Home / Browse projects / Mumbai Suburban, Maharashtra / SKY HEIGHTS PHASE II WING D AND E

Registration lapsed No litigation declared Residential / Group Housing project

SKY HEIGHTS PHASE II WING D AND E

By CRYSTAL CONSTRUCTIONS

RG-MH-58658 · RERA P51800014393 · Last updated on MahaRERA portal: 29 Apr 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
0 of 11Construction stages donefurthest along: Excavation, 50%
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

SKY HEIGHTS PHASE II WING D AND E is a Residential / Group Housing project by CRYSTAL CONSTRUCTIONS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800014393 on 29 Nov 2017. Possession was promised by 29 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSKY HEIGHTS PHASE II WING D AND E
  • TypeResidential / Group Housing
  • Location
    • Suhasani Pawaskar Marg
    • Dahisar
    • Borivali
    • Mumbai Suburban
    • 400068
  • Pincode400068
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800014393
  • ReraGenie IDRG-MH-58658

Builder

  • NameCRYSTAL CONSTRUCTIONS
  • Entity typePartnership
  • PartnerHILAL MERCHANT
  • Other registrations2 more →
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects9 →

Key dates

34 months past promisethis monthRegisteredNov 2017First promiseDec 2022Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on29 Nov 2017
  • Promised completion29 Dec 2023
  • Revised completionRevised to 29 Dec 2023 (originally 30 Dec 2022)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SKY HEIGHTS PHASE II WING D AND ENA260000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Apr 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 50%.

SKY HEIGHTS PHASE II WING D AND E: 43% average across the applicable activities

ActivityProgress
Excavation50%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor50%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises48%
Sanitary Fittings within the flats / premises48%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks48%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.48%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.48%

Progress on shared amenities15

As on 29 Apr 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes48%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes48%
Storm Water DrainsYes48%
Landscaping & Tree PlantingYes48%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes48%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes48%
Electrical meter room, sub-station, receiving stationYes48%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed260

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots260
Closed/Covered260

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,593 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI22502.66
Proposed, not sanctioned11,242 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchANDHERI EAST

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectTEEARCH
EngineerJW CONSULTANTS LLP
PartnerRole in project
CRYSTAL CONSTRUCTIONS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800013399Dec 2022 → Dec 2023

Reason as filed by the promoterTHE PROMOTER HAS ALREADY APPLIED FOR OC ON 27/09/2022 AND THE SAME IS BEING AWAITED COPY OF WHICH IS ATTACHED AS UNDER IN SR NO 2

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Nov 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Nov 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Mar 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Apr 2023

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCPhase2.pdf29 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2019 P2.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Mar 20 P2.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Mar 21 P2.pdf16 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 2 Certificates of CA (Form 5).pdf16 Feb 2023
Certificates of CA (Form 5)File: FORM 5.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A Dahisar.pdf13 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold booked Inventory.pdf13 Jan 2023
Certificates of CA (Form 3)File: Form 3.pdf13 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sky Heights Phase 2 Form 1 Mar 22.pdf30 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CSH P2 Form 2 Mar 22.pdf30 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1Phase2Sep21.pdf14 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2Phase2Sep21.pdf14 Oct 2021
Certificates of CA (Form 3)File: Form3Phase2Sep21.pdf14 Oct 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1P2Jun21.pdf14 Aug 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form2P2Jun21.pdf14 Aug 2021
Certificates of CA (Form 3)File: form3phase2jun21.pdf14 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: CC15Floor.pdf12 Apr 2021
Building plan approvalFile: DrawingD.pdf30 Mar 2021
Building Plan Approval (IOD)File: DrawingD.pdf30 Mar 2021
Building plan approvalFile: Amendletter.pdf18 Feb 2021
Building Plan Approval (IOD)File: Amendletter.pdf18 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: FURTHERCC.pdf18 Feb 2021
Commencement Certificates / NA Order for plotted developmentFile: FURTHERCC.pdf18 Jul 2020
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng_PII_March_2018.pdf20 Aug 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng_PII_June_2018.pdf20 Aug 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng_PII_Sep_2018.pdf20 Aug 2019
Certificates of CA (Form 3)File: CA_PII_March_2018.pdf20 Aug 2019
Certificates of CA (Form 3)File: CA_PII_June_2018.pdf20 Aug 2019
Certificates of CA (Form 3)File: CA_PII_Sep_2018.pdf20 Aug 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng_PII_Dec_2018.pdf17 Aug 2019
Certificates of CA (Form 3)File: CA_PII_Dec_2018.pdf17 Aug 2019
Certificates of CA (Form 5)File: CRYSTAL CONSTRUCTION.pdf14 Nov 2018
Certificates of CA (Form 3)File: CRESCENT SKY HEIGHTS PHASE 2 CA CERTIFICATE.pdf21 Aug 2018
Building plan approvalFile: IOD Remark.pdf14 Nov 2017
Building plan approvalFile: Amended IOD.pdf14 Nov 2017
Layout approvalFile: layout.pdf14 Nov 2017
Layout approvalFile: Declaration Layout Approval.pdf14 Nov 2017
Copy of the legal title reportFile: Title Certificate.pdf14 Nov 2017
Copy of the legal title reportFile: Index II.pdf14 Nov 2017
Copy of the legal title reportFile: 712 Extract.pdf14 Nov 2017
Details of encumbrancesFile: Declaration of No-Encumbrances.pdf14 Nov 2017
Copy of Layout Approval (in case of layout)File: layout.pdf14 Nov 2017
Copy of Layout Approval (in case of layout)File: Declaration Layout Approval.pdf14 Nov 2017
Building Plan Approval (IOD)File: IOD Remark.pdf14 Nov 2017
Building Plan Approval (IOD)File: Amended IOD.pdf14 Nov 2017
Commencement Certificates / NA Order for plotted developmentFile: CC 29417.pdf14 Nov 2017
Declaration in FORM BFile: FORM B Affidavit cum Declaration.pdf14 Nov 2017
Certificates of CA (Form 3)File: Crystal Letter CA DE.pdf14 Nov 2017
Proforma of Allotment letterFile: Allotment Letter.pdf14 Nov 2017
Proforma of Allotment letterFile: Agreement for sale.pdf14 Nov 2017
OtherFile: PRC.pdf14 Nov 2017
OtherFile: Disclaimer Sky Heights.pdf14 Nov 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SKY HEIGHTS PHASE II WING D AND E on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dahisar6,700+ in Mumbai Suburban

2 kmSKY HEIGHTS PHASE II WINCompleted 30Lapsed / revoked 22Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 113 registered projects within 2 km.

Builder: CRYSTAL CONSTRUCTIONS

CRYSTAL CONSTRUCTIONS has 3 registrations on MahaRERA, including SKY HEIGHTS and CRYSTAL HEIGHTS. Its filings disclose 9 earlier MahaRERA projects: declares 9 of 9 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that SKY HEIGHTS PHASE II WING D AND E shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SKY HEIGHTS PHASE II WING D AND E is delayed beyond 29 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SKY HEIGHTS PHASE II WING D AND E?

The registered promoter entity is CRYSTAL CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SKY HEIGHTS PHASE II WING D AND E?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SKY HEIGHTS PHASE II WING D AND E?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SKY HEIGHTS PHASE II WING D AND E?

The professionals named in the filing: Architect: TEEARCH; Engineer: JW CONSULTANTS LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SKY HEIGHTS PHASE II WING D AND E?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SKY HEIGHTS PHASE II WING D AND E. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SKY HEIGHTS PHASE II WING D AND E to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.