Registered No litigation declared Residential / Group Housing project

SIDDHARTH NAGAR GULMOHAR CHS LTD

By SHIVAM PARIVAR DEVELOPERS PVT LTD

RG-MH-75300 · RERA P51800008681 · Last updated on MahaRERA portal: 23 Apr 2026

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 24 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
5 of 11Construction stages donefurthest along: Slabs of Super Structure, 94%
24 of 155Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 183 documents Report an error

SIDDHARTH NAGAR GULMOHAR CHS LTD is a Residential / Group Housing project by SHIVAM PARIVAR DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008681 on 19 Aug 2017. Possession is promised by 30 Dec 2026. The completion date has moved by 24 months from the original filing. 131 of the 155 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameSIDDHARTH NAGAR GULMOHAR CHS LTD
  • TypeResidential / Group Housing
  • Location
    • Siddharth Nagar Road No 2 MIG Colony
    • Goregaon west
    • Borivali
    • Mumbai Suburban
    • 400104
  • Pincode400104
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800008681
  • ReraGenie IDRG-MH-75300

Builder

  • NameSHIVAM PARIVAR DEVELOPERS PVT LTD
  • Entity typeCompany
  • DirectorsSanjay Waman Bhosale, Pramod Waman Bhosale, Ajit Waman Bhosale
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on19 Aug 2017
  • Promised completion30 Dec 2026
  • Revised completionRevised to 30 Dec 2026 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed183 files

Current status

85%131 of 155 units booked
95.0%Work done, per cost certificate

Figures as on 23 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SIDDHARTH NAGAR GULMOHAR CHS LTDNA25251469155

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 94%.

SIDDHARTH NAGAR GULMOHAR CHS LTD: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure94%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises56%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks77%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.53%

Progress on shared amenities15

As on 23 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes30%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes30%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Closed/Covered1
Open Space2

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,318 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jul 2025

Approvals and building plan

Sanctioning authorityMaharashtra Housing and Area Development Authority
Permissible FSI12335.85
Proposed, not sanctioned3,458 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch343, Mani Bhavan, SV Rd, OPP, Jawahar Nagar, Goregaon, Mumbai, Maharashtra 400104
Estimated costRs 93.95 cr
Cost incurredRs 89.25 cr
Work done95.0%
BuildingWingEstimatedIncurred
SIDDHARTH NAGAR GULMOHAR CHS LTDNARs 92.33 crRs 87.71 cr
-NARs 1.62 crRs 1.54 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSpace Moulders
EngineerVaijnath Nachankar
Chartered AccountantShripati Gandhi Choudhari and Co
Chartered AccountantRahul Bera
PartnerRole in project
SHIVAM PARIVAR DEVELOPERS PVT LTD-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800026074Dec 2024 → Dec 2025

Reason as filed by the promoterAs per attachment

EA04032620086Dec 2024 → Dec 2026

Reason as filed by the promoterThe current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed.Industry Slow Down - As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately aff

Litigation declared1

CaseCourtStatus
3091/2014City Civil Court at DindoshiFor Hearing

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000055428Gajesh Dattatray SurveShivam Parivar Developers Pvt Ltd19/07/2018
CC006000000079147Sarju Kamlekarshivam parivar developers04/05/2019
CC006000000089839RAJESH KHANDHAR AND ASHA KHANDHARSHIVAM PARIVAR DEVELOPERSPRIVATE LIMITED24/06/2019
CC006000000193349Anil KumarShivam Parivar Developers Pvt. Ltd29/06/2020
CC12502923Abdul Munaf Abdul Aziz SolankiSiddharth Nagar Gulmohar CoOperative Housing Society Limited Respondent Landowner Promoter20/08/2025
CC12600936Karan Veer MehraSHIVAM PARIVAR DEVELOPERS PVT LTD20/02/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Sep 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Sep 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2026

Documents filed183

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 183 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Gulmohar - March 26.pdf23 Apr 2026
Withdrawal Update Form 2File: Form 2 - Gulmohar - March 26.pdf23 Apr 2026
Withdrawal Update Form 3File: Form 3 - Gulmohar - March 26.pdf23 Apr 2026
Form 2A (FY 2025-2026)File: Form-2A Gulmohar March 2026.pdf21 Apr 2026
Form 5 (FY 2024-2025)File: Form 5.pdf5 Mar 2026
Form 2A (FY 2024-2025)File: Form-2A Gulmohar March-2025.pdf19 Feb 2026
Form 5 (FY 2020-2021)File: Form 5 - Gulmohar FY 20-21.pdf19 Feb 2026
Form 5 (FY 2021-2022)File: Form 5 - Gulmohar FY 21-22.pdf19 Feb 2026
Form 5 (FY 2022-2023)File: Form 5 - Gulmohar FY 22-23.pdf19 Feb 2026
Form 5 (FY 2023-2024)File: Form 5 - Gulmohar FY 23-24.pdf19 Feb 2026
Form 2A (FY 2019-2020)File: Form 2A - 19-20.pdf18 Feb 2026
Form 2A (FY 2020-2021)File: Form 2A - 20-21.pdf18 Feb 2026
Form 2A (FY 2021-2022)File: Form 2A - 21-22.pdf18 Feb 2026
Form 2A (FY 2022-2023)File: Form 2A - 22-23.pdf18 Feb 2026
Form 2A (FY 2023-2024)File: Form 2A 23-24.pdf18 Feb 2026
Form 5 (FY 2019-2020)File: Form 5 - 19-20.pdf18 Feb 2026
Withdrawal Update Form 1File: Form 1 - Gulmohar - Dec 25.pdf11 Feb 2026
Withdrawal Update Form 2File: Form 2 - Gulmohar - Dec 25.pdf11 Feb 2026
Withdrawal Update Form 3File: Form 3 - Gulmohar - Dec 25 sign.pdf11 Feb 2026
Withdrawal Update Form 1File: Form-1 Gulmohar Sept 25_page-.pdf5 Dec 2025
Withdrawal Update Form 2File: Form 2 - Sept 25.pdf5 Dec 2025
Withdrawal Update Form 3File: Form 3 Gulmohar - Sept 25.pdf5 Dec 2025
Withdrawal Update Form 1File: Form-1 Gulmohar June 25.pdf25 Sep 2025
Withdrawal Update Form 2File: Form-2 Gulmohar June-2025.pdf25 Sep 2025
Withdrawal Update Form 3File: GULMOHAR JUNE 25 FORM 3 signed.pdf25 Sep 2025
Form 1File: Form-1 Gulmohar Dec 24.pdf17 Jul 2025
Form 2File: Form-2 Gulmohar March 2025.pdf17 Jul 2025
Form 3File: FORM 3 - Gulmohar - March 25.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: RERA Disclosure - Gulmohar.pdf17 Jul 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Gulmohar - Declaration about Separate Bank Ac.pdf11 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration for Separate Bank Ac - Gulmohar CHSL.pdf11 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Gulmohar Dec24.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR MARCH 2020.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR MARCH 2021.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR MARCH 2022.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR MARCH 2023.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR MARCH 2024.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR JUNE 2024.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR SEPTEMBER 2024.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR DECEMBER 2024.pdf31 Jan 2025
Certificates of CA (Form 3)File: FORM 3- GULMOHAR DECEMBER 2024_1.pdf31 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Gulmohar Dec24.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Gulmohar FY 19-20.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Gulmohar FY 20-21.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA Disclasure - 30062024 Gulmohar.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA Disclosure Gulmohar - Sept 24.pdf31 Jan 2025
Disclosure of sold/ booked inventoryFile: RERA Disclosure - Gulmohar CHSL - December 2024.pdf31 Jan 2025
CERSAI detailsFile: Declaration CERSAI for Gulmohar CHSL.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Gulmohar FY 21-22.pdf31 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclousure of Interest in other RERA - Ajit Bhosale.pdf31 Jan 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclousure of Interest in other RERA - Sanjay Bhosale.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - Gulmohar FY 22-23.pdf31 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Gulmohar FY 23-24.pdf31 Jan 2025
Declaration in FORM BFile: Affidevit Cum Declaration - Form B - Gulmohar_compressed.pdf6 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gulmohar Form-1 March24.pdf6 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gulmohar Form-1 June-24.pdf6 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GulmoharForm-1 Sept24.pdf6 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Gulmohar Sept-24.pdf6 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Gulmohar March-24.pdf6 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Gulmohar June-24.pdf6 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Gulmohar Form2A Year 21-22.pdf6 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Gulmohar Form2A Year 22-23.pdf6 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Gulmohar Form 2A year 23-24.pdf6 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked inventory_compressed.pdf12 Jun 2024
Disclosure of sold/ booked inventoryFile: Discloure of Sold - June_compressed.pdf6 Apr 2024
Disclosure of sold/ booked inventoryFile: Discloure of Sold - Sept_compressed.pdf6 Apr 2024
Disclosure of sold/ booked inventoryFile: Discloure of Sold - Dec - Gulmohar compressed.pdf6 Apr 2024
Proforma of Agreement for saleFile: APF - DRAFT Gulmohar.pdf6 Apr 2024
Proforma of Allotment letterFile: Allotment As per Rera - Gulmohar.pdf6 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form-1 Gulmohar.pdf22 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 18122023 Gulmohar Engineers Certificate.pdf22 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Gulmohar CC 25-03-2023.pdf24 Mar 2023
Declaration about Commencement CertificateFile: Declaration for CC- Gulmohar.pdf24 Mar 2023
Building plan approvalFile: IOD -07-09-2022.pdf16 Sep 2022
Layout approvalFile: MYSCAN_20220909_0001.pdf16 Sep 2022
Layout approvalFile: MYSCAN_20220909_0002.pdf16 Sep 2022
Layout approvalFile: MYSCAN_20220909_0003.pdf16 Sep 2022
Layout approvalFile: MYSCAN_20220909_0004.pdf16 Sep 2022
Layout approvalFile: MYSCAN_20220909_0005.pdf16 Sep 2022
Layout approvalFile: MYSCAN_20220909_0006.pdf16 Sep 2022

How this compares with Mumbai Suburban

85%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SIDDHARTH NAGAR GULMOHAR CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Goregaon west6,700+ in Mumbai Suburban

2 kmSIDDHARTH NAGAR GULMOHARCompleted 136Lapsed / revoked 62Other 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 336 registered projects within 2 km.

Builder: SHIVAM PARIVAR DEVELOPERS PVT LTD

SHIVAM PARIVAR DEVELOPERS PVT LTD has 5 registrations on MahaRERA, including SIDDHARTH NAGAR GULMOHAR CHS LTD and NIRLON EMPLOYEES COOPERATIVE HOUSING SOCIETY LIMITED BUILDING NO 11, 12 ,13. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SIDDHARTH NAGAR GULMOHAR CHS LTD is delayed beyond 30 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SIDDHARTH NAGAR GULMOHAR CHS LTD?

The registered promoter entity is SHIVAM PARIVAR DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SIDDHARTH NAGAR GULMOHAR CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SIDDHARTH NAGAR GULMOHAR CHS LTD?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SIDDHARTH NAGAR GULMOHAR CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SIDDHARTH NAGAR GULMOHAR CHS LTD?

The professionals named in the filing: Architect: Space Moulders; Engineer: Vaijnath Nachankar; Chartered Accountant: Shripati Gandhi Choudhari and Co; Chartered Accountant: Rahul Bera. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SIDDHARTH NAGAR GULMOHAR CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SIDDHARTH NAGAR GULMOHAR CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SIDDHARTH NAGAR GULMOHAR CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.