ReraGenieLog inGet a buyer report

Home / Browse projects / Dakshina Kannada, Karnataka / SMART CITY

Registration approved No litigation declared Commercial project

SMART CITY

By GREENLAND INFRASTRUCTURE DEVELOPERS

RG-KA-81188 · RERA PRM/KA/RERA/1257/336/PR/090523/005922 · Last updated on RERA Karnataka portal: 4 May 2023

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Jan 2023Possession promisedno revision filed
0Complaints at RERA Karnatakaon this registration
Jump to the 102 documents Report an error

SMART CITY is a Commercial project by GREENLAND INFRASTRUCTURE DEVELOPERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/336/PR/090523/005922 on 9 May 2023. Possession is promised by 6 Jan 2023.

At a glance

Project

  • NameSMART CITY
  • TypeCommercial
  • Location
    • Bantwala
    • Dakshina Kannada
    • 574243
  • Pincode574243
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/336/PR/090523/005922
  • ReraGenie IDRG-KA-81188

Builder

  • NameGREENLAND INFRASTRUCTURE DEVELOPERS
  • Entity typePartnership Firm
  • GSTIN29AATFG3821C1ZC
  • Authorized SignatoryHAMEED G

Key dates

Registered
9 May 2023
Promised
6 Jan 2023

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on9 May 2023
  • Promised completion6 Jan 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed102 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SMART CITY---09898

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 4 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

Building:

ActivityProgress
Earth work and other leveling preparation work-
Foundation footing work-
Upto Plinth Level-
Sub-structure flooring (Parking Floor, more than one floor below general ground level)-
Retaining wall (All types)Not applicable
RCC or MS Framed structure-
Masonry Construction-
Plastering inside , outside & Ceiling-
Joinery: Doors, Windows, Ventilators etc-
Basic work of Water supply, Sanitary and Electrification-
Dadoing, Skirting, Flooring, Tiles work (All types)-
Railing and Grill fixing-
Electrification, Water supply and Sanitary Finishing-
Painting-
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work-
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 4 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes-
Sewage and Drainage SystemYes-
Water conservation/rain water harvesting/recharge of ground waterYes-
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes-
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)NoNot applicable
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes-
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes-
Club HouseNoNot applicable
Community HallNoNot applicable
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymNoNot applicable
ParksNoNot applicable
Power BackupNoNot applicable
Piped GasNoNot applicable
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes-
LiftsYes-
Corridor/LobbiesYes-
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes-
TerraceNoNot applicable
Outer WallNoNot applicable
Open parking areasNoNot applicable
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership2

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,501 sq m
Named landowners2
LandownerVillageDistrict
CHANDRANATH DEVARA BASADI -ADMINISTRATOR MR. D. VINAYA KUMAR--
CHANDRANATH DEVARA BASADI -ADMINISTRATOR MR. D. VINAYA KUMAR--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 4.95 cr
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 4.85 cr-
On-site expenditure-Consultants FeesRs 5.00 lakh-
Payment of taxesRs 4.53 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSAFI UMAR REHMAN
EngineerSAFI UMAR REHMAN
Chartered AccountantV RAGHAVENDRA

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed102

As listed on the registration, under the names the promoter filed them with; the newest 80 of 102 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/336/PR/090523/005922 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
approved sanction planFile: approved sanction plan.pdf4 May 2023
sanctioned floor plan, section & elevation planFile: approved sanction plan.pdf4 May 2023
RTC, survey 430/6B-
Mutation, survey 430/6B-
Encumbrance Certificate, survey 430/6B-
Conversion/Alienation Order, survey 430/6B-
JDA, survey 430/6B-
Khatha, survey 430/6B-
RTC, survey 430/9-
Mutation, survey 430/9-
Encumbrance Certificate, survey 430/9-
Conversion/Alienation Order, survey 430/9-
JDA, survey 430/9-
Khatha, survey 430/9-
Registration CertificateFile: firm regsiatrtion certificate.pdf-
Partnership DeedFile: partnership-amendement 2021.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: form 1_compressed.pdf-
Certificate issued by Architect Form 2File: architect certiifcate.pdf-
Certificate issued by Engineer Form 3File: engineer certificate.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidavit.pdf-
Certificate from Chartered AccountFile: form 1_compressed.pdf-
Balance Sheet 2021 - 2022File: BS with schedule 2022.pdf-
Balance Sheet 2020 - 2021File: BS with schedule 2021.pdf-
Balance Sheet 2019 - 2020File: BS with schedule-2020.pdf-
Audited Profit and Loss Statement 2021 - 2022File: PL 2022.pdf-
Audited Profit and Loss Statement 2020 - 2021File: PL 2021.pdf-
Audited Profit and Loss Statement 2019 - 2020File: PL 2020.pdf-
Cash Flow Statement 2021 - 2022File: IS 2022-23.pdf-
Cash Flow Statement 2020 - 2021File: IS 2021-22.pdf-
Income Tax Return Acknowledgement 2021 - 2022File: ITR 2022-23.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: ITR 2021-22.pdf-
building licence-
Sanction plan-
single layout-
Sanction plan-
Sanction plan-
Sanction plan-
specification-
single layout order-
single layout plan-
stability certiifcate-
search report-
title deed_compressed-
conversion order-
conversion order-
JDA_compressed-
proforma AOS-
proforma allotment letter-
broucher_compressed-
form b_compressed-
afffidavit 3(1)-
jda affidavit-
mescom noc_compressed-
water noc_compressed-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
pollution noc_compressed-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-
Unnamed document-

How this compares with Dakshina Kannada

30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep SMART CITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

Builder: GREENLAND INFRASTRUCTURE DEVELOPERS

GREENLAND INFRASTRUCTURE DEVELOPERS has 1 registration on RERA Karnataka, including SMART CITY. Its filings disclose no earlier RERA Karnataka projects. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if SMART CITY is delayed beyond 6 Jan 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SMART CITY?

The registered promoter entity is GREENLAND INFRASTRUCTURE DEVELOPERS, a partnership firm as per the filing. Its GSTIN 29AATFG3821C1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SMART CITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SMART CITY?

The professionals named in the filing: Architect: SAFI UMAR REHMAN; Engineer: SAFI UMAR REHMAN; Chartered Accountant: V RAGHAVENDRA. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SMART CITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SMART CITY. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SMART CITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.