ReraGenieLog inGet a buyer report

Home / Browse projects / Gandhinagar, Gujarat / SKYDECK 36

Valid until 28 Feb 2026 Residential/Group Housing project

SKYDECK 36

By UNIQUE INFRACON

RG-GJ-36273 · RERA PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12364/EX1/150925/280226 · Last updated on GujRERA portal: 26 Aug 2025

Source: official GujRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • Nothing verified clear yet
Feb 2026Possession promisedmoved 6 months from the original
3 of 9Construction stages donefurthest along: Staircases, 80%
22 of 36Units unsoldnot recorded sold or booked
Jump to the 38 documents Report an error

SKYDECK 36 is a Residential/Group Housing project by UNIQUE INFRACON in Gandhinagar, Gujarat, registered with GujRERA as PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12364/EX1/150925/280226 on 4 Oct 2023. Possession is promised by 28 Feb 2026. The completion date has moved by 6 months from the original filing. 14 of the 36 units on this registration are recorded sold or booked, and 3 of 9 construction stages are filed complete.

At a glance

Project

  • NameSKYDECK 36
  • TypeResidential/Group Housing
  • Location
    • BLOCK / SUR. NO. 414/3
    • F.P.NO. 17/3
    • T.P.S. NO.18 (KUDASAN-RANDESAN-RAYSAN)
    • NR. VRUNDAVAN ELYSIA
    • AT. KUDASAN
    • Gandhinagar
  • PincodeNot stated
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12364/EX1/150925/280226
  • ReraGenie IDRG-GJ-36273

Builder

  • NameUNIQUE INFRACON
  • Entity typePARTNERSHIP FIRM

Key dates

this monthRegisteredOct 2023First promiseAug 2025Revised toFeb 2026

Key facts

Registration and timeline

  • StatusValid until 28 Feb 2026
  • Registered on4 Oct 2023
  • Promised completion28 Feb 2026
  • Revised completionRevised to 28 Feb 2026 (originally 31 Aug 2025)
  • Buildings1 building record
  • Documents filed38 files

Current status

39%14 of 36 units booked
59.4%Of the estimated cost spent so far

Figures as on 26 Aug 2025, this project's latest GujRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A---36036

The full filing

Everything below is from the project's own GujRERA filing, free to read.

Construction progress by building1

As on 26 Aug 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 9 construction stages are filed complete. The stage furthest along is Staircases, at 80%.

A: 71% average across the applicable activities

ActivityProgress
Excavation100%
Podiums (if any)Not applicable
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, internal plaster, floorings, doors and windows within flats75%
Sanitary fittings within the flats45%
Staircases, lift wells and lobbies at each floor level, overhead and underground water tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing70%
Installation of lifts, water pumps, fire fighting fittings, electrical fittings and finishing70%

Progress on shared amenities19

As on 26 Aug 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal roads and footpathsYes0%
Water supplyYes0%
Sewerage (chamber, lines, septic tank, STP)Yes0%
Storm water drainsYes0%
Landscaping and tree plantingYes0%
Street lightingYes0%
Community buildingsNoNot applicable
Treatment and disposal of sewage and sullage waterNoNot applicable
Solid waste management and disposalYes0%
Water conservation, rain water harvestingYes0%
Energy managementNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Fire fightingYes0%
Drinking water facilitiesYes0%
Emergency evacuationYes0%
Use of renewable energyYes0%
SecurityYes0%
Letter boxYes0%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,932 sq m

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountNot declared
Estimated costRs 21.23 cr
Cost incurredRs 12.61 cr
Spent of the estimate59.42%
BuildingWingEstimatedIncurred
ANARs 21.23 crRs 12.61 cr

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPlacekinesis Associates
EngineerJigar G. Shah

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12364/EX1/150925/280226Applied Aug 2025; approved Sep 2025

Documents filed38

As listed on the registration, under the names the promoter filed them with. The files themselves are available at source: search the registration number PR/GJ/GANDHINAGAR/GANDHINAGAR/Others/RAA12364/EX1/150925/280226 on the GujRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Accountant's certificate (Form 3)26 Aug 2025
Engineer's certificate (Form 2)13 Aug 2025
Engineer's certificate annexure13 Aug 2025
Architect's certificate (Form 1)12 Aug 2025
Site photograph, A12 Aug 2025
RERA registration certificate4 Oct 2023
Auditor's report (1 of 3)-
Auditor's report (2 of 3)-
Auditor's report (3 of 3)-
Income tax return (1 of 3)-
Income tax return (2 of 3)-
Income tax return (3 of 3)-
Project specific document-
Directors' report (1 of 3)-
Directors' report (2 of 3)-
Directors' report (3 of 3)-
Commencement certificate-
Approved sanctioned plan-
Approved layout plan-
Agreement-
Land location-
Encumbrance certificate-
Area development document-
Brochure-
Project related document-
Declaration in Form B-
Title clearance certificate-
Title report-
Project photograph-
Audited balance sheet (1 of 3)-
Audited balance sheet (2 of 3)-
Audited balance sheet (3 of 3)-
Audited profit and loss statement (1 of 3)-
Audited profit and loss statement (2 of 3)-
Audited profit and loss statement (3 of 3)-
Cash flow statement (1 of 3)-
Cash flow statement (2 of 3)-
Cash flow statement (3 of 3)-

How this compares with Gandhinagar

39%of this project is bookeddistrict median 53%
16%of Gandhinagar projects moved their completion datethis one moved by 6 months

Computed across the 1,600+ Gandhinagar projects on ReraGenie, from their own filings.

Keep SKYDECK 36 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Gandhinagar1,600+ in Gandhinagar

2 kmSKYDECK 36Other 287Dot size: filed unitsN

Filed coordinates, straight-line distance. 287 registered projects within 2 km.

Builder: UNIQUE INFRACON

UNIQUE INFRACON has 1 registration on GujRERA, including SKYDECK 36. Read the full track record. See more projects on the Gandhinagar district page.

Frequently asked questions

What are my rights if SKYDECK 36 is delayed beyond 28 Feb 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with GujRERA.

How do I verify and contact the developer of SKYDECK 36?

The registered promoter entity is UNIQUE INFRACON, a partnership firm as per the filing. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's GujRERA listing and in its filed documents.

Is my payment protected in SKYDECK 36?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SKYDECK 36?

The professionals named in the filing: Architect: Placekinesis Associates; Engineer: Jigar G. Shah. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SKYDECK 36?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on GujRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SKYDECK 36. Everything on this page comes from what the promoter filed on GujRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SKYDECK 36 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.