ReraGenieLog inGet a buyer report

Home / Browse projects / Bengaluru Urban, Karnataka / SIPANI ROYAL HERITAGE PHASE-II

Registration approved No litigation declared Residential/Group Housing project

SIPANI ROYAL HERITAGE PHASE-II

By SIPANI PROPERTIES PVT LTD

RG-KA-58118 · RERA PRM/KA/RERA/1251/308/PR/180519/001752 · Last updated on RERA Karnataka portal: 15 Apr 2026

Source: official RERA Karnataka filing

Red flags

  • 1 complaint at RERA Karnataka
  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Jun 2026Possession promisedmoved 42 months from the original
6 of 17Construction stages donefurthest along: Internal and External work including..., 95%
224 of 224Units unsoldnot recorded sold or booked
1Complaints at RERA Karnatakaon this registration
Jump to the 83 documents Report an error

SIPANI ROYAL HERITAGE PHASE-II is a Residential/Group Housing project by SIPANI PROPERTIES PVT LTD in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180519/001752 on 19 May 2018. Possession is promised by 30 Jun 2026. The completion date has moved by 42 months from the original filing. 0 of the 224 units on this registration are recorded sold or booked, and 6 of 17 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSIPANI ROYAL HERITAGE PHASE-II
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180519/001752
  • ReraGenie IDRG-KA-58118

Builder

  • NameSIPANI PROPERTIES PVT LTD
  • Entity typeCompany
  • CINU70102KA1997PTC023041
  • Authorized SignatoryMADHAVA MURTHY M N
  • DirectorsR K SIPANI, RAMESH SIPANI, DINESH SIPANI
  • Other registrations6 more →
  • Declared earlier projects10 →

Key dates

this monthRegisteredMay 2018First promiseDec 2022Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on19 May 2018
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2022)
  • Buildings4 building records
  • Documents filed83 files

Current status

0%0 of 224 units booked
15.4%Of the estimated cost spent so far

Figures as on 15 Apr 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
K---56056
L---56056
M---56056
N---56056

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 15 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 17 construction stages are filed complete. The stage furthest along is Internal and External work including landscapes as per..., at 95%.

Building: 93% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure100%
Masonry construction: Bricks, Concrete blocks etc92%
Plastering inside , outside & Ceiling92%
Joinery: Doors, Windows, Ventilators etc85%
Basic work of Water supply, Sanitary and Electrification90%
Dadoing, Skirting, Flooring, Tiles work (All types)85%
Railing and Grill fixing83%
Electrification, Water supply and Sanitary Finishing92%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network90%
Weather Proof work(tile,concrete)89%
Painting80%
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings95%

Progress on shared amenities43

As on 15 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes99%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes99%
Street LightingYes99%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes0%
Fire protection and fire safety requirementsYes95%
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes96%
Emergency Evacuation servicesYes95%
Storm water drainsYes99%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes99%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes96%
Club HouseYes100%
Community HallYes99%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes99%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes100%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
CHILDERN PAY AREAYes100%
SERENE FOUNTAIN BODYYes100%
StaircasesYes99%
LiftsYes85%
Staircases and Lift lobbies, corridor,lobbies, corridorYes96%
Fire escapesYes96%
Common entrance and exit for the building / common portico/foyer/verandahYes97%
BasementYes100%
TerraceYes95%
Outer WallYes100%
Open parking areas and common storage spacesYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,298 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 46.72 cr
Cost incurredRs 7.19 cr
Spent of the estimate15.39%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 35.74 crRs 7.02 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 7.40 crRs 6.26 lakh
On-site expenditure-Salaries of workersRs 1.93 crRs 6.20 lakh
On-site expenditure-Consultants FeesRs 68.00 lakh-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 48.00 lakhRs 2.04 lakh
On-site expenditure-Site OverheadRs 36.00 lakhRs 2.14 lakh
Payment of taxesRs 9.00 lakh-
Payment of chargesRs 2.50 lakh-
Payment of feesRs 1.50 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVERNEKAR ASSOCIATES pvt ltd
EngineerVENKATESH BABU REDDY

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionDec 2022 → Sep 2023

No reason recorded in the filing

EX/PRM/KA/RERA/1251/308/PR/231031/001752Sep 2023 → Sep 2024

Reason as filed by the promoterothers

ExtensionSep 2024 → Jun 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka1

Case no.ComplainantRespondentFiled
CMP/200624/0006069-SIPANI PROPERTIES PVT LTD24/06/2020

Documents filed83

As listed on the registration, under the names the promoter filed them with; the newest 80 of 83 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180519/001752 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - SRH Ph2 31-3-26 FY2025-26.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 - SRH PH-2 ARCHITCT 31-3-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineers certificate SRH -2 -QU 31-3-26.pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q4 2025-26 Registration documentFile: DOD SRH phase1 -2 Regd Doc bk-1-504 of 24-25 dt 8-4-2024_compressed.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: RERA Form 4 - SRH Ph2 Q3 FY2025-26.pdf14 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form05 Architect SRH-2 Q3 25-26.pdf14 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 srh-2 Q3 Engineer certificate.pdf14 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)14 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)14 Jan 2026
Q3 2025-26 KPTCL- BESCOM14 Jan 2026
Q3 2025-26 Fire and Safety14 Jan 2026
Q3 2025-26 Airport Authority of India14 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department14 Jan 2026
Q3 2025-26 Registration documentFile: DOD SRH phase1 -2 Regd Doc bk-1-504 of 24-25 dt 8-4-2024_compressed.pdf14 Jan 2026
CertificateFile: INCORPORATION CERTIFICATE SPPL.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: Ex-1 Archtect certificate SRH-2.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Ex-5 Engineer SRH2 work completed.pdf-
CA Certificate for Funds UtilizationFile: EX3 -CA Certificates - SRH 2 as on 30June2023.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Ex-2 pending work Architect certificate SRH-2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Ex-6 SRH 2 Engineer pending work to complete.pdf-
CA Certificate for Funds required for Project CompletionFile: EX4 - CA Certificates - SRH 2 -as of 30-6-2023.pdf-
AffidavitFile: Form-B Notarised.pdf-
Consent letter from 2/3rd of AllotteesFile: Consent Ltr M wing -7.pdf-
Relevant Document/sFile: Compenstion for Delay Delivery 7 POINT 6.pdf-
Details Of Sold/ Un-sold UnitsFile: sold -un sold list M wing-56-14 -42.pdf-
Document 1File: Affidavit cum Undertaking -promoter- 2-3rd allottees requirement.pdf-
Document 2File: Ex-7 Affadavit for Extn.pdf-
Document 3File: FORM 7 mARCH 2022 RAGHVENDRA & CO.pdf-
Document 4File: Structual stability certificate SRH-2 Extn period.pdf-
Document 5File: Authorisation letter.pdf-
Document 6File: ENGINEER CERTIFICATe cost to incur SRH-2.pdf-
Document 7File: Consent of Extn in AOS page 4.pdf-
Commencement letter SRH phase-II dt 1-2-2018-
High lighted plan dwg 2 of 4 (Block 4)1-2-2018 details of car parking & others-
SALE DEED DRAFT -SRH-PHASE-1I-
AOS -RERA-SRH- II KNS final-14-2-18-
Sale deed RTC & conversion orders-phase -2-
Apartment sanctioned plan- phase-2-
SRH_SitE Plan_27_07_2017- 2-75 FAR-
Allotment letter format SRH phase-2-
Brochure Sipani Royal Heritage phase -2-
SPECIFICATION SRH phase -2-
EC 308-309-311 from 1-4-70 to jan 2018-
E-KHATHA new 308,309,311-28-10-17-
JDA-GPA-land sale deed -SRH-merged file-
Fire NOC for SRH-
conersion_orders Phase -II-
Relinequishing_deed 1969-2017-18 SRH-
AIR PORT AUTHORITY NOC SRH-
BESCOM SRH NOC-
KSPCB_NOC_SRH-
Environment NOC FOR SRH 12-5-17-
BSNL SRH NOC-
Unnamed document-
legal opinion final S & R april 2017-
Balance Sheet 2016 - 2017File: Balance sheet 2016-17.pdf-
Balance Sheet 2015 - 2016File: BALANCE SHEET.pdf-
Balance Sheet 2014 - 2015File: BALANCE SHEET 2014-15.pdf-
Audited Profit and Loss Statement 2016 - 2017File: Proft & loss acct 2016-17.pdf-
Audited Profit and Loss Statement 2015 - 2016File: STATEMENT OF PROFIT AND LOSS.pdf-
Audited Profit and Loss Statement 2014 - 2015File: P L AC 2014-15.pdf-
Director's Report 2016 - 2017File: DIRECTORS REPORT.pdf-
Director's Report 2015 - 2016File: DIRECTORS REPORT.pdf-
Director's Report 2014 - 2015File: DIRECTORS REPORT - 2015.pdf-
Cash Flow Statement 2016 - 2017File: Cash flow statement 2016-17.pdf-
Cash Flow Statement 2015 - 2016File: CASH FLOW STATEMENT.pdf-
Auditor's Report 2016 - 2017File: Auditor's report 2017.pdf-
Auditor's Report 2015 - 2016File: AUDITOR'S REPORT 2015-16.pdf-
Auditor's Report 2014 - 2015File: Audit report 2014-15 sppl.pdf-
Income Tax Return Acknowledgement 2016 - 2017File: I TR Ack A Y 2017-18.pdf-
Income Tax Return Acknowledgement 2015 - 2016File: IT RETURN ACKNOWLEDGEMENT.pdf-
Income Tax Return Acknowledgement 2014 - 2015File: IT ACKNOWLEDGEMENT 15 16.pdf-
Form B declaration Sipani Royal Heritage Phase II-

How this compares with Bengaluru Urban

0%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 42 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep SIPANI ROYAL HERITAGE PHASE-II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: SIPANI PROPERTIES PVT LTD

sipani properties pvt ltd has 7 registrations on RERA Karnataka, including sipani bliss and SIPANI CITY PHASE-1. Its filings declare 10 earlier projects, 7 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if SIPANI ROYAL HERITAGE PHASE-II is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of SIPANI ROYAL HERITAGE PHASE-II?

The registered promoter entity is SIPANI PROPERTIES PVT LTD, a company as per the filing. Its CIN U70102KA1997PTC023041 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in SIPANI ROYAL HERITAGE PHASE-II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SIPANI ROYAL HERITAGE PHASE-II?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at SIPANI ROYAL HERITAGE PHASE-II?

The professionals named in the filing: Architect: VERNEKAR ASSOCIATES pvt ltd; Engineer: VENKATESH BABU REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIPANI ROYAL HERITAGE PHASE-II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIPANI ROYAL HERITAGE PHASE-II. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIPANI ROYAL HERITAGE PHASE-II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.