Home / Browse projects / Bengaluru Rural, Karnataka / SJ PARK VILLE

Registration approved No litigation declared Residential/Group Housing project

SJ PARK VILLE

By SJ CONSTRUCTIONS

RG-KA-04524 · RERA PRM/KA/RERA/1250/304/PR/240326/008547 · Last updated on RERA Karnataka portal: 14 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2029Possession promisedno revision filed
1 of 15Construction stages donefurthest along: Earth work and other leveling..., 90%
107 of 118Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 153 documents Report an error

SJ PARK VILLE is a Residential/Group Housing project by SJ CONSTRUCTIONS in Bengaluru Rural, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1250/304/PR/240326/008547 on 24 Mar 2026. Possession is promised by 31 Dec 2029. 11 of the 118 units on this registration are recorded sold or booked, and 1 of 15 construction stages are filed complete.

At a glance

Project

  • NameSJ PARK VILLE
  • TypeResidential/Group Housing
  • Location
    • Hosakote
    • Bengaluru Rural
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1250/304/PR/240326/008547
  • ReraGenie IDRG-KA-04524

Builder

  • NameSJ CONSTRUCTIONS
  • Entity typePartnership Firm
  • GSTIN29ADCFS7935H1ZM
  • Authorized SignatoryKORLAPATI SURESH
  • Other registrations3 more →
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2026PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on24 Mar 2026
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings10 building records
  • Documents filed153 files

Current status

9%11 of 118 units booked
20.5%Of the estimated cost spent so far

Figures as on 14 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Block A---707
Block B---16016
Block C---16016
Block D---13013
Block E---404
Block F---808
Block G---808
Block H---30030
Block I---15015
CLUB HOUSE---101

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 14 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 15 construction stages are filed complete. The stage furthest along is Earth work and other leveling preparation work, at 90%.

Building: 30% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work90%
Foundation footing work45%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)45%
Retaining wall (All types)Not applicable
RCC or MS Framed structure25%
Masonry Construction25%
Plastering inside , outside & Ceiling45%
Joinery: Doors, Windows, Ventilators etc45%
Basic work of Water supply, Sanitary and Electrification0%
Dadoing, Skirting, Flooring, Tiles work (All types)0%
Railing and Grill fixing0%
Electrification, Water supply and Sanitary Finishing25%
Painting0%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work0%
Internal and External work including landscapes as per sanctioned drawings0%

Progress on shared amenities40

As on 14 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes25%
Sewage and Drainage SystemYes45%
Water conservation/rain water harvesting/recharge of ground waterYes25%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsYes0%
Electricity supply transformer and substationYes0%
Storm water drainsYes25%
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes45%
Parks & Tree plantingYes0%
Street LightingYes0%
ElectricityYes0%
Smart Home AutomationNoNot applicable
CCTV SurveillanceNoNot applicable
Club HouseYes0%
Community HallYes0%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityYes0%
Swimming PoolYes0%
GymYes0%
ParksYes0%
Power BackupYes0%
Piped GasNoNot applicable
Water and SanitationYes0%
Air ConditioningNoNot applicable
StaircasesYes10%
LiftsNoNot applicable
Corridor/LobbiesNoNot applicable
Fire escapesNoNot applicable
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementNoNot applicable
TerraceYes0%
Outer WallYes15%
Open parking areasYes0%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership5

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Named landowners5
LandownerVillageDistrict
Padma N--
Lakshmi P--
Akash M--
Akshay M--
H Rajini Vishwanatha Reddy--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 129.63 cr
Cost incurredRs 26.58 cr
Spent of the estimate20.5%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 105.63 crRs 23.04 cr
Payment of taxesRs 13.00 crRs 89.91 lakh
On-site expenditure-Site OverheadRs 5.00 crRs 1.56 cr
Principal sum and interest payable to financial institutions-Scheduled BanksRs 5.00 crRs 86.59 lakh
On-site expenditure-Consultants FeesRs 1.00 crRs 21.00 lakh

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectB V Narendranath Reddy
EngineerRAJPUROHIT KARANSINGH PRABHUSINGH
Chartered AccountantPAYYAVULA SRIKANTH

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed153

As listed on the registration, under the names the promoter filed them with; the newest 80 of 153 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1250/304/PR/240326/008547 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q2 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 Final_compressed.pdf14 Oct 2026
Q2 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5.pdf14 Oct 2026
Q2 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6.pdf14 Oct 2026
Q2 2026-27 Water supply and sewage board14 Oct 2026
Q2 2026-27 KSPCB- PCB (10 Acres to 125 Acres)14 Oct 2026
Q2 2026-27 KPTCL- BESCOM14 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf15 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form -5, Ar.pdf15 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form -6, Engineer.pdf15 Jul 2026
Q1 2026-27 Water supply and sewage board15 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)15 Jul 2026
Q1 2026-27 KPTCL- BESCOM15 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6.pdf15 Apr 2026
Q4 2025-26 Water supply and sewage board15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
authenticated copy of connected MR showing flow of titles in favour of landowner before conversion iFile: MR merged.pdf17 Mar 2026
podi MR from 32 to 32/2File: Podi 32 to 32-2.pdf17 Mar 2026
Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: Full Plan_compressed.pdf17 Mar 2026
Approval/NOC under section 14 of the KTCP Act from competent AuthorityFile: CLU-KTCP NOC.pdf17 Mar 2026
Kindly upload SEIAA NOCFile: SEIAA NOC.pdf17 Mar 2026
Kindly upload the STP drawing with engineer signatureFile: STP with engineer sign.pdf17 Mar 2026
Kindly upload th estimate duly signed by engineer only along with engineer licence.File: Brief estimated cost certified by engineer_compressed.pdf17 Mar 2026
kindly upload land cost calculation sheet as per guidance certificatFile: Land Cost Calculation Sheet Declaration and Guidance Value.pdf17 Mar 2026
CDP Map Showing Proposed SiteFile: CDP Map showing proposed site.pdf17 Mar 2026
Authenticated copy of current year RTCFile: RTC merged.pdf6 Mar 2026
authenticated copy of connected MR showing flow of titles in favour of landowner before conversion iFile: MR 32-2.pdf6 Mar 2026
title deed of the current landowner as per latest transaction of rajni vishwanath reddyFile: Rajini Vishwanath reddy title doc.pdf6 Mar 2026
JDA between land owner and promoter in sr no 43/2File: Vishwanath reddy JDA 43-2_compressed.pdf6 Mar 2026
Authenticated Defect free EC from 1-4-2011 to till date in all sr nos.File: EC merged.pdf6 Mar 2026
ADLR Certified survey sketch Certifying the Boundary of the Proposed land-Original survey sketchFile: ADLR Sketch.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block A_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block B_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block C_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block D_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block E_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block F_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block G_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block H_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Block I_compressed.pdf6 Mar 2026
Upload all original sanctioned drawings, floor plan, sectional drawings and elevationsFile: Club House.pdf6 Mar 2026
Upload commencement certificateFile: Commencement Certificate.pdf6 Mar 2026
Demarcation of proposed land in Approved Master plan Certified by the competent authorityFile: Full Plan_compressed.pdf6 Mar 2026
Demarcation of proposed land in original Village map certified by the competent authority.File: Village map.pdf6 Mar 2026
Approval/NOC under section 14 of the KTCP Act from competent AuthorityFile: KSPCB NOC.pdf6 Mar 2026
Details of facilities provided thereof including fire fighting facilities, drinking water facilitiesFile: Declaration for facilities like fire fighting, drinking water, emergency services and rene6 Mar 2026
Latitude and Longitude of the proposed project does not match with the project location.File: Latitude and Longitude with image.PNG6 Mar 2026
Date of approval in uploaded engineer licence is not visible,kindly upload clear visible licenceFile: Final Engineer License.pdf6 Mar 2026
Upload the Form -6 Engineer certificate instead of Form-3, since the project is ongoing projectFile: SJ Villa Form 6.pdf6 Mar 2026
Kindly upload elaborated structural stability certificateFile: Stability Certificate with plan.pdf6 Mar 2026
Kindly upload AFS by including all the clauses as per RERA proforma only as per the prescribed standFile: Proforma for Agreement of Sale.pdf6 Mar 2026
Kindly upload Proforma Allotment letter as per the standard prescribed format available in RERA porFile: Proforma of Allotment Letter.pdf6 Mar 2026
Kindly upload SEIAA NOC.File: SEIAA NOC PARK VILLE.pdf6 Mar 2026
Kindly upload project estimate duly signed engineer whose having valid licence.File: Project Estimates certified by Architect_compressed.pdf6 Mar 2026
Kindly upload the STP drawing certified by the Engineer as per the guidelines.File: STP DRAWING.pdf6 Mar 2026
Kindly upload the Land cost calculation sheet as per the guidance value(Self-attested copy) along wiFile: Self attested land cost calculation.pdf6 Mar 2026
Kindly clarify the main source of water supply to the project along with the supporting documents aFile: Declaration for Source of water.pdf6 Mar 2026
Kindly clarify the main source of water supply to the project along with the supporting documents aFile: Water NOC.pdf6 Mar 2026
Kindly clarify the main source of water supply to the project along with the supporting documents aFile: Borewell 1.jpeg6 Mar 2026
Kindly clarify the main source of water supply to the project along with the supporting documents aFile: Borewell 2.jpeg6 Mar 2026
Kindly clarify the main source of water supply to the project along with the supporting documents aFile: Borewell 3.jpeg6 Mar 2026
Kindly clarify the main source of water supply to the project along with the supporting documents aFile: Borewell 4.jpeg6 Mar 2026
RTC, survey 32/2-
Mutation, survey 32/2-
Encumbrance Certificate, survey 32/2-
Conversion/Alienation Order, survey 32/2-
Sale/Title/Gift Deed, survey 32/2-
JDA, survey 32/2-
Khatha, survey 32/2-
RTC, survey 42/1-
Mutation, survey 42/1-
Encumbrance Certificate, survey 42/1-
Conversion/Alienation Order, survey 42/1-
Sale/Title/Gift Deed, survey 42/1-
JDA, survey 42/1-
Khatha, survey 42/1-
RTC, survey 42/3-
Mutation, survey 42/3-

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
SJ TRILLIUMSy No. 71/7, Near Anjaneya Temple, Varthur Village, Varthur HobliCompleted-No date filed
SJ PINNACLESy No. 5/4, 5/7, 5/8, Katha No. 2882, Varthuru Village, BangaloreCompleted-No date filed
East BreezeSy No. 164/2, 164/5, 164/6, 164/7, 164/8, 164/9, Hagadur, Whitefield, Immadihalli Main RoadCompleted-No date filed

How this compares with Bengaluru Rural

9%of this project is bookeddistrict median 45%
20%of Bengaluru Rural projects moved their completion datethis one has not
0%of Bengaluru Rural registrations are shown as withdrawn or revokedthis one is not

Computed across the 650+ Bengaluru Rural projects on ReraGenie, from their own filings.

Keep SJ PARK VILLE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Rural650+ in Bengaluru Rural

Builder: SJ CONSTRUCTIONS

SJ CONSTRUCTIONS has 4 registrations on RERA Karnataka, including SJ PARK VILLE and SJ CLASSIQUE. Its filings declare 4 earlier projects, 3 of them declared completed. Read the full track record. See more projects on the Bengaluru Rural district page.

Frequently asked questions

What are my rights if SJ PARK VILLE is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SJ PARK VILLE?

The registered promoter entity is SJ CONSTRUCTIONS, a partnership firm as per the filing. Its GSTIN 29ADCFS7935H1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SJ PARK VILLE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at SJ PARK VILLE?

The professionals named in the filing: Architect: B V Narendranath Reddy; Engineer: RAJPUROHIT KARANSINGH PRABHUSINGH; Chartered Accountant: PAYYAVULA SRIKANTH. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SJ PARK VILLE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SJ PARK VILLE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SJ PARK VILLE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.