ReraGenieLog inGet a buyer report

Home / Browse projects / Chandrapur, Maharashtra / Sidheshwar Nagari-2

Completed No litigation declared Plotted project

Sidheshwar Nagari-2

By Sidheshwar Bhaiyyaji Bharre

RG-MH-50423 · RERA P50900055598 · Last updated on MahaRERA portal: 12 Dec 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Chandrapur registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedregistration recorded completed
12 of 17Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 59 documents Report an error

Sidheshwar Nagari-2 is a Plotted project by Sidheshwar Bhaiyyaji Bharre in Chandrapur, Maharashtra, registered with MahaRERA as P50900055598 on 4 Apr 2024. The registration is recorded completed; possession was promised by 31 Mar 2027. 5 of the 17 units on this registration are recorded sold or booked.

At a glance

Project

  • NameSidheshwar Nagari-2
  • TypePlotted
  • Location
    • Bramhapuri
    • Mouza Bramhapuri
    • Brahmapuri (M Cl)
    • Brahmapuri
    • Chandrapur
    • 441206
  • Pincode441206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50900055598
  • ReraGenie IDRG-MH-50423

Builder

  • NameSidheshwar Bhaiyyaji Bharre
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredApr 2024PromisedMar 2027Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on4 Apr 2024
  • Promised completion31 Mar 2027
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed59 files

Current status

29%5 of 17 units booked

Figures as on 12 Dec 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 12 Dec 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 12 Dec 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntYes100%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,219 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Jun 2025

Approvals and building plan

Sanctioning authorityMunicipal Corporation Brahmhapuri

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPlot No 50, Near Gujare Petrol Pump, Nagbhid Road, Shesh Nagar,Bramhapuri-441206

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRoshan naktode Naktode
EngineerRoshan Naktode Naktode
Chartered AccountantAPJ & Associates
Chartered AccountantAtul BhaiYYa
Chartered AccountantAbhinav Welekar
Chartered AccountantShweta Mohta
PartnerRole in project
Sidheshwar Bhaiyyaji Bharre-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 19 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Dec 2025

Documents filed59

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Completion CertificateFile: CC Mail SS.pdf12 Dec 2025
Completion CertificateFile: Siddheshwar Nagari -02 Form 4.pdf23 Sep 2025
Completion CertificateFile: complation Certificate Siddeshwar Nagari 2.pdf14 Aug 2025
Completion CertificateFile: Siddeshwar Bharre-2 Clarification certificate.pdf14 Aug 2025
Withdrawal Update Form 1File: Form-1 30-05-2025.pdf5 Aug 2025
Withdrawal Update Form 1File: Form-1 30-05-2025.pdf5 Aug 2025
Withdrawal Update Form 2File: Form-2 30-05-2025.pdf5 Aug 2025
Withdrawal Update Form 2File: Form-2 30-05-2025.pdf5 Aug 2025
Withdrawal Update Form 3File: Form -3 30-05-2025 Sign.pdf5 Aug 2025
Withdrawal Update Form 3File: Form -3 30-05-2025 Sign.pdf5 Aug 2025
Form 2A (FY 2024-2025)File: form2A sidhesh nagri 2 update.pdf12 Jul 2025
Withdrawal Update Form 1File: 1_FORM 1.pdf10 Jul 2025
Withdrawal Update Form 2File: 2_FORM 2.pdf10 Jul 2025
Withdrawal Update Form 3File: 3_form-3 30-01- 23.pdf10 Jul 2025
Form 5 (FY 2024-2025)File: Form-5 Siddheshwar Bharree 31-03-2025..pdf8 Jul 2025
Form 1File: Sidhhesh Nagari (2) Form 1 (30-6-4).pdf3 Jul 2025
Form 2File: Sidhhesh Nagari (2) Form 2 ( 30-6-24).pdf3 Jul 2025
Form 3File: Form-3 30-6-2024 Sign.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold and Unsold inventory Annexure 29.pdf3 Jul 2025
Form 1File: Siddhesh Nagari (2) Form 1 (30-9-24).pdf3 Jul 2025
Form 2File: Sidhhesh Nagari (2) Form 2 (30-9-24).pdf3 Jul 2025
Form 3File: Form-3 30-9-2024 Sign.pdf3 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold And Unsold inventory Annexure 29.pdf3 Jul 2025
Form 1File: Letterhead scan form-1.pdf19 Jun 2025
Form 2File: Letterhead scan form-2.pdf19 Jun 2025
Form 3File: form -3 31-12-2024.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Annexure 29.pdf19 Jun 2025
Form 1File: letterhead scan form-1.pdf19 Jun 2025
Form 2File: form-2 scan 31-03-2025 letterhead.pdf19 Jun 2025
Form 3File: Form-3 scan 31-3-2025.pdf19 Jun 2025
Disclosure of Sold and Booked InventoryFile: Annexure 29.pdf19 Jun 2025
Other - TechnicalFile: 22_ANNEXURE A DECLARATION -CUM-UNDERTAKING.pdf21 Mar 2024
Proforma of Agreement for saleFile: 9_ATS.pdf20 Mar 2024
Layout approvalFile: 10_Map.pdf19 Mar 2024
Building plan approval or NA orderFile: 7_NA Order.pdf19 Mar 2024
PAN CardFile: PAN.pdf19 Mar 2024
Copy of the legal title reportFile: 4_Search Report.pdf19 Mar 2024
Details of encumbrances concerned to FinanceFile: 5A_Financial Encumbrance.pdf19 Mar 2024
Details of encumbrances concerned to FinanceFile: 5B_Legal Encumbrance.pdf19 Mar 2024
Details of encumbrances concerned to LegalFile: 5A_Financial Encumbrance.pdf19 Mar 2024
Details of encumbrances concerned to LegalFile: 5B_Legal Encumbrance.pdf19 Mar 2024
Copy of Layout Approval (in case of layout)File: 10_Map.pdf19 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: 7_NA Order.pdf19 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: 7_NA Order.pdf19 Mar 2024
Declaration about Commencement CertificateFile: 12_Declaration about Commencement Certificate.pdf19 Mar 2024
Declaration in FORM BFile: 6_Form B.pdf19 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_FORM 1.pdf19 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_FORM 2.pdf19 Mar 2024
Disclosure of sold/ booked inventoryFile: 11_Annexure 29.pdf19 Mar 2024
CERSAI detailsFile: 16_CERSAI DECLATION.pdf19 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_form-3 30-01- 23.pdf19 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 18_Disclosure of Interest.pdf19 Mar 2024
Proforma of Allotment letterFile: 8_ALLOTMENT LETTER.pdf19 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 14_Declaration about Separate bank Account.pdf19 Mar 2024
Deviation Report with respect to Allotment letterFile: 15_Deviation for Allotment letter.pdf19 Mar 2024
Deviation Report with respect to model copy of AgreementFile: 13_Deviation to ATS.pdf19 Mar 2024
Other - LegalFile: 17_Sale Deed.pdf19 Mar 2024
Other - LegalFile: 19_CLARIFICATION ABOUT PLOT AREA.pdf19 Mar 2024
Other - TechnicalFile: 20_CC MAIL.pdf19 Mar 2024

How this compares with Chandrapur

29%of this project is bookeddistrict median 18%
10%of Chandrapur projects moved their completion datethis one has not
39%of Chandrapur registrations have lapsed or been cancelledthis one is completed

Computed across the 220+ Chandrapur projects on ReraGenie, from their own filings.

Keep Sidheshwar Nagari-2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mouza Bramhapuri220+ in Chandrapur

2 kmSidheshwar Nagari-2Completed 18Lapsed / revoked 5Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 27 registered projects within 2 km.

Builder: Sidheshwar Bhaiyyaji Bharre

Sidheshwar Bhaiyyaji Bharre has 2 registrations on MahaRERA, including Sidheshwar Nagari-2 and Sidheshwar Nagari-3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Chandrapur district page.

Frequently asked questions

What are my rights if Sidheshwar Nagari-2 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sidheshwar Nagari-2?

The registered promoter entity is Sidheshwar Bhaiyyaji Bharre, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sidheshwar Nagari-2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sidheshwar Nagari-2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sidheshwar Nagari-2?

The professionals named in the filing: Architect: Roshan naktode Naktode; Engineer: Roshan Naktode Naktode; Chartered Accountant: APJ & Associates; Chartered Accountant: Atul BhaiYYa; Chartered Accountant: Abhinav Welekar; Chartered Accountant: Shweta Mohta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sidheshwar Nagari-2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sidheshwar Nagari-2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sidheshwar Nagari-2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.