ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Siddhichandrabhaga Heights

Completed No litigation declared Others project

Siddhichandrabhaga Heights

By BHARAT VASTIMAL SOLANKI

RG-MH-98062 · RERA P52100049408 · Last updated on MahaRERA portal: 17 Oct 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 11 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Internal walls, 90%
0Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

Siddhichandrabhaga Heights is a Others project by BHARAT VASTIMAL SOLANKI in Pune, Maharashtra, registered with MahaRERA as P52100049408 on 8 Feb 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 11 months from the original filing.

At a glance

Project

  • NameSiddhichandrabhaga Heights
  • TypeOthers
  • Location
    • GURUWAR PETH
    • KRISHNA HATTI CHOWK
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411042
  • Pincode411042
  • RERA no.P52100049408
  • ReraGenie IDRG-MH-98062

Builder

  • NameBHARAT VASTIMAL SOLANKI
  • Entity typeIndividual
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredFeb 2023First promiseJan 2025Revised toDec 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on8 Feb 2023
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 1 Jan 2025)
  • Buildings1 building record
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SiddhichandrabhagaNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

Siddhichandrabhaga: 79% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 17 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed9

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots9
Closed/Covered9

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area214 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
JYOTI PRAVIN NASHTEPune (M Corp.)Pune
NASHTE NARAYAN SHIVLINGPune (M Corp.)Pune
BHALCHANDRA SHIVLING NASHTEPune (M Corp.)Pune

Approvals and building plan

Permissible FSI863.99
Proposed, not sanctioned864 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch455 RAVIWAR PETH, PUNE 411002

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
BHARAT VASTIMAL SOLANKI-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100026077Jan 2025 → Dec 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges, and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 31-12-2025 to

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Jan 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - Siddhichandrabhaga Heights as on Sep 2025.pdf17 Oct 2025
Form 2File: Form 2 - Siddhichandrabhaga Heights as on Sep 2025.pdf17 Oct 2025
Form 3File: Form 3 - Siddhichandrabhaga Heights as on Sep 2025.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Siddhichandrabhaga Heights as on Sep 2025.pdf17 Oct 2025
Form 1File: Form 1-Siddhichandrabhaga Heights as on June 2025.pdf5 Aug 2025
Form 2File: Form 2 - Siddhichandrabhaga Heights as on June 2025.pdf5 Aug 2025
Form 3File: Form 3 of Siddhichandrabhaga Heights as on 30-06-2025.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Siddhichandrabhaga Heights as on June 2025.pdf5 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhichandrabhaga Heights as on March 2025.pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Siddhichandrabhaga Heights as on March 2025.pdf30 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhichandrabhaga Heights as on March 2025.pdf30 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 ARCHITECT CERTIFICATE-MAR-25.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate (1).pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG certificate.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: sold inventory.pdf28 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23.pdf28 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 2023-24.pdf28 Jan 2025
Layout approvalFile: SANCTION PLAN.pdf11 Jan 2025
Building plan approvalFile: SANCTION PLAN.pdf11 Jan 2025
Copy of Layout Approval (in case of layout)File: SANCTION PLAN.pdf11 Jan 2025
Building Plan Approval / NA Order for plotted developmentFile: SANCTION PLAN.pdf11 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhichandrabhaga Heights as on December 2024.pdf9 Jan 2025
Declaration in FORM BFile: Form B.pdf6 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 24.pdf6 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 24.pdf6 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD SIDDHI CHANDRABHAGA HEIGHTS SEPT-24.pdf11 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sept 2024_compressed.pdf19 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sept 2024.pdf19 Oct 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf19 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Siddhi Chandrabhaga Sep 24.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2022-2023.pdf17 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A 2023-24.pdf17 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Siddhi chandrabhaga as on 30-09-2024.pdf16 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on Sep 2024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Siddhi Chandrabhaga Sep 24.pdf9 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on June 2024.pdf12 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Siddhi chandrabhaga as on 30-06-2024 (2).pdf12 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SIDDHI CHANDRABHAGA Q-1.pdf9 Jul 2024
Disclosure of sold/ booked inventoryFile: SIDDHI CHANDRABHAGA CIRCULAR 29 AS ON MARCH 2024.pdf14 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on March 2024.pdf15 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Siddhi chandrabhaga as on Mar 24.pdf15 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - SIDDHI CHANDRABHAGA 31-03-2024.pdf13 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Siddhichandrabhaga as on 31st December 2023 (SIGNED).pdf5 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - march 2023.pdf29 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2023.pdf29 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2023.pdf29 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2023.pdf29 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - march 2023.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2023.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2023.pdf25 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2023.pdf25 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERCIFICATE 31-03-23.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE 30-06-23.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE 30-09-23.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERCIFICATE 31-12-23.pdf18 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2023.pdf18 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on Dec 2023.pdf10 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Siddhi Chandrabhaga as on Dec 2023.pdf10 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhi Chandrabhaga as on Dec 2023.pdf9 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhi Chandrabhaga as on March 2023.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhi Chandrabhaga as on March 2023.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhi Chandrabhaga as on June 2023.pdf11 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Siddhi Chandrabhaga as on Sep 2023.pdf11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on March 2023.pdf11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on June 2023.pdf11 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Siddhi Chandrabhaga as on Sep 2023.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Siddhi Chandrabhaga as on March 2023.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Siddhi Chandrabhaga as on June 2023.pdf11 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Siddhi Chandrabhaga as on Sep 2023.pdf11 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Siddhi Chandrabhaga as on 2022-23.pdf11 Nov 2023
Copy of the legal title reportFile: 1 Copy of the legal title report (25).pdf6 Feb 2023
Other - LegalFile: AFS_Bharat vastimal solanki_Siddhi chaandrabhaga_06022023.pdf6 Feb 2023
Proforma of Agreement for saleFile: Final AFS.pdf30 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow30 Jan 2023
Other - LegalFile: New Allotment Letter_Bharat vastimal solanki_Siddhi chaandrabhaga_23012023.pdf30 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants_compressed.pdf28 Jan 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE - FINANCE-Siddhichandrabhaga- Bharat Solanki.pdf27 Jan 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE - LEGAL-Siddhichandrabhaga-Bharat Solanki.pdf27 Jan 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE - FINANCE-Siddhichandrabhaga- Bharat Solanki.pdf27 Jan 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE - LEGAL-Siddhichandrabhaga-Bharat Solanki.pdf27 Jan 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 11 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Siddhichandrabhaga Heights on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KRISHNA HATTI CHOWK13,700+ in Pune

Builder: BHARAT VASTIMAL SOLANKI

Bharat Vastimal Solanki has 2 registrations on MahaRERA, including Siddhi Nakoda and Siddhichandrabhaga Heights. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Siddhichandrabhaga Heights is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Siddhichandrabhaga Heights?

The registered promoter entity is BHARAT VASTIMAL SOLANKI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Siddhichandrabhaga Heights?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Siddhichandrabhaga Heights?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in Siddhichandrabhaga Heights?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Siddhichandrabhaga Heights. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Siddhichandrabhaga Heights to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.