Assetz Mizumi Reserve Tower A1 A2 A4
By APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
RG-KA-80318 · RERA PRM/KA/RERA/1251/310/PR/040226/008450 · Last updated on RERA Karnataka portal: 15 Oct 2026
Source: official RERA Karnataka filing
Red flags
- Litigation declared, 4 cases
Clear
- No complaints on record
- Completion date never moved
- Separate project account declared
Saved.
Assetz Mizumi Reserve Tower A1 A2 A4 is a Residential/Group Housing project by APG COMMUNITY DEVELOPMENT PRIVATE LIMITED in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/310/PR/040226/008450 on 4 Feb 2026. Possession is promised by 30 Dec 2030. 302 of the 440 units on this registration are recorded sold or booked, and 1 of 18 construction stages are filed complete.
At a glance
Project
- NameAssetz Mizumi Reserve Tower A1 A2 A4
- TypeResidential/Group Housing
- Location
- Bengaluru South
- Bengaluru Urban
- 560068
- Pincode560068
- MapView location on Google Maps (as filed on RERA)
- RERA no.PRM/KA/RERA/1251/310/PR/040226/008450
- ReraGenie IDRG-KA-80318
Builder
- NameAPG COMMUNITY DEVELOPMENT PRIVATE LIMITED
- Entity typeCompany
- CINU45203KA2014PTC077653
- GSTIN29AANCA1479M1ZZ
- Authorized SignatorySanjay Sudhakar Torgal
- CeoAkshay Kishore Dewani
- DirectorsAkshay Kishore Dewani, Sanjay Sudhakar Torgal
- Project HeadGurumurthy N
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistration approved
- Registered on4 Feb 2026
- Promised completion30 Dec 2030
- Revised completionNone
- Buildings3 building records
- Documents filed490 files
Current status
Figures as on 15 Oct 2026, this project's latest RERA Karnataka filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 1 | - | - | - | 176 | 0 | 176 |
| Tower 2 | - | - | - | 176 | 0 | 176 |
| Tower 4 | - | - | - | 88 | 0 | 88 |
The full filing
Everything below is from the project's own RERA Karnataka filing, free to read.
Construction progress by building1
As on 15 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 18 construction stages are filed complete. The stage furthest along is Foundation footing work, at 80%.
Building: 16% average across the applicable activities
| Activity | Progress |
|---|---|
| Earth work and other leveling preparation work | 100% |
| Foundation footing work | 80% |
| Upto Plinth Level | 50% |
| Sub-structure flooring (Parking Floor, more than one floor below general ground level) | 0% |
| Retaining wall (All types) | 50% |
| RCC or MS Framed structure | 5% |
| Masonry Construction | 0% |
| Plastering inside , outside & Ceiling | 0% |
| Joinery: Doors, Windows, Ventilators etc | 0% |
| Basic work of Water supply, Sanitary and Electrification | 0% |
| Dadoing, Skirting, Flooring, Tiles work (All types) | 0% |
| Railing and Grill fixing | 0% |
| Electrification, Water supply and Sanitary Finishing | 0% |
| Painting | 0% |
| Fire prevention and fire fighting fitting and fixture with network | 0% |
| Weather Proof work(tile,concrete) | 0% |
| Wardrobe, Showcase, Kitchen cabinet, Puja work | Not applicable |
| Elevation work | 0% |
| Internal and External work including landscapes as per sanctioned drawings | 0% |
Progress on shared amenities40
As on 15 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Water Supply | Yes | 0% |
| Sewage and Drainage System | Yes | 0% |
| Water conservation/rain water harvesting/recharge of ground water | Yes | 0% |
| Energy management | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Solid waste management and disposal | Yes | 0% |
| Emergency Evacuation services | Yes | 0% |
| Internal Roads & Footpaths | Yes | 0% |
| Electricity supply transformer and substation | Yes | 0% |
| Storm water drains | Yes | 0% |
| Use of renewable energy | Yes | 0% |
| Sewage Treatment Plant (STP) | Yes | 0% |
| Parks & Tree planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Electricity | Yes | 0% |
| Smart Home Automation | No | Not applicable |
| CCTV Surveillance | Yes | 0% |
| Club House | Yes | 0% |
| Community Hall | Yes | 0% |
| Outdoor Sports facility | Yes | 0% |
| Indoor Sports facility | Yes | 0% |
| Swimming Pool | Yes | 0% |
| Gym | Yes | 0% |
| Parks | Yes | 0% |
| Power Backup | Yes | 0% |
| Piped Gas | No | Not applicable |
| Water and Sanitation | Yes | 0% |
| Air Conditioning | Yes | 0% |
| Staircases | Yes | 0% |
| Lifts | Yes | 0% |
| Corridor/Lobbies | Yes | 0% |
| Fire escapes | Yes | 0% |
| Common entrance and exit for the building/common portico/foyer/verandah | Yes | 0% |
| Basement | Yes | 0% |
| Terrace | Yes | 0% |
| Outer Wall | Yes | 0% |
| Open parking areas | Yes | 0% |
| Provision for lodging of management staff and security staff | Yes | 0% |
| Water conservation and renewable energy | Yes | 0% |
| Common storage spaces | No | Not applicable |
Land and ownership26
This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Mrs. Shilpa Rama Ganesh | - | - |
| Mrs. Shilpa Rama Ganesh | - | - |
| Sri. Priya Krishna | - | - |
| Jayamma | - | - |
| Sri. Priya Krishna | - | - |
| Sri. Priya Krishna | - | - |
| Raju | - | - |
| Arun Kumar | - | - |
| Arun Kumar | - | - |
| Arun Kumar | - | - |
| Raju | - | - |
| Sri. PriyaKrishna | - | - |
| Arun Kumar | - | - |
| Sri. Priya Krishna | - | - |
| Arun Kumar | - | - |
| Sri. PriyaKrishna | - | - |
| Pradeep Krishnappa | - | - |
| Sri. Priya Krishna | - | - |
| N. Girish Kumar | - | - |
| Mr. G. R. Byresh | - | - |
| Sri. Ramesh | - | - |
| Sri. Priya Krishna | - | - |
| Sri. Ramesh | - | - |
| Mr Naveen Reddy | - | - |
| Mr. Prathap Reddy | - | - |
| Mr. G. R. Byresh | - | - |
Project account and cost
70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Cost line | Estimated | Incurred |
|---|---|---|
| Estimated Cost of Construction as certified by Engineer | Rs 335.03 cr | Rs 40.55 cr |
| On-site expenditure-Site Overhead | Rs 28.77 cr | Rs 11.95 cr |
| Approval | Rs 27.83 cr | Rs 7.77 cr |
| Principal sum and interest payable to financial institutions-Scheduled Banks | Rs 22.32 cr | Rs 15.93 cr |
| On-site expenditure-Consultants Fees | Rs 7.69 cr | Rs 95.72 lakh |
Certifying professionals and partners3
Certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Sandeep Rajendran |
| Engineer | B E Pruthviraja |
| Chartered Accountant | Y S Shetty & Company |
Litigation declared4
| Case | Court | Status |
|---|---|---|
| O.S. No. 109 of 2006 | Senior Civil Judge, Anekal | - |
| O.S. No. 25577 of 2023 | City Civil Judge, Mayo Hall | - |
| O.S. No. 5489 of 2024 | Principal City Civil & Sessions Judge, Bengaluru | - |
| O.S. NO. 157 OF 2012 | Principal Senior Civil Judge, Anekal | - |
Complaints filed with RERA Karnataka
No complaints on record against this registration.
Documents filed490
As listed on the registration, under the names the promoter filed them with; the newest 80 of 490 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/310/PR/040226/008450 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Oct 2026 |
| Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Oct 2026 |
| Q2 2026-27 Water supply and sewage board | 15 Oct 2026 |
| Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Oct 2026 |
| Q2 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Oct 2026 |
| Q2 2026-27 KPTCL- BESCOM | 15 Oct 2026 |
| Q2 2026-27 Fire and Safety | 15 Oct 2026 |
| Q2 2026-27 Airport Authority of India | 15 Oct 2026 |
| Q2 2026-27 BSNL/Telecommunication Department | 15 Oct 2026 |
| Q2 2026-27 Preventive Order (Injunction / Interim Order / Final Order / Stay OrderFile: Disposal order dated 06 07 2026.pdf | 15 Oct 2026 |
| Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Jul 2026 |
| Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Jul 2026 |
| Q1 2026-27 Water supply and sewage board | 15 Jul 2026 |
| Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres) | 15 Jul 2026 |
| Q1 2026-27 KSPCB- MOEF (Above 50 Acres) | 15 Jul 2026 |
| Q1 2026-27 KPTCL- BESCOM | 15 Jul 2026 |
| Q1 2026-27 Fire and Safety | 15 Jul 2026 |
| Q1 2026-27 Airport Authority of India | 15 Jul 2026 |
| Q1 2026-27 BSNL/Telecommunication Department | 15 Jul 2026 |
| Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form -4 Chartered Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form-5 Architect Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Apr 2026 |
| Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form -6 Engineer Assetz Mizumi Reserve Tower A1 A2 A4.pdf | 15 Apr 2026 |
| Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres) | 15 Apr 2026 |
| Q4 2025-26 KSPCB- MOEF (Above 50 Acres) | 15 Apr 2026 |
| Q4 2025-26 KPTCL- BESCOM | 15 Apr 2026 |
| Q4 2025-26 Fire and Safety | 15 Apr 2026 |
| Q4 2025-26 Airport Authority of India | 15 Apr 2026 |
| Q4 2025-26 BSNL/Telecommunication Department | 15 Apr 2026 |
| Annexure 1-SY 173-1 MutationFile: Annexure 1-SY 173-1 Mutation.pdf | 4 Feb 2026 |
| Annexure 2 -SY 175 MutationFile: Annexure 2 -SY 175 Mutation.pdf | 4 Feb 2026 |
| Annexure 3-SY 176 MutationFile: Annexure 3-SY 176 Mutation.pdf | 4 Feb 2026 |
| Annexure 6-SY 203 MutationFile: Annexure 6-SY 203 Mutation.pdf | 4 Feb 2026 |
| Annexure 7- Sy No 203, MutationFile: Annexure 7- Sy No 203, Mutation.pdf | 4 Feb 2026 |
| Annexure 8- Sy No173-2 MutationFile: Annexure 8- Sy No173-2 Mutation.pdf | 4 Feb 2026 |
| Annexure 9- Sy No 177-1 MutationFile: Annexure 9- Sy No 177-1 Mutation.pdf | 4 Feb 2026 |
| Annexure 11-SY 177-2 Mutation ,File: Annexure 11-SY 177-2 Mutation ,.pdf | 4 Feb 2026 |
| Annexure 12-SY 179-1 MutationFile: Annexure 12-SY 179-1 Mutation.pdf | 4 Feb 2026 |
| Annexure 13-SY 179-2 MutationFile: Annexure 13-SY 179-2 Mutation.pdf | 4 Feb 2026 |
| Annexure 15-SY 180-1 MutationFile: Annexure 15-SY 180-1 Mutation.pdf | 4 Feb 2026 |
| Annexure 17-SY 180-3 MutationFile: Annexure 17-SY 180-3 Mutation.pdf | 4 Feb 2026 |
| Annexure 19-SY 5-4 MutationFile: Annexure 19-SY 5-4 Mutation.pdf | 4 Feb 2026 |
| Annexure 24-SY 7 MutationFile: Annexure 24-SY 7 Mutation.pdf | 4 Feb 2026 |
| Annexure 25 -SY 7 MutationFile: Annexure 25 -SY 7 Mutation.pdf | 4 Feb 2026 |
| Annexure 27 -SY 8-4 MutationFile: Annexure 27 -SY 8-4 Mutation.pdf | 4 Feb 2026 |
| Annexure 28-SY 8-5 MutationFile: Annexure 28-SY 8-5 Mutation.pdf | 4 Feb 2026 |
| JDA_23 Acre Original & AddendumFile: JDA_23 Acre Original & Addendum.pdf | 4 Feb 2026 |
| JDA_Sy No 8-1 Original & AddendumFile: JDA_Sy No 8-1 Original & Addendum.pdf | 4 Feb 2026 |
| JDA_Sy No 8-5 Original & AddendumFile: JDA_Sy No 8-5 Original & Addendum.pdf | 4 Feb 2026 |
| Sy No 8-5 Release DeedFile: Sy No 8-5 Release Deed.pdf | 4 Feb 2026 |
| Sale Deed and Gift Deed -Sy No 175File: Sale Deed and Gift Deed -Sy No 175.pdf | 4 Feb 2026 |
| BrochureFile: Updated Brochure.pdf | 4 Feb 2026 |
| SpecificationsFile: Updated Specifications.pdf | 4 Feb 2026 |
| Dimarcation and Area StatementFile: Dimarcation and Area Statement.pdf | 4 Feb 2026 |
| Annexure 4A-RTC- Sy no 5-4File: Annexure 4A-RTC- Sy no 5-4.pdf | 4 Feb 2026 |
| Annexure 4B-RTC-Sy no 5-5File: Annexure 4B-RTC-Sy no 5-5.pdf | 4 Feb 2026 |
| Annexure 4C-RTC Sy no 173-1File: Annexure 4C-RTC Sy no 173-1.pdf | 4 Feb 2026 |
| Annexure 4E-RTC- Sy no 175File: Annexure 4E-RTC- Sy no 175.pdf | 4 Feb 2026 |
| Annexure 4F-RTC- Sy no 176File: Annexure 4F-RTC- Sy no 176.pdf | 4 Feb 2026 |
| Annexure 4G-RTC- Sy no 177-1File: Annexure 4G-RTC- Sy no 177-1.pdf | 4 Feb 2026 |
| Annexure 4H-RTC- Sy no 177-2File: Annexure 4H-RTC- Sy no 177-2.pdf | 4 Feb 2026 |
| Annexure 4I-RTC- Sy no 178File: Annexure 4I-RTC- Sy no 178.pdf | 4 Feb 2026 |
| Annexure 4J-RTC- Sy no 179-1File: Annexure 4J-RTC- Sy no 179-1.pdf | 4 Feb 2026 |
| Annexure 4L-RTC- Sy no180-1File: Annexure 4L-RTC- Sy no180-1.pdf | 4 Feb 2026 |
| Annexure 4M-RTC- Sy no 180-2File: Annexure 4M-RTC- Sy no 180-2.pdf | 4 Feb 2026 |
| Annexure 4N-RTC- Sy no 180-3File: Annexure 4N-RTC- Sy no 180-3.pdf | 4 Feb 2026 |
| Annexure 4O-RTC- Sy no 187-1File: Annexure 4O-RTC- Sy no 187-1.pdf | 4 Feb 2026 |
| Annexure 4P-RTC- Sy no 203File: Annexure 4P-RTC- Sy no 203.pdf | 4 Feb 2026 |
| Annexure 4Q-RTC- Sy no 5File: Annexure 4Q-RTC- Sy no 5.pdf | 4 Feb 2026 |
| Annexure 4R-RTC- Sy no 6- PAFile: Annexure 4R-RTC- Sy no 6- PA.pdf | 4 Feb 2026 |
| Annexure 4S-RTC- Sy no 7 -PAFile: Annexure 4S-RTC- Sy no 7 -PA.pdf | 4 Feb 2026 |
| Annexure 4T-RTC- Sy no 8-1 PAFile: Annexure 4T-RTC- Sy no 8-1 PA.pdf | 4 Feb 2026 |
| Annexure 4U-RTC- Sy no 8-5File: Annexure 4U-RTC- Sy no 8-5.pdf | 4 Feb 2026 |
| Annexure 4V-RTC- Sy no 8-4File: Annexure 4V-RTC- Sy no 8-4.pdf | 4 Feb 2026 |
| Building LicenceFile: 0-Building Licence.pdf | 3 Feb 2026 |
| Site PlanFile: 1-Site Plan.pdf | 3 Feb 2026 |
| Combined Basement-01st FloorFile: 2-Combined Basement-01st Floor.pdf | 3 Feb 2026 |
| Combined Basement-02nd FloorFile: 3-Combined Basement-02nd Floor.pdf | 3 Feb 2026 |
| Combined Ground Floor PlanFile: 4-Combined Ground Floor Plan.pdf | 3 Feb 2026 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Bengaluru Urban
Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.
Keep Assetz Mizumi Reserve Tower A1 A2 A4 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bengaluru Urban4,100+ in Bengaluru Urban
Filed coordinates, straight-line distance. 20 registered projects within 2 km.
MEMCO SKYLINE - JUTAKU
MEMCO SKYLINE PRIVATE LIMITED
SNN RAJ SERENITY
SNN Builders Private Limited
TVS Emerald Jardin
Emerald Haven Development Limited
CASAGRAND AMOR
CASA GRANDE GARDEN CITY BUILDERS PVT LTD
Assetz Canvas & Cove 2.0 - Block B & C
APG HABITAT PRIVATE LIMITED
Assetz Canvas & Cove - Phase 1 Wing A & B
APG HABITAT PRIVATE LIMITED
See every Bengaluru Urban project, with the district possession charts
Builder: APG COMMUNITY DEVELOPMENT PRIVATE LIMITED
APG COMMUNITY DEVELOPMENT PRIVATE LIMITED has 2 registrations on RERA Karnataka, including Assetz Mizumi Reserve Tower A3 A5 and Assetz Mizumi Reserve Tower A1 A2 A4. Its filings disclose no earlier RERA Karnataka projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Bengaluru Urban district page.
Frequently asked questions
What are my rights if Assetz Mizumi Reserve Tower A1 A2 A4 is delayed beyond 30 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.
How do I verify and contact the developer of Assetz Mizumi Reserve Tower A1 A2 A4?
The registered promoter entity is APG COMMUNITY DEVELOPMENT PRIVATE LIMITED, a company as per the filing. Its CIN U45203KA2014PTC077653 and GSTIN 29AANCA1479M1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.
Is my payment protected in Assetz Mizumi Reserve Tower A1 A2 A4?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
Who certifies construction progress at Assetz Mizumi Reserve Tower A1 A2 A4?
The professionals named in the filing: Architect: Sandeep Rajendran; Engineer: B E Pruthviraja; Chartered Accountant: Y S Shetty & Company. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Assetz Mizumi Reserve Tower A1 A2 A4?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.