oct 2023 |
| Architects certificate with valid COA numberFile: Annexure 27-Architect Certificate.pdf | 12 Oct 2023 |
| SEIAA NOCFile: Annexure 28-MOEF NOC.pdf | 12 Oct 2023 |
| The Engineer certificateFile: Annexure 30-Engineer Certificate.pdf | 12 Oct 2023 |
| the Certificate from a Registered Engineer indicating the structural safetyFile: Annexure 31-structural safety certificate.pdf | 12 Oct 2023 |
| The renewed BWSSB NOCFile: Annexure 32-BWSSB NOC.pdf | 12 Oct 2023 |
| The fee receipt paid towards BESCOMFile: Annexure 33- Bescom receipt.pdf | 12 Oct 2023 |
| project name and project address and upload the project specification certified by the EngineerFile: Annexure 34-Project Specification.pdf | 12 Oct 2023 |
| The self-attested copy of the EngineerFile: Annexure 35-Self Attested Engineer.pdf | 12 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Assetz Canvas & Cove - Phase 1 Wing A & B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 27 registered projects within 2 km.
MEMCO SKYLINE - JUTAKU
MEMCO SKYLINE PRIVATE LIMITED
SNN RAJ SERENITY
SNN Builders Private Limited
TVS Emerald Jardin
Emerald Haven Development Limited
CASAGRAND AMOR
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
Assetz Mizumi Reserve Tower A1 A2 A4
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
Assetz Canvas & Cove 2.0 - Block B & C
APG HABITAT PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: APG HABITAT PRIVATE LIMITED
APG HABITAT PRIVATE LIMITED has 4 registrations on RERA Karnataka, including Assetz Canvas & Cove 2.0 - Block A and Assetz Canvas & Cove 2.0 - Block B & C. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Assetz Canvas & Cove - Phase 1 Wing A & B is delayed beyond 30 Apr 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Assetz Canvas & Cove - Phase 1 Wing A & B?
The registered promoter entity is APG HABITAT PRIVATE LIMITED, a company as per the filing. Its CIN U70109KA2016PTC093453 and GSTIN 29AAOCA4442R1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Assetz Canvas & Cove - Phase 1 Wing A & B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Assetz Canvas & Cove - Phase 1 Wing A & B?
The professionals named in the filing: Architect: Kishore Panikkar; Engineer: B E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Assetz Canvas & Cove - Phase 1 Wing A & B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.