Home / Browse projects / Pune, Maharashtra / SILVER STONE

Completed No litigation declared Residential / Group Housing project

SILVER STONE

By Panama Sunarch Developers

RG-MH-12280 · RERA P52100010659 · Last updated on MahaRERA portal: 2 Apr 2025

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
124 of 154Construction stages doneacross 14 buildings; furthest along: Internal walls, 97%
2Complaints at MahaRERAon this registration
Jump to the 172 documents Report an error

SILVER STONE is a Residential / Group Housing project by Panama Sunarch Developers in Pune, Maharashtra, registered with MahaRERA as P52100010659 on 31 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 6 months from the original filing. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSILVER STONE
  • TypeResidential / Group Housing
  • Location
    • HANDEWADI
    • OUATADE HANDEWADI
    • Haveli
    • Pune
    • 412308
  • Pincode412308
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100010659
  • ReraGenie IDRG-MH-12280

Builder

  • NamePanama Sunarch Developers
  • Entity typePartnership
  • PartnersNEELIMA GAUTAM LADKAT, Gautam Balasaheb Ladkat

Key dates

this monthRegisteredAug 2017First promiseDec 2024Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 30 Dec 2024)
  • Buildings14 building records
  • Documents filed172 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building DENA160000
Building FGNA160000
Building HNA90000
Row House No 1NA20000
Row House No 2NA20000
Row House No 3NA20000
Row House No 4NA20000
Row House No 5NA20000
Row House No 6NA20000
Row House No 7NA20000
Row House No 8NA20000
Row House No 9NA20000
Row House No 10NA20000
Building AmenityNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building14

As on 2 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

124 of 154 construction stages are filed complete across 14 buildings. The stage furthest along is Internal walls, at 97%.

Building DE91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building FG88%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.83%
Building H73%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 482%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 782%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House No 1082%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Building Amenity87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities19

As on 2 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes90%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes80%
Water PumpYes100%
Underground Water TankYes100%
Paving of areas appurtenant to BuildingYes80%
Compound WallYes80%

Parking filed128

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots128
Closed/Covered84
Open Space44
BuildingClosed/CoveredOpen SpaceTotal
Building DE20020
Building FG21021
Building H404
Building Amenity394483

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area16,547 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
TANAJI SAHEBRAO CHAVANHadapsarPune
YASHWANT SAHEBRAO CHAVANHadapsarPune
KAILAS SAHEBRAO CHAVANHadapsarPune
NILESH ANANDRAO CHAVANHadapsarPune

Approvals and building plan

Permissible FSI19862.59
Proposed, not sanctioned17,233 sq m
Buildings approved14
Buildings sanctioned14

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDESTINATION CENTRE MAGARPATTA CITY HADPSAR PUNE

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVK a architecture
EngineerS S Patane Associates
EngineerSuhel Diwan
Chartered AccountantKataria and Karnavat
PartnerRole in project
Panama Sunarch Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025721Dec 2024 → Jun 2025

Reason as filed by the promoterActual work on site is completed and submitted file for completion certificate before PMRDA, Pune on 13/09/2024 (OC attached). It’s pending due to PMRDA’s new norms about Water and Garden NOC. need time for compliance of NOC's. It's procedural delay to get Occupancy certificate from PMRDA Pune

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12501494Vishwajeet NalawadePanama Sunarch Developers04/05/2025
CC12501495Vishwajeet NalawadePanama Sunarch Developers04/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 6 Jan 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Jun 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Jan 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Jul 2021

Documents filed172

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Declaration in FORM BFile: FORM B.pdf2 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5- 2023-24.pdf2 Apr 2025
Certificates of CA (Form 5)File: Form 5- 2017-18.pdf31 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5- 2019-20.pdf31 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5- 2020-21.pdf31 Mar 2025
CERSAI detailsFile: CERSAI_Search_Report.pdf31 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A- Seperate Bank acc declaration.pdf31 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5- 2021-22.pdf31 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A_March 22.pdf31 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest in other organisation.pdf31 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A_March 23.pdf31 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5- 2022-23.pdf31 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured unsecured.pdf31 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Silver Stone.PDF6 Feb 2025
Declaration in FORM BFile: Form B- Affidavit_compressed.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: Declaration Sold Inventory_compressed.pdf31 Jan 2025
Certificates of CA (Form 3)File: CA.pdf24 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Artch.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng.pdf22 Jan 2025
Certificates of CA (Form 3)File: CA CERTIFICATE SIGNED_compressed.pdf11 Nov 2024
Certificates of CA (Form 3)File: CA CERTIFICATE SIGNED_compressed.pdf11 Nov 2024
Certificates of CA (Form 3)File: CA CERTIFICATE SIGNED_compressed.pdf11 Nov 2024
Certificates of CA (Form 3)File: CA CERTIFICATE SIGNED_compressed.pdf11 Nov 2024
Certificates of CA (Form 3)File: CA CERTIFICATE SIGNED_compressed.pdf11 Nov 2024
Certificates of CA (Form 3)File: CA Certificate Silver Stone.pdf20 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Silver Stone 31032024.pdf29 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certificate-Silver stone 31032024.pdf29 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Arch Certificate 30092023.pdf16 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Silver Stone Engineer Certificate 30092023.pdf16 Nov 2023
Certificates of CA (Form 3)File: Silver Stone CA Certificate.pdf16 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch certificate 31122022.pdf7 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer's Certificate 31122022.pdf7 Feb 2023
Certificates of CA (Form 3)File: Form 3 CA certificate 31122022.pdf7 Feb 2023
Certificates of CA (Form 3)File: Form 3 CA certificate 31122022.pdf7 Feb 2023
Details of encumbrancesFile: encumbrance certificate silver stone.pdf2 Dec 2022
Certificates of CA (Form 3)File: Form 3- CA certficate- June2022_compressed.pdf22 Sep 2022
Certificates of CA (Form 3)File: Form 3- CA certificate -2022_Final RERA.pdf21 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 220630-RERA Arch Certificate_compressed.pdf20 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate RERA Form 2022.pdf3 May 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer’s certificate RERA 2022.pdf3 May 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch RERA Certificate 2022.pdf23 Feb 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers RERA Certificate 31-12-2021.pdf23 Feb 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: DE-Soc Registration Certificate_compressed.pdf15 Nov 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: H- Soc Registration Certificate_compressed.pdf15 Nov 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Formation.pdf20 Oct 2021
Declaration about Commencement CertificateFile: Format D-declaration abt CC.pdf20 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A_Engineers's_Quality Assurance Certificate_19072021.pdf20 Jul 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY REGISTRATION CERT OF SILVER STONE.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: Disclosure-Sold-unsold Inventories-31-12-2020 (1).pdf19 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate- H building and RH 1 to 4_compressed.pdf19 Jul 2021
OtherFile: Disclosure-Sold-unsold Inventories-31-12-2020 (1).pdf2 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certificate 31-12-2020.pdf5 Apr 2021
Certificates of CA (Form 3)File: CA certificate.pdf16 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 201105 - Arch Certificate Final.pdf9 Nov 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE 01112020 Final.pdf7 Nov 2020
Details of encumbrancesFile: No Encumbrances Certificate.pdf10 Jul 2020
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate DE and Amenity Silver Stone-RERA.pdf11 Apr 2020
Layout approvalFile: Layout 31122019.pdf6 Jan 2020
Copy of Layout Approval (in case of layout)File: Layout 31122019.pdf6 Jan 2020
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate 31122019.pdf6 Jan 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch certificate 300919 final.pdf11 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certificate 300919 final.pdf11 Dec 2019
Certificates of CA (Form 3)File: CA certificate 300919.pdf11 Dec 2019
Certificates of CA (Form 5)File: FORM5- 29-9-2019_compressed.pdf25 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate 13062019.pdf11 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate13062019.pdf11 Jul 2019
Certificates of CA (Form 3)File: Form 3 CA certificate Dec 18.pdf27 Mar 2019
Certificates of CA (Form 3)File: Form 3 CA certificate Sept 18.pdf26 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Jan 19.pdf29 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's Certficate 19012019.pdf29 Jan 2019
Form 2AFile: Quality Assuarance Certificate RERA 1.pdf29 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate-compressed.pdf16 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate-compressed.pdf16 Jan 2019
Certificates of CA (Form 5)File: FORM 5_RERA_AUDIT REPORT_CA_FY_1718-ilovepdf-compressed.pdf30 Sep 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificates 300618.pdf25 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate 300618.pdf25 Sep 2018
Certificates of CA (Form 5)File: Form 3 CA Certificate 300618.pdf25 Sep 2018
Building plan approvalFile: 10.pdf1 Jun 2018
Building plan approvalFile: 1.pdf1 Jun 2018
Building plan approvalFile: 11.pdf1 Jun 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SILVER STONE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HANDEWADI13,700+ in Pune

2 kmSILVER STONECompleted 41Lapsed / revoked 17Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 94 registered projects within 2 km.

Builder: Panama Sunarch Developers

Panama Sunarch Developers has 1 registration on MahaRERA, including SILVER STONE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SILVER STONE is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SILVER STONE?

The registered promoter entity is Panama Sunarch Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SILVER STONE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SILVER STONE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SILVER STONE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SILVER STONE?

The professionals named in the filing: Architect: VK a architecture; Engineer: S S Patane Associates; Engineer: Suhel Diwan; Chartered Accountant: Kataria and Karnavat. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SILVER STONE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SILVER STONE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SILVER STONE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.