Registration lapsed No litigation declared Residential / Group Housing project

Siddhi Samruddhi

By SANGHVI DEVELOPERS

RG-MH-10363 · RERA P52100003255 · Last updated on MahaRERA portal: 16 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 59 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 32 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2021Possession promised59 months past this date
30 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

Siddhi Samruddhi is a Residential / Group Housing project by SANGHVI DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100003255 on 5 Aug 2017. Possession was promised by 23 Nov 2021 and is now 59 months past that date. The completion date has moved by 32 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSiddhi Samruddhi
  • TypeResidential / Group Housing
  • Location
    • Katraj-Kondhwa Road
    • Near Mauli Garden
    • Katraj
    • Haveli
    • Pune
    • 411046
  • Pincode411046
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003255
  • ReraGenie IDRG-MH-10363

Builder

  • NameSANGHVI DEVELOPERS
  • Entity typePartnership
  • PartnersManoj Madanlal Chhajed, Mahendra Bhabutmal Sanghvi, Shrenik Subhashcandra Sanghvi, Subhash Bhabutmal Sanghvi, Kumarpal Mahendra Sanghvi
  • Declared earlier projects1 →

Key dates

59 months past promisethis monthRegisteredAug 2017First promiseMar 2019Revised toNov 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on5 Aug 2017
  • Promised completion23 Nov 2021
  • Revised completionRevised to 23 Nov 2021 (originally 31 Mar 2019)
  • Buildings3 building records
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D BuildingNA120000
Bungalow 1NA20000
Bungalow 2NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 16 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

D Building91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bungalow 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bungalow 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed40

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots40
Closed/Covered22
Open Space18
BuildingClosed/CoveredOpen SpaceTotal
D Building221638
Bungalow 1011
Bungalow 2011

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,400 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
PhatePune (M Corp.)Pune
Vitthal MoreSangamnerPune
Pushpa Sarjerao MorePune (M Corp.)Pune
Namdeo BalkawadePune (M Corp.)Pune
Vitthal Bhaguji BalkawadePune (M Corp.)Pune
MoharkarPune (M Corp.)Pune

Approvals and building plan

Permissible FSI4099.8
Proposed, not sanctioned4,100 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIKHIL PRIDE, Showroom No S2 Upper and Mezzanine floor Tilak Road Pune 411030

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGIRISH M KARANDE and Associates
EngineerNeeraj Kankariya
Chartered AccountantSharma Kuldeep And Co
Chartered AccountantSharma Daliya And Associates
PartnerRole in project
SANGHVI DEVELOPERS-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001553Mar 2019 → Oct 2020

Reason as filed by the promoterAt the time of submission of the application to the MahaRERA, only seven floors of D Building and two bungalows were approved by the concerned Government authorities by CC No.2742/16 dated 02/12/2016. The D building in our project is actually planned for eleven floors. We were expecting the permission for the floors above the 7th floor to be received soon after making the MahaRERA application. However, the approval of the plans from the government authorities got delayed. The approval was received in phases. a)The first approval was received vide CC No.2295/17 dated 8/12/2017 up to eighth floo

EXT52100006005Mar 2019 → Oct 2020

Reason as filed by the promoterI/We the Promoters of the Project SANGHVI DEVELOPERS Reregistered under project registration no P52100003255 do hereby declare that we had mentioned the revised proposed date of completion of project is 31st March 2019. The same was extended for a year by extension certificate dated 10th April 2019 granted by MahaRERA. During this period new formality to obtain NOC from Ministry of Defence has arised and therefore the project got delayed. We would like to inform you that the project is 95% completed. We have 36 unsold inventories which needs to be sell but without the Extension Number we are u

EXT52100009570Mar 2019 → Nov 2021

Reason as filed by the promoterRespected Sir, As per your email dated 25.8.2022 we have uploaded FORM 4 as per your format send in your email. Please make the changes in your recorded accordingly. Thanking You. M/s. Sanghvi Developers Jaydeep Jain.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000023202Mr. Noordin Karmali MulaniM/s. Sanghavi Developers through its Partner Mr. Jaydeep Pukhraj Jain03/07/2019

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Apr 2025

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2AFile: Form 2 final.pdf16 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect Certificate.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate.pdf16 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 upto 31-03-2020.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineer Certificate.pdf16 Apr 2025
Proforma of Agreement for saleFile: Agreement to Sell.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate.pdf16 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Final 2021-22.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate.pdf16 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Final 2021-22.pdf16 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_100_.pdf12 Apr 2025
Certificates of CA (Form 3)File: Form_3_final.pdf12 Apr 2025
Certificates of CA (Form 5)File: Form_5_Final_2021-22.pdf12 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form_2_final.pdf12 Apr 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: siddhisamruddhiCHS.pdf12 Apr 2025
Details of encumbrances concerned to FinanceFile: No Emcumbrances Certificate.pdf8 Apr 2025
Details of encumbrances concerned to LegalFile: No Emcumbrances Certificate.pdf8 Apr 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 PDF 22-2-22.pdf28 Nov 2024
Form 2AFile: FORM 2A.pdf1 Feb 2023
Disclosure of sold/ booked inventoryFile: Disclosure.pdf1 Feb 2023
CERSAI detailsFile: Completion certificate.pdf1 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion certificate.pdf3 Dec 2021
Declaration about Commencement CertificateFile: Format D.pdf26 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf27 Jul 2021
Declaration about Commencement CertificateFile: Commencement Certificate.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate_compressed.pdf27 Jul 2021
Disclosure of sold/ booked inventoryFile: List of Sold and unsold units_compressed.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 upto 31-03-2020_compressed.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 upto 31-03-2021_compressed.pdf27 Jul 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion.pdf27 Jul 2021
Details of Restarting of Construction work post lockdownFile: COMPLETION APLICATION-converted.pdf21 May 2021
Details of Restarting of Construction work post lockdownFile: STATUS OF COMPLETION-converted.pdf21 May 2021
OtherFile: STATUS OF COMPLETION-converted.pdf21 May 2021
OtherFile: COMPLETION APLICATION-converted.pdf21 May 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Certificate.pdf27 Mar 2020
Form 2AFile: Engineer Form 2A dated 18-03-2020_.pdf27 Mar 2020
Certificates of CA (Form 3)File: CA FROM 3.pdf27 Mar 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 CA dated 19 03 2020.pdf27 Mar 2020
Form 2AFile: Rera Form 2A.pdf4 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: CC-0106-2018.pdf12 Mar 2019
Building plan approvalFile: 1-9.pdf11 Mar 2019
Building plan approvalFile: 2-9.pdf11 Mar 2019
Building plan approvalFile: 3-9.pdf11 Mar 2019
Building plan approvalFile: 4-9.pdf11 Mar 2019
Building plan approvalFile: 5-9.pdf11 Mar 2019
Building plan approvalFile: 6-9.pdf11 Mar 2019
Building plan approvalFile: 7-9.pdf11 Mar 2019
Building plan approvalFile: 9-9.pdf11 Mar 2019
Building plan approvalFile: 2018 Plan 1-7.pdf11 Mar 2019
Building plan approvalFile: 2018 plan 2-7.pdf11 Mar 2019
Building plan approvalFile: 2018 Plan 3-7.pdf11 Mar 2019
Building plan approvalFile: 2018 plan 4-7.pdf11 Mar 2019
Building plan approvalFile: 2018 plan 5-7.pdf11 Mar 2019
Building plan approvalFile: 2018 Plan 6-7.pdf11 Mar 2019
Building plan approvalFile: 2018 Plan 7-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 1-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 3-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 4-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 5-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 6-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 7-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 9-9.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 Plan 1-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 plan 2-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 Plan 3-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 plan 4-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 plan 5-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 Plan 6-7.pdf11 Mar 2019
Building Plan Approval (IOD)File: 2018 Plan 7-7.pdf11 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: CC_8122017.pdf8 Mar 2019
Commencement Certificates / NA Order for plotted developmentFile: CC_12122017.pdf8 Mar 2019
Certificates of CA (Form 5)File: Form 5_2017-18.pdf6 Mar 2019
Building plan approvalFile: HPSC0185-ilovepdf-compressed-min.pdf30 Mar 2018
Building Plan Approval (IOD)File: HPSC0185-ilovepdf-compressed-min.pdf30 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf30 Mar 2018
Building plan approvalFile: D building 8th floor plan.pdf28 Mar 2018
Building Plan Approval (IOD)File: D building 8th floor plan.pdf28 Mar 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate.pdf28 Mar 2018
PAN CardFile: Sanghvi Developers Pan Card 1.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
RENUKA RESIDENCYNear Mauli Garden Katraj Kondwa Road. Pune 411046108CompletedJan 2012Late, Apr 2012

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 32 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Siddhi Samruddhi on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Near Mauli Garden13,700+ in Pune

2 kmSiddhi SamruddhiCompleted 58Lapsed / revoked 36Other 63Dot size: filed unitsN

Filed coordinates, straight-line distance. 157 registered projects within 2 km.

Builder: SANGHVI DEVELOPERS

SANGHVI DEVELOPERS has 1 registration on MahaRERA, including Siddhi Samruddhi. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Siddhi Samruddhi shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Siddhi Samruddhi is delayed beyond 23 Nov 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Siddhi Samruddhi?

The registered promoter entity is SANGHVI DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Siddhi Samruddhi?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Siddhi Samruddhi?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Siddhi Samruddhi?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Siddhi Samruddhi?

The professionals named in the filing: Architect: GIRISH M KARANDE and Associates; Engineer: Neeraj Kankariya; Chartered Accountant: Sharma Kuldeep And Co; Chartered Accountant: Sharma Daliya And Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Siddhi Samruddhi?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Siddhi Samruddhi. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Siddhi Samruddhi to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.