Home / Browse projects / Bengaluru Urban, Karnataka / sipani Royal Heritage Phase-I

Registration approved No litigation declared Residential/Group Housing project

sipani Royal Heritage Phase-I

By sipani properties pvt ltd

RG-KA-48459 · RERA PRM/KA/RERA/1251/308/PR/180328/002366 · Last updated on RERA Karnataka portal: 24 Jul 2026

Source: official RERA Karnataka filing

Red flags

  • 4 complaints at RERA Karnataka
  • Completion date moved by 60 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
Sep 2026Possession promisedmoved 60 months from the original
5 of 17Construction stages donefurthest along: RCC or MS Framed structure, 99%
967 of 980Units unsoldnot recorded sold or booked
4Complaints at RERA Karnatakaon this registration
Jump to the 89 documents Report an error

sipani Royal Heritage Phase-I is a Residential/Group Housing project by sipani properties pvt ltd in Bengaluru Urban, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1251/308/PR/180328/002366 on 28 Mar 2018. Possession is promised by 30 Sep 2026. The completion date has moved by 60 months from the original filing. 13 of the 980 units on this registration are recorded sold or booked, and 5 of 17 construction stages are filed complete. 4 complaints are on record with the regulator.

At a glance

Project

  • Namesipani Royal Heritage Phase-I
  • TypeResidential/Group Housing
  • Location
    • Anekal
    • Bengaluru Urban
  • PincodeNot stated
  • RERA no.PRM/KA/RERA/1251/308/PR/180328/002366
  • ReraGenie IDRG-KA-48459

Builder

  • Namesipani properties pvt ltd
  • Entity typeCompany
  • CINU70102KA1997PTC023041
  • Authorized SignatoryMadhava Murthy M N
  • DirectorsRamesh sipani, R K SIPANI, DINESH SIPANI
  • Other registrations6 more →
  • Declared earlier projects10 →

Key dates

this monthRegisteredMar 2018First promiseSep 2021Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on28 Mar 2018
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Sep 2021)
  • Buildings10 building records
  • Documents filed89 files

Current status

1%13 of 980 units booked
6.7%Of the estimated cost spent so far

Figures as on 24 Jul 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WING---98098
B wing---98098
C Wing---98098
D wing---98098
E Wing---98098
F Wing---98098
G wing---98098
H wing---98098
I wing---98098
J wing---98098

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 17 construction stages are filed complete. The stage furthest along is RCC or MS Framed structure, at 99%.

Building: 91% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Retaining wall (All types)100%
Plinth level Beam100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
RCC or MS Framed structure99%
Masonry construction: Bricks, Concrete blocks etc95%
Plastering inside , outside & Ceiling90%
Joinery: Doors, Windows, Ventilators etc85%
Basic work of Water supply, Sanitary and Electrification80%
Dadoing, Skirting, Flooring, Tiles work (All types)80%
Railing and Grill fixing85%
Electrification, Water supply and Sanitary Finishing85%
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Fire prevention and fire fighting fitting and fixture with network85%
Weather Proof work(tile,concrete)85%
Painting80%
Elevation workNot applicable
Internal and External work including landscapes as per santioned drawings95%

Progress on shared amenities41

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Internal Roads & FootpathsYes99%
Sewage and Drainage SystemYes100%
Parks & Tree plantingYes99%
Street LightingYes99%
Provision for community buildings and for treatment and disposal of sewage and sullage waterYes100%
Solid waste management and disposalYes100%
Water conservationYes100%
Energy managementYes0%
Fire protection and fire safety requirementsYes95%
Education/Health/Other public amenitiesYes-
Electricity supply transformer and substationYes96%
Emergency Evacuation servicesYes96%
Storm water drainsYes99%
Use of renewable energyYes0%
Water conservation/rain water harvesting/recharge of ground waterYes100%
ElectricityYes99%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes99%
Club HouseYes99%
Community HallYes99%
Outdoor Sports facilityYes100%
Indoor Sports facilityYes99%
Swimming PoolYes100%
GymYes100%
ParksYes100%
Power BackupYes99%
GasNoNot applicable
Water and SanitationYes100%
Air Conditioning And incerntionNoNot applicable
StaircasesYes98%
LiftsYes89%
Staircases and Lift lobbies, corridor,lobbies, corridorYes97%
Fire escapesYes98%
Common entrance and exit for the building / common portico/foyer/verandahYes98%
BasementYes99%
TerraceYes95%
Outer WallYes100%
Open parking areas and common storage spacesYes99%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyYes100%

Land and ownership

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area39,406 sq m
Named landownersNone

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 141.32 cr
Cost incurredRs 9.41 cr
Spent of the estimate6.66%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 108.73 crRs 8.64 cr
Principal sum and interest payable to financial institutions-Non Banking financial institution (NBFC)Rs 15.53 crRs 46.13 lakh
Payment of chargesRs 4.50 cr-
On-site expenditure-Consultants FeesRs 3.50 crRs 19.01 lakh
On-site expenditure-Salaries of workersRs 2.85 cr-
Payment of taxesRs 2.00 cr-
On-site expenditure-Cost Of Services(Water, Electricity, Sewage)Rs 1.95 crRs 9.67 lakh
On-site expenditure-Site OverheadRs 1.75 crRs 1.41 lakh
Payment of feesRs 50.00 lakh-

Certifying professionals and partners2

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVERNEKAR ASSOCIATES pvt ltd
EngineerVENKATESH BABU REDDY

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

ExtensionSep 2021 → Jun 2022

No reason recorded in the filing

EX/PRM/KA/RERA/1251/308/PR/220902/002366Jun 2022 → Jun 2023

Reason as filed by the promoterothers

ExtensionJun 2023 → Sep 2026

No reason recorded in the filing

Complaints filed with RERA Karnataka4

Case no.ComplainantRespondentFiled
CMP/200701/0006099-sipani properties pvt ltd01/07/2020
CMP/220119/0008828-sipani properties pvt ltd19/01/2022
00232/2025-sipani properties pvt ltd30/01/2025
00621/2025-sipani properties pvt ltd11/04/2025

Documents filed89

As listed on the registration, under the names the promoter filed them with; the newest 80 of 89 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1251/308/PR/180328/002366 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - SRH Ph1 30-6-26 Q1 FY2026-27.pdf24 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form-5 SRH-1 Architect 30-6-26.pdf24 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineers certificate SRH 1 -QU 30-6-26.pdf24 Jul 2026
Q1 2026-27 KSPCB- PCB (10 Acres to 125 Acres)24 Jul 2026
Q1 2026-27 KSPCB- MOEF (Above 50 Acres)24 Jul 2026
Q1 2026-27 KPTCL- BESCOM24 Jul 2026
Q1 2026-27 Fire and Safety24 Jul 2026
Q1 2026-27 Airport Authority of India24 Jul 2026
Q1 2026-27 BSNL/Telecommunication Department24 Jul 2026
Q1 2026-27 Registration documentFile: DOD SRH phase1 -2 Regd Doc bk-1-504 of 24-25 dt 8-4-2024_compressed.pdf24 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - SRH Ph1 31-3-26 Q4 FY25.pdf15 Apr 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: FORM 5 - SRH PH-1 ARCHITCT 31-3-26.pdf15 Apr 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineers certificate SRH 1 -QU 31-3-26.pdf15 Apr 2026
Q4 2025-26 KSPCB- PCB (10 Acres to 125 Acres)15 Apr 2026
Q4 2025-26 KSPCB- MOEF (Above 50 Acres)15 Apr 2026
Q4 2025-26 KPTCL- BESCOM15 Apr 2026
Q4 2025-26 Fire and Safety15 Apr 2026
Q4 2025-26 Airport Authority of India15 Apr 2026
Q4 2025-26 BSNL/Telecommunication Department15 Apr 2026
Q4 2025-26 Registration documentFile: DOD SRH phase1 -2 Regd Doc bk-1-504 of 24-25 dt 8-4-2024_compressed.pdf15 Apr 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4 - SRH Ph1 -31-12-25 Q3 FY25 (3).pdf16 Jan 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form05 Architect SRH-1 Q3 25-26.pdf16 Jan 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form-6 Engineer 31-12-25 Q3 25-26.pdf16 Jan 2026
Q3 2025-26 KSPCB- PCB (10 Acres to 125 Acres)16 Jan 2026
Q3 2025-26 KSPCB- MOEF (Above 50 Acres)16 Jan 2026
Q3 2025-26 KPTCL- BESCOM16 Jan 2026
Q3 2025-26 Fire and Safety16 Jan 2026
Q3 2025-26 Airport Authority of India16 Jan 2026
Q3 2025-26 BSNL/Telecommunication Department16 Jan 2026
Q3 2025-26 Registration documentFile: DOD SRH phase1 -2 Regd Doc bk-1-504 of 24-25 dt 8-4-2024_compressed.pdf16 Jan 2026
CertificateFile: INCORPORATION CERTIFICATE SPPL.pdf-
Project Details-
Architect Certificate for Work Completion Schedule till DateFile: VERNEKAR_ Ex1.pdf-
Engineer Certificate for Work Completion Schedule till DateFile: Engineer-Ex5-20220322131430.pdf-
CA Certificate for Funds UtilizationFile: CA FORM EX3 _20220321193419.pdf-
Architect Certificate for Pending Work Completion Schedule.File: Venekar EX 2.pdf-
Engineer Certificate for Pending Work Completion Schedule.File: Enginner -Ex-6-20220322131445.pdf-
CA Certificate for Funds required for Project CompletionFile: CA FORM EX4_20220321193459.pdf-
AffidavitFile: Form B Notarised.pdf-
Latest Encumbrance CertificateFile: EC 31-3-22 SRH.pdf-
Consent letter from 2/3rd of AllotteesFile: CONSENT LETTERS EXTN pdf.pdf-
Details Of Sold/ Un-sold UnitsFile: SoldUnsoldDetails.xls-
Document 1File: Ex-7 -Affadavit -reasons for delay.pdf-
Document 2File: Compensation -page 11 of AGREEMENT - F 205.pdf-
Document 3File: SANCTION PLAN, APALETTER,SALABLE AREA STATEMENT.pdf-
Document 4File: NOC- SRH all in one.pdf-
C C - site approval SRH 27-7-17-
combined EC SRH-COMPRESED-
SALE DEED DRAFT -SRH-PHASE-1-
Agreement to sell -PHASE-I RERA -SRH-
combined sale deeds SRH-
Approved building plan SRH-
SRH_SitE Plan_27_07_2017- 2-75 FAR-
Allotment Letter - SRH-
SRH Brochure-
SRH - Specifications-
combined EC SRH-COMPRESED-
combined kata & conversion order-
JDA & Gpa srh-
MR, PHODI & ETC-
Conversion order SRH-
Relinequishing_deed 1969-2017-18 SRH-
AIR PORT AUTHORITY NOC SRH-
BESCOM SRH NOC-
KSPCB_NOC_SRH-
BSNL SRH NOC-
SRH_SitE Plan_27_07_2017- 2-75 FAR-
Approved building plan SRH-
Balance Sheet 2016 - 2017File: BALANCE SHEET.pdf-
Balance Sheet 2015 - 2016File: BALANCE SHEET 2014-15.pdf-
Balance Sheet 2014 - 2015File: BALANCE SHEET.pdf-
Audited Profit and Loss Statement 2016 - 2017File: STATEMENT OF PROFIT AND LOSS.pdf-
Audited Profit and Loss Statement 2015 - 2016File: P L AC 2014-15.pdf-
Audited Profit and Loss Statement 2014 - 2015File: PROFIT & LOSS.pdf-
Director's Report 2016 - 2017File: DIRECTORS REPORT - 2016.pdf-
Director's Report 2015 - 2016File: DIRECTORS REPORT - 2015.pdf-
Director's Report 2014 - 2015File: Directors report.pdf-
Cash Flow Statement 2016 - 2017File: CASH FLOW STATEMENT.pdf-
Cash Flow Statement 2015 - 2016File: cash flow 2014-15.pdf-
Auditor's Report 2016 - 2017File: AUDITOR'S REPORT 2015-16.pdf-

How this compares with Bengaluru Urban

1%of this project is bookeddistrict median 51%
34%of Bengaluru Urban projects moved their completion datethis one moved by 60 months
1%of Bengaluru Urban registrations are shown as withdrawn or revokedthis one is not

Computed across the 4,100+ Bengaluru Urban projects on ReraGenie, from their own filings.

Keep sipani Royal Heritage Phase-I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Bengaluru Urban4,100+ in Bengaluru Urban

Builder: sipani properties pvt ltd

sipani properties pvt ltd has 7 registrations on RERA Karnataka, including sipani bliss and SIPANI CITY PHASE-1. Its filings declare 10 earlier projects, 7 of them declared completed. Read the full track record. See more projects on the Bengaluru Urban district page.

Frequently asked questions

What are my rights if sipani Royal Heritage Phase-I is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of sipani Royal Heritage Phase-I?

The registered promoter entity is sipani properties pvt ltd, a company as per the filing. Its CIN U70102KA1997PTC023041 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in sipani Royal Heritage Phase-I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against sipani Royal Heritage Phase-I?

Each case number above is a complaint filed with RERA Karnataka. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

Who certifies construction progress at sipani Royal Heritage Phase-I?

The professionals named in the filing: Architect: VERNEKAR ASSOCIATES pvt ltd; Engineer: VENKATESH BABU REDDY. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in sipani Royal Heritage Phase-I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About sipani Royal Heritage Phase-I. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save sipani Royal Heritage Phase-I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.