SILVER LEAF
RG-MH-13428 · RERA P50500047042 · Last updated on MahaRERA portal: 4 Mar 2024
Source: official MahaRERA filing
Red flags
- De-registered
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SILVER LEAF is a Residential / Group Housing project by TRIDENT VENTURES in Nagpur, Maharashtra, registered with MahaRERA as P50500047042 on 26 Sep 2022. Possession is promised by 31 Mar 2029.
At a glance
Project
- NameSILVER LEAF
- TypeResidential / Group Housing
- Location
- MANISH NAGAR ROAD
- MANISH NAGAR
- Nagpur (M Corp.)
- Nagpur (Urban)
- Nagpur
- 440015
- Pincode440015
- MapView location on Google Maps (as filed on RERA)
- RERA no.P50500047042
- ReraGenie IDRG-MH-13428
Builder
- NameTRIDENT VENTURES
- Entity typePartnership
- PartnerDEEPAK SUDHAKAR BADKI
Key dates
Key facts
Registration and timeline
- StatusDe-registered
- Registered on26 Sep 2022
- Promised completion31 Mar 2029
- Revised completionNone
- Buildings1 building record
- Documents filed52 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SILVER LEAF | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Mar 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
SILVER LEAF: 75% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 40% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 92% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 4 Mar 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed45
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SHOBHA DATTATRYA INGALE | Nagpur (M Corp.) | Nagpur |
| VIVEK RAMKRISHNA DATE | Nagpur (M Corp.) | Nagpur |
| AMIT SUDHAKAR BADKI | Nagpur (M Corp.) | Nagpur |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | NIRAJ S BAINGANE |
| Engineer | NIRAJ S BAINGANE |
| Chartered Accountant | SAMEER DIVECHA |
| Partner | Role in project |
|---|---|
| TRIDENT VENTURES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 22 Aug 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2029
Documents filed52
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SILVER LEAF ARCHITECTS CERTIFICATE 31 DEC 22.pdf | 4 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC CER MAR 23.pdf | 4 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC CER JUN 23.pdf | 4 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARC CER DEC 23.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SILVER LEAF ENG CERTIFICATE 31 DEC 22.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CER MAR 23.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CER JUN 23.pdf | 4 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CER DEC 23.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: booked sold dec 22.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: booked sold march 23.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: booked sold inventory june 23.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: book sold dec 23.pdf | 4 Mar 2024 |
| Disclosure of sold/ booked inventoryFile: book sold dec 23.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate dec 22.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate mar 23.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate june 23.pdf | 4 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate dec 23.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: anual report.pdf | 4 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: anual report.pdf | 4 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE SILVER LEAF.pdf | 18 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer certificate silver leaf NEW.pdf | 18 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: booked inventory.pdf | 18 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf | 18 Jan 2024 |
| Details of encumbrances concerned to LegalFile: NON ENCUMBRANCE ON PROMOTERS LETTER HEAD.pdf | 14 Sep 2022 |
| OtherFile: MODEL AFS AGREEMENT FOE SALE.pdf | 14 Sep 2022 |
| OtherFile: latest allotment letter.pdf | 14 Sep 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: c a certificate.pdf | 1 Sep 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf | 1 Sep 2022 |
| Copy of the legal title reportFile: legal title report WITH HIGLIGHT.pdf | 22 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: DEVIATION ALLOTMENT OF PROM LH.pdf | 22 Aug 2022 |
| Deviation Report with respect to Allotment letterFile: deviation report from draft allotment letter.pdf | 22 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: deviation from draft sale agreement.pdf | 22 Aug 2022 |
| Deviation Report with respect to model copy of AgreementFile: DEVIATION FOR SALE AGREEMENT ON PL.pdf | 22 Aug 2022 |
| OtherFile: REVISED FORM B FINAL .pdf | 22 Aug 2022 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER NEW FORMAT.pdf | 19 Aug 2022 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: bank certificate.pdf | 8 Jul 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT'S CERTIFICATE.pdf | 14 Jun 2022 |
| OtherFile: MEMORANDUM OF UNDERSTANDING.pdf | 14 Jun 2022 |
| Building plan approvalFile: MAP LAYOT.PDF | 31 May 2022 |
| Layout approvalFile: MAP LAYOT.PDF | 31 May 2022 |
| PAN CardFile: TRDENT VENTURES PAN.pdf | 31 May 2022 |
| Details of encumbrancesFile: NON ENCUMBBRANCE CERTIFICATE.pdf | 31 May 2022 |
| Details of encumbrancesFile: NON ENCUMBERANCE CERTIFICATE.pdf | 31 May 2022 |
| Copy of Layout Approval (in case of layout)File: MAP LAYOT.PDF | 31 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: MAP LAYOT.PDF | 31 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: NIT.pdf | 31 May 2022 |
| Declaration about Commencement CertificateFile: DECLARATION CERTIFICATE.pdf | 31 May 2022 |
| Declaration in FORM BFile: FORM-B.pdf | 31 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 1.pdf | 31 May 2022 |
| CERSAI detailsFile: order no 19 Report from CERSAI.pdf | 31 May 2022 |
| CERSAI detailsFile: NON ENCUMBERANCE CERTIFICATE.pdf | 31 May 2022 |
| CERSAI detailsFile: reply cersai.pdf | 31 May 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Nagpur
Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.
Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 52 filed documents as one ZIP, foldered, with a manifest
Keep SILVER LEAF on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MANISH NAGAR2,800+ in Nagpur
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
STRAWBERRY FARM
MEGHA AMOL WALKE
OFFICERS ENCLAVE
R SANDESH INFRASTRUCTURES PRIVATE LIMITED
WHITE TIGER AND WILD FLOWER
MILINDKUMAR BHAURAO MESHRAM
PALAZZO ROYAL
INTERCONTINENTAL OASIS INFRA LLP
gokul
surendra mangaldas chadda
Sai Villa 5
Earth Infra Venture
See every Nagpur project, with the district possession charts
Builder: TRIDENT VENTURES
TRIDENT VENTURES has 1 registration on MahaRERA, including SILVER LEAF. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Nagpur district page.
Frequently asked questions
What does it mean that SILVER LEAF shows as de-registered on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SILVER LEAF is delayed beyond 31 Mar 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SILVER LEAF?
The registered promoter entity is TRIDENT VENTURES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SILVER LEAF?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SILVER LEAF?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SILVER LEAF?
The professionals named in the filing: Architect: NIRAJ S BAINGANE; Engineer: NIRAJ S BAINGANE; Chartered Accountant: SAMEER DIVECHA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SILVER LEAF?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback