SIGMA CENTURIA

By SIGMA REALTORS

RG-MH-09893 · RERA P52100003501 · Last updated on MahaRERA portal: 4 Nov 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 81 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
10 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
23 of 70Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

SIGMA CENTURIA is a Others project by SIGMA REALTORS in Pune, Maharashtra, registered with MahaRERA as P52100003501 on 5 Aug 2017. The registration is recorded completed; possession was promised by 13 Jun 2025. The completion date has moved by 81 months from the original filing. 47 of the 70 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameSIGMA CENTURIA
  • TypeOthers
  • Location
    • sr no 204/4/5/6/7
    • papde wasti
    • Fursungi
    • Haveli
    • Pune
    • 412308
  • Pincode412308
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003501
  • ReraGenie IDRG-MH-09893

Builder

  • NameSIGMA REALTORS
  • Entity typePartnership
  • PartnerTUSHAR SHASHIKANT PUNEKAR

Key dates

this monthRegisteredAug 2017First promiseSep 2018Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on5 Aug 2017
  • Promised completion13 Jun 2025
  • Revised completionRevised to 13 Jun 2025 (originally 30 Sep 2018)
  • Buildings2 building records
  • Documents filed133 files

Current status

67%47 of 70 units booked
99.9%Work done, per cost certificate

Figures as on 4 Nov 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIGMA CENTURIA RESIDENTIALNA8770070
SIGMA CENTURIA COMMERCIALNA00000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 4 Nov 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

SIGMA CENTURIA RESIDENTIAL91%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SIGMA CENTURIA COMMERCIAL0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 4 Nov 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed45

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots45
Open Space45

Land and ownership5

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,300 sq m
Land owned byThe promoter, with other names on the file
Named landowners5
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Sep 2025
LandownerVillageDistrict
ASHOK HARIBHAU PAPDEFursungiPune
LEELA RAMESH PAPDEFursungiPune
DEEPALI PAPDEFursungiPune
SHASHANK PAPDEFursungiPune
ANUPAMA KEVLEMarket YardPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI4721.1
Proposed, not sanctioned3,947 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDP ROAD
Estimated costRs 9.88 cr
Cost incurredRs 9.87 cr
Work done99.89%
BuildingWingEstimatedIncurred
SIGMA CENTURIA RESIDENTIALNARs 9.88 crRs 9.87 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNEELESH CHORGHADE
EngineerSAMARTH COMPREHENSIVE CIVIL CONSULTANCY PVT LTD
EngineerAtul Krishnath Sakhare
EngineerSamadhan Prabhu Hanpude
Chartered AccountantCA Pratik D Jain
Chartered AccountantRSPH & Associates
PartnerRole in project
Sigma Realtors-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012134Sep 2018 → Dec 2022

Reason as filed by the promoter1] Delay in process of Amenity hand over. 2] Proposing revision in lay out. 3] out of 70 units , 60 unit got part occupancy certificate. only 10 units & club house are remaining.

EXT52100008437Sep 2018 → Sep 2021

Reason as filed by the promoterRespected Authority, We obtained part occupancy certificate( O.C.C/0664/18 PMC) for sigma centuria phase 1. i.e 60 units out of 70 units EXT52100000703. Now, we are planning to amalgamate phase 1 & phase 2. Delay in planning for phase 2 & covid 19 pandemic causes for delay for final completion .i.e (30/09/2019.) we request you to grant us extension period for proposed date of completion 30/9/2021. We also attached resolution of association of allottees for proposed extension period & part occupancy certificate. Regards, sigma realtors.

EXT52100000703Sep 2018 → Sep 2019

Reason as filed by the promoterdue to change of sanctioning authority from PMRDA to PMC, we got delayed for water & garden noc required for final completion. we got part occupancy certificate (o.c.c/0664/18) dated 18/8/2018 for 60 flats out of 70 flats with parking from PMC.

EA13092502579Sep 2018 → Jun 2025

Reason as filed by the promoterwe have obtained full occupancy certificate from Fursungi-Uruli Devachi Municipal Council dated 13/06/2025.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Full OC.pdf4 Nov 2025
Withdrawal Update Form 1File: Architect Certificate-June-25.pdf31 Oct 2025
Withdrawal Update Form 1File: Architect Certificate-June-25.pdf31 Oct 2025
Withdrawal Update Form 2File: ER Certificate (June 25).pdf31 Oct 2025
Withdrawal Update Form 2File: ER Certificate (June 25).pdf31 Oct 2025
Withdrawal Update Form 3File: CA Certificate (June 25) final.pdf31 Oct 2025
Withdrawal Update Form 3File: CA Certificate (June 25) final.pdf31 Oct 2025
Form 2A (FY 2023-2024)File: Form 2A - 2023 24.pdf11 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A - 2024 -25.pdf11 Oct 2025
Form 1File: 1-AR-Sept-24.pdf27 Sep 2025
Form 2File: 1-ER-Sept-24.pdf27 Sep 2025
Form 3File: 1-CA Certificate-Sep 24.pdf27 Sep 2025
Disclosure of Sold and Booked InventoryFile: 1-Disclosure - Sept 24.pdf27 Sep 2025
Form 1File: architect letter june 2024.pdf27 Sep 2025
Form 2File: Engineer Certificate June 2024.pdf27 Sep 2025
Form 3File: CA June 2024 Final.pdf27 Sep 2025
Disclosure of Sold and Booked InventoryFile: sigma centuria - june 24 converted.pdf27 Sep 2025
Form 2A (FY 2022-2023)File: Form 2A - 2022-23.pdf27 Sep 2025
Form 2A (FY 2021-2022)File: Form 2A - 2021-22.pdf27 Sep 2025
Form 2File: ER Certificate ( March 25).pdf23 Sep 2025
Form 3File: CA Certificate (March 25) Final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Inventory March 25.pdf23 Sep 2025
Form 1File: AR Certificate March 25.pdf23 Sep 2025
Form 1File: AR Certificate Dec 24.pdf23 Sep 2025
Form 2File: ER Certificate(Dec 24).pdf23 Sep 2025
Form 3File: CA Certificate (Dec 24) Final.pdf23 Sep 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - December 2024.pdf23 Sep 2025
Form 5 (FY 2023-2024)File: Rera audit report 23-24 Final.pdf23 Sep 2025
Form 5 (FY 2024-2025)File: RERA audit report 24-25 Final.pdf23 Sep 2025
Form 5 (FY 2019-2020)File: 2019-20.pdf22 Sep 2025
Form 5 (FY 2020-2021)File: 2020-21.pdf22 Sep 2025
Form 5 (FY 2021-2022)File: 2020-21.pdf22 Sep 2025
Form 5 (FY 2022-2023)File: 2022-23.pdf22 Sep 2025
Disclosure of sold/ booked inventoryFile: Adobe Scan 13 Nov 2024 (1) (1).pdf19 Nov 2024
Disclosure of sold/ booked inventoryFile: Adobe Scan 13 Nov 2024 (1) (1).pdf19 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect letter june 2024.pdf6 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate June 2024.pdf6 Aug 2024
Certificates of CA (Form 3)File: CA cert Jun 24 (1).pdf6 Aug 2024
Disclosure of sold/ booked inventoryFile: sigma centuria - June 2024.pdf31 Jul 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: RA Audit Signed Copy - converted.pdf24 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf20 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf20 Jun 2024
Certificates of CA (Form 3)File: CA Cert Signed copy (2).pdf20 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf30 May 2024
Disclosure of sold/ booked inventoryFile: Disclsoure of Sold Booked - Dec 23.pdf30 May 2024
Disclosure of sold/ booked inventoryFile: Disclsoure of Sold Booked - March 24.pdf30 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Engineer Certificate March 18_compressed (1).pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Engineer Certificate March 19 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Engineer Certificate March 20 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Engineer Certificate March 21 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Engineer Certificate March 21 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Engineer Certificate June 21 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Engineer Certificate Sept 21_compressed.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Engineer Certificate Dec 21 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8 Engineer Certificate March 22 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9 Engineer Certificate June 22 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 10 Engineer Certificate Sep 22 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11 Engineer Certificate Dec 22 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 12 Engineer Certificate March 23 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 13 Engineer Certificate June 23 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14 Engineer Certificate Sep 23 ok.pdf6 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15 Engineer Certificate Dec 23 ok.pdf6 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1-Architect Certificate -March-18.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2-Architect Certificate- March-19.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3-Architect Certificate-March-20.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4-Architect Certificate- March-21.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5-Architect Certificate- June-21.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6-Architect Certificate- Sept-21.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7-Architect Certificate- Dec-21.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8-Architect Certificate- March-22.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9-Architect Certificate -June-22.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 10-Architect Certificate- Sept-22.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 11-Architect Certificate-Dec-22.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 12-Architect Certificate-March-23.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 13- Architect Certificate-June-23.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 14-Architect Certificate- Sept-23.pdf5 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 15-Architect Certificate- Dec-23.pdf5 Apr 2024
Certificates of CA (Form 3)File: 1-CA Certificate- Mar 2018.pdf5 Apr 2024
Certificates of CA (Form 3)File: 2-CA Certificate- Mar 2019.pdf5 Apr 2024
Certificates of CA (Form 3)File: 3-CA Certificate Mar 2020.pdf5 Apr 2024

How this compares with Pune

67%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 81 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIGMA CENTURIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near papde wasti13,700+ in Pune

2 kmSIGMA CENTURIACompleted 43Lapsed / revoked 15Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 93 registered projects within 2 km.

Builder: SIGMA REALTORS

SIGMA REALTORS has 1 registration on MahaRERA, including SIGMA CENTURIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SIGMA CENTURIA is delayed beyond 13 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIGMA CENTURIA?

The registered promoter entity is SIGMA REALTORS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIGMA CENTURIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SIGMA CENTURIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIGMA CENTURIA?

The professionals named in the filing: Architect: NEELESH CHORGHADE; Engineer: SAMARTH COMPREHENSIVE CIVIL CONSULTANCY PVT LTD; Engineer: Atul Krishnath Sakhare; Engineer: Samadhan Prabhu Hanpude; Chartered Accountant: CA Pratik D Jain; Chartered Accountant: RSPH & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIGMA CENTURIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIGMA CENTURIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIGMA CENTURIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.